DECISIONS 1. That approval be granted for additional expenditure of £13,216, as identified in the report of the Cabinet Executive, as a consequence of the early withdrawal of central Government funding. 2. That provision of this funding from the General Reserve Fund be approved. Reason: To enable the Council to withdraw from its contractual commitments in accordance with the Agreement and the negotiated arrangements with SLM.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1This report is to advise members of actions taken to vary the contract to terminate the Free Swimming programme with effect from the 30 September 2010 and to seek the necessary finance available.
Recommendations
2.1Approval is given to the additional expenditure of £13,216 identified in the report as a consequence of the early withdrawal of central government funding.
2.2Approval is given to this funding being provided from the General Reserve Fund
3. Reason for Decisions Recommended
3.1To enable the Council to withdraw from its contractual commitments in accordance with the Agreement and the negotiated arrangements with SLM.
4. Forward Plan
4.1Forward Plan Reference Number: 07/10(013).
5. Key Decision
5.1Yes.
6. Matters for Consideration
6.1The Government offered Councils funding for a Free Swimming Programme for 16’s and under and 60’s and over which started in April 2009. 6.2 This Council decided to participate in this programme for both the under 16s and the over 60s and the arrangement negotiated with SLM was incorporated into the Management Agreement by Deed of Variation. This programme has been particularly beneficial in this District with 61,432 people participating from the scheme commencing up to 31 July 2010. In addition, by participating we were able to access capital funding of £200,000 in the last financial year which was used to improve pool heating with the installation of a combined heat and power gas plant which will improve customer experience, reduce running costs and reduce environmental impact.
6.3This Programme was incorporated into the Management Agreement between the Council and SLM for the running of Enderby Leisure Centre. Clause 9.8 of the agreement stated that the programme would continue until March 2011 and specified the sum that SLM would receive. This sum was financed directly from the central government funding for the programme.
6.4The Secretary of State for Culture, Olympics, Media and Sport, on behalf of the five funding Departments, announced on 17 June that the resource funding for the Government’s Free Swimming Programme would cease on 31 July 2010. On 6 July a letter was received confirming the reduced budget allocation. Negotiations have been undertaken with SLM with a view to agreeing the early termination of the contractual arrangement and as a consequence I have served notice (as the Authorised Officer for the contract) on SLM.
6.5Under the terms of the notice;
1. The current Free Swimming Programme will continue until 30 Sept 2010 and SLM will receive payment pro-rata until that date.
2. SLM will also continue the course of free swimming lessons for the 1400 children currently enrolled for the remainder of the 50 week course, and whilst the course is running will also allow those enrolled to swim for free at public sessions of the pool.
3. Two specially designated sessions will be available during the week at which those aged over 60 can swim for free.
4. The arrangements set out in 2 and 3 above will be reviewed in December 2010.
6.6The early termination of the Government funding will leave the Council having to fund two months of the Free Swim Programme in 1 above, for which no budget currently exists. Items 2 and 3 above will be provided by SLM at no cost to the Council.
7. Other Relevant Considerations
7.1Human Rights Act 1998 Human rights have been considered but there are no overarching matters for concern in relation to this report.
7.2Legal Implications The actions set out in this report enable the Council to comply with its legal obligations.
7.3Human Resources Implications There are no human resources implications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.