DECISIONS 1. That the Local Development Framework (LDF) Annual Monitoring Report 2009/2010, attached to the report of the Planning Policy Manager as Appendix 1, be submitted to the Secretary of State. 2. That the Planning Policy Manager be authorised to add further information concerning policy monitoring to the Annual Monitoring Report 2009/2010 prior to its submission to the Secretary of State. Reasons: 1. The Local Development Framework Annual Monitoring Report must be submitted to the Secretary of State by 31 December 2010 in order to meet the requirements of The Town and Country Planning (Local Development) (England) Regulations 2004. 2. The Annual Monitoring Report is not yet complete, however, there is an opportunity between the meeting of Cabinet Executive on 6 December 2010 and the closing date for the submission of the Annual Monitoring Report to include additional monitoring information.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Appendix A: Local Development Scheme Programme Timetable (May 2007) Appendix B: Schedule of Saved Policies contained in the Blaby District Local Plan (Adopted September 1999)
Tables
Table 1: Housing core indicators Table 2: Business development/employment core indicators Table 3: Transport and accessibility core indicators Table 4: Local services core indicators Table 5: Flood protection and water quality core indicator Table 6: Renewable energy core indicator Table 7: Gypsy and Travellers
1. Executive Summary Annual Monitoring Report 2 December 2010 1.1 This Annual Monitoring Report has been produced by Blaby District Council under the Planning and Compulsory Purchase Act 2004. The document contains information on progress towards the milestones set out in the revised Local Development Scheme, May 2007, (LDS) and for the current monitoring framework.
Local Development Scheme:
1.2The LDS in place for the monitoring year (2009/10) was the Council’s second LDS, which was bought into effect on 31st May 2007.
1.3The first milestone identified in the revised LDS is commencement of the preparation of the Core Strategy. This took place in July 2007.
Policy Implementation:
1.4A brief summary is provided below of the key findings from the core indicators for 2009/10;
Housing:
• Past and projected housing completion rates are currently below the requirement in the East Midlands Regional Plan (2006 - 2026) to deliver 7,600 dwellings by 2026 District-wide.
• 76% of 180 dwellings completed in 2009/10 were built on previously developed land (as defined in PPS 3 at 31st March 2010).
• 0% of all new dwelling completions on large sites (10 or more dwellings) were completed at less than 30 dwellings per hectare. 69% of all new dwelling completions on large sites were completed at between 30 and 50 dwellings per hectare. 31% of all new dwelling completions on large sites were completed at above 50 dwellings per hectare.
• 37 affordable homes were completed in the District in 2009/10.
Business Development/ Employment:
• A total of 4,103m2 of employment floorspace was developed in 2009/10; 2,410m2 of this was in employment areas.
• 2,557m2 of employment floorspace (62%) was developed on previously developed land.
• A total of 25.67ha of land is defined as available for employment use in the District of Blaby. This is shown below according to land that has been allocated in the Local Plan and land with planning permission;
Annual Monitoring Report 3 December 2010 Allocated: – 15.58ha Planning Permission:- B1: 0.38ha B1(a): 5.44ha, B1(b): 0ha, B1(c): 0ha, B2: 0.39ha, B8: 0ha, Mixed (more than just one use class): 4.27ha
• There were no employment land losses in 2009/10.
Transport and Accessibility;
• 7 out of a total of 7 (100%) non-residential completions complied with Blaby District Local Plan car parking standards.
• 100% of all residential completions were within 30 minutes public transport time of a GP, primary school, employment area and retail area; 99% of all residential completions were within 30 minutes public transport of a secondary school; and 85% of all residential completions were within 30 minutes public transport time of a hospital.
Local Services;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.