DECISIONS 1. That the report be noted. 2. That the additional capital expenditure of £99,576 as highlighted in the report is formally authorised for inclusion in the Capital Programme. Reasons: 1. It is important that the Cabinet Executive is kept informed of progress in meeting the Council’s capital investment programme for the financial year. 2. To ensure that any additions to the overall Capital Programme are formally approved by full Council in line with constitutional requirements.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Progress against the 2014/15 Capital Programme was last reported to Cabinet Executive on 3rd November 2014. It was noted then that at 30th September 2014 the Council’s forecast capital expenditure for 2014/15 amounted to £5.25m. Since then there have been a number of further schemes added leading to an increased Capital Programme total of £5.48m. 4.2 The following schemes have been added to the Capital Programme:
Refurbishment of Enderby Road Industrial Estate Units – funded £85,000 by way of a contribution from the General Reserve Fund
Depot Relocation – transfer of unused revenue budget in respect of £45,916 feasibility study
Increase in the Disabled Facilities Grants budget – funded by £37,936 contributions from East Midlands Homes
Play equipment, Oakfield Park, Blaby – funded by a S106 £56,640 contribution
Contribution to Blaby CCTV scheme – funded by revenue £5,000 contribution £230,492
The project for refurbishment of industrial estate units was reported to Council last July and has already been formally approved. This work is well underway and will enable the Council to generate additional rent income once the units are re-let.
Council has previously approved the sum of £80,000 to fund a feasibility study into the proposal to relocate the depot. Upon completion of the feasibility study £45,916 of this budget provision was left unspent. This has been used to supplement the Capital Programme as a contribution towards the design and build costs.
The remaining balance from the table above, £99,576, will require the formal approval of full Council in order for it to be included within the Capital Programme. All of this expenditure can be financed without any impact on General Fund Balances.
4.3Appendix A provides a detailed breakdown, scheme by scheme, of actual expenditure against the Capital Programme for the period 1st April 2014 to 31st December 2014. As at 31st December a total of £1,257,299 had been spent against the budget of £5,481,969, a variance of £4,224,670.
The main variances are:
New Depot Site, Whetstone (£2,449,787) – the majority of the work undertaken to date relates to design, site surveys, and value engineering to assess the potential build costs. The Council has signed a pre- construction contract with Wates which commits us to £32,000 for work they have done on surveys and associated activity. There will be no significant construction costs until the new financial year, once the planning application has been considered on 5th March 2015. If successful the intention would then be to complete the lease of land from Leicestershire County Council. Pavilion Refurbishment Programme (£363,000) – the business plan was approved by Council in September 2014, and only limited expenditure had been incurred by 31st December. However, at that date contractual commitments amounted to almost £277,000. Building work is currently ahead of schedule and the project is expected to come in on budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.