Treasury Management Mid Year Monitoring Report 2015/16

Approved Executive 2 papers

Cabinet Executive approved this item on Monday 16 November 2015. Below is the council's own wording, with the papers it was decided on.

Item186

Resolved

DECISION That the report be accepted. Reason: 1. The regulatory framework governing treasury management activities includes a requirement that the Council should, as a minimum, receive a mid year treasury monitoring report in addition to the forward looking annual treasury strategy and the backward looking annual treasury report. 2. This report fulfils the requirement above and incorporates the needs of the Prudential Code to ensure adequate monitoring of capital expenditure plans and the Council’s prudential indicators. The treasury strategy and prudential indicators for 2015/16 were contained in the report approved by Council on 19 February 2015.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

APPENDIX A

PRUDENTIAL INDICATORS

1. Capital Expenditure and Financing

This indicator shows the capital expenditure plans for the year and demonstrates how those plans are expected to be financed. 2015/16 Position as at 2015/16 th Approved 30 September Revised Budget 2015 Estimate £ £ £ Capital Expenditure S106-backed schemes 0 21,420 1,176,315 Other schemes 3,241,000 673,144 6,529,047 Total Capital Programme 3,241,000 694,564 7,705,362 Financed by: Capital receipts 1,275,500 220,782 2,583,443 Capital grants and contributions 193,000 236,365 1,515,405 Capital reserves 0 88,261 135,208 Revenue contributions 0 49,494 295,685 Total Financing 1,468,500 594,902 4,529,741 Borrowing Requirement 1,772,500 99,662 3,175,621

The Revised Capital Programme includes expenditure and resources brought forward from 2014/15 totalling £3,488,810.

2. Capital Financing Requirement

The Capital Financing Requirement (CFR) is a measure of the Council’s underlying need to borrow for capital purposes. It will increase as the Council incurs capital expenditure which cannot be met from other resources, but this will be partially offset by revenue repayments for the year (the Minimum Revenue Provision).

2015/16 Position as at 2015/16 th Approved 30 September Revised Budget 2015 Estimate £ £ £ st CFR as at 1 April 2015 8,424,021 7,003,317 7,003,317 Capital Expenditure in Year 3,241,000 694,564 7,705,362 Financing in Year (1,468,500) (594,902) (4,529,741) Minimum Revenue Provision (668,639) (309,247) (618,494) st CFR as at 31 March 2015 9,527,882 6,793,732 9,560,444 APPENDIX A

3. The Portfolio Position

The table below compares the Council’s actual external debt, including other long term liabilities such as finance leases, with the CFR. This indicator also acts as a limit to borrowing activity. Gross external debt should not, except in the short term, exceed the total of CFR in the preceding year plus the estimated additional CFR for 2015/16 and the next two financial years. This allows some limited flexibility for borrowing in advance of need. No difficulties are envisaged in complying with this indicator for the current or future financial years.

2015/16 Position as at 2015/16 th Approved 30 September Revised Budget 2015 Estimate £ £ £ External Debt st Debt at 1 April 2015 5,871,137 3,871,137 3,871,137 st Finance Leases at 1 April 2015 456,577 456,577 456,577 Estimated Borrowing 2015/16 2,500,000 0 0 Estimated Repayments 2015/16 (1,518,940) (213,846) (1,430,283) st Estimated Debt at 31 March 2016 7,308,774 4,113,868 2,897,431 CFR (as above) 9,527,882 6,793,732 9,560,444 Under/(Over) Borrowing 2,219,108 2,679,864 6,663,013

4. Operational Boundary for External Debt

This is the limit which external debt is not normally expected to exceed. In most cases this would be a similar figure to the CFR, but may be lower or higher depending on the levels of actual debt.

2015/16 Position as at 2015/16 th Approved 30 September Revised Budget 2015 Estimate £ £ £ Borrowing 9,112,500 3,657,415 9,112,500 Other Long Term Liabilities 517,500 456,453 517,500 Total 9,630,000 4,113,868 9,630,000

5. Authorised Limit for External Debt

A further key prudential indicator represents a control on the maximum level of borrowing. This is the limit beyond which external debt is prohibited. It reflects the level of external debt which, while not desired, could be afforded in the short term, but is not sustainable in the longer term.

2015/16 Position as at 2015/16 th Approved 30 September Revised Budget 2015 Estimate £ £ £ Borrowing 10,125,000 3,657,415 10,125,000 Other Long Term Liabilities 575,000 456,453 575,000 Total 10,700,000 4,113,868 10,700,000 APPENDIX A

6. Treasury Management Limits on Activity

There are three debt related treasury activity limits. The purpose of these is to manage risk and reduce the impact of any adverse movement in interest rates. However, if these are too restrictive they will impair the opportunities to reduce costs and/or improve performance. The indicators are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A: Treasury Management Mid Year Monitoring Report 2015-16Report 118 KB DownloadRead as text
PDF
Treasury Management Mid Year Monitoring Report 2015/16Report 169 KB Download

At this meeting

Whole meeting

Who was there

7 of 20 attended
TR
Councillor Terry RichardsonLeader, present
MW
Councillor Maggie WrightDeputy Leader, present
DF
Councillor David FreerMember, present
TG
Councillor Tony Greenwood MBEMember, present
GJ
Councillor Guy JacksonMember, present
SS
Councillor Sheila ScottMember, present
DC
Councillor David ClementsMember, present
MA
Mr Mark AlflatOfficer, in attendance
JT
Mrs Jane TomanOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
MF
Mark FooteOfficer, in attendance
NB
Nick BrownOfficer, in attendance

All 20 on the meeting page

On this subject at Blaby

Search all
  1. Treasury Management Mid Year Monitoring Report 2015/16This decision
  2. Quarter 1 Treasury Management Update 2026-27Approved
  3. Treasury Management Outturn 2025/26Approved
  4. Quarter 3 Treasury Management Update 2025/26Approved
  5. Prudential Indicator & Treasury Management Strategy 2026/27Approved
  6. Quarter 1 Treasury Management Update 2025/26Decided

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open