DECISIONS 1. That the proposed Capital Programme for 2016/17 be approved. 2. That the application of capital resources of £3,182,055, including a borrowing requirement £822,055, be approved. Reasons: To obtain approval for the proposed level of capital expenditure in 2016/17, and how it is proposed this expenditure should be financed.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
As part of the budget process officers are asked to put forward requests for funding of capital expenditure. In each case the request has to be supported with information illustrating that the expenditure is needed because:
It meets corporate and service priorities or It supports the delivery of a statutory service, or is a result of a contractual or a legal obligation or It will generate more income and/or provide better facilities
All of the requests put forward are considered by the Asset Management Group (AMG), which is an officer group that monitors progress against the Capital Programme throughout the year.
Capital expenditure may be funded through borrowing, capital receipts (money the Council has received from the sale of capital assets), external grants or from revenue contributions and reserves.
Where borrowing is used there is a cost for interest and also a charge known as the Minimum Revenue Provision (MRP) where the Council is required to set aside an amount based on the size of the borrowing and the lifetime of the asset purchased. Interest and MRP costs are included in the Council’s General Fund revenue budget.
4.2Proposal(s)
The total proposed Capital Programme for 2016/17 amounts to £3,182,055. Further details, on a scheme by scheme basis, are shown in Appendix A.
Relocation of the Depot
At its meeting of 3rd November 2015, Council approved the investment of a further £1,110,000 for the construction of a new depot at Whetstone. This brought the total planned expenditure to £6.110m, which is to be funded as follows:
£3m from existing capital receipts; £1.5m from the disposal of the current depot site; £1.5m from borrowing; £110,000 from revenue reserves.
£2m expenditure, all funded through capital receipts, has been included within the 2016/17 Capital Programme, although it is likely that a further £1.5m will be carried forward from 2015/16 in line with the expected work schedule.
Fleet Replacement Programme
The proposed Capital Programme includes £320,000 on the replacement of fleet vehicles. The Fleet Manager assesses the need for replacement vehicles on a case by case basis, and has been able to extend the useful life of the fleet through careful maintenance.
Disabled Facilities Grants
An amount of £450,000 has been included in the programme to provide disabled facilities grants, of which £200,000 is to be funded through borrowing. The remaining £250,000 is the amount which is estimated to be received in government grant through the Better Care Fund. Final allocations have not yet been announced, and the overall programme may need to be increased or decreased once the final settlement is known.
Replacement of Back Office Systems
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.