DECISION That the financial performance for 2017/18, including the impact on reserves and balances at 31st March 2018, be approved. Reasons: 1. The Council’s unaudited accounts were published on 31st May 2018, in line with the requirements of the Accounts and Audit Regulations 2015. 2. The audit of accounts commenced on 4th June and is now substantially complete. At the time of writing details of any amendments to the accounts, arising from the audit process, have not been finalised. However, any matters which might affect the outturn figures contained in this report will be the subject of a verbal update at the meeting.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Date of Meeting 9 July 2018 Title of Report Financial Performance 2017/18 This is not a Key Decision and is on the Forward Plan Lead Member Cllr. Maggie Wright - Finance & Assets (Deputy Leader) Report Author Finance Strategic Manager
1. What is this report about?
1.1The report sets out details of the Council’s financial performance against the General Fund revenue budget, Business Rates Retention, and the Capital Programme in respect of the financial year ended 31st March 2018.
2. Recommendation(s) to Cabinet Executive
2.1That the financial performance for 2017/18, including the impact on reserves and balances at 31st March 2018, is approved.
3. Reason for Decisions Recommended
3.1The Council’s unaudited accounts were published on 31st May 2018, in line with the requirements of the Accounts and Audit Regulations 2015.
3.2The audit of accounts commenced on 4th June and is now substantially complete. At the time of writing details of any amendments to the accounts, arising from the audit process, have not been finalised. However, any matters which might affect the outturn figures contained in this report will be the subject of a verbal update at the meeting.
4. Matters to consider
4.1General Fund Revenue Account
Performance against the Budget
The Council’s net expenditure for 2017/18 is summarised by Portfolio at Appendix A.
The Revised Budget allowed for a contribution from balances of £240,241 but ultimately a surplus of £270,598 has been achieved, representing a positive variance of £510,839 for 2017/18. Members will recall that, whilst not formally reflected in the budget, the Quarter 3 Monitoring Report in January 2018 forecast a surplus of £161,000. This means that we have exceeded that forecast by a further £109,000 in actual terms.
Major Variances
The table at Appendix B highlights the major variances, some of the more significant of which are detailed below.
Increased Income DEFRA awarded us two grants to support work to improve air quality in the district. These totalled £109,000 but were not received until April so have been carried forward to 2018/19.
As shown in the key income streams table below, Refuse and Recycling income exceeded the budget by £77,478, due largely to garden bin rentals.
We received some large S106 monitoring contributions in respect of Lubbesthorpe and Everards Brewery, meaning that we exceeded our budget by almost £86,000.
Reduced Expenditure/Use of reserves The establishment budget was underspent by £342,280, up from the £297,000 at the end of December, as reported in the Quarter 3 Monitoring Report. This variance is largely a result of vacant posts, some of which have now been filled. The budget incorporated provision for expenditure connected with the local plan, partly externally funded and including inspection fees, various studies and assessments, the timing of which is not precise. The underspend amounted to £256,374 and this has been carried forward to 2018/19 to allow for completion. Revenue contributions to capital expenditure of £432,243 were not required due to slippage in the Capital Programme. The most significant element of this relates to a contribution from the Special Schemes Reserve towards the Council Offices refurbishment project.
The impact of the surplus of £270,598 is that the General Fund balance stands at £3,165,454 at 31st March 2018. The Council’s policy is to maintain the General Fund balance within a range of 10% and 30% of the net budget requirement. Following the transfer referred to above, the General Fund balance stands at 27.8%, such that balances remain within the expected range. Key Income Streams
The following table provides an analysis of the performance of the Council’s key income streams during the year:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.