Resolved

DECISION THAT APPLICATION 21/1386/FUL BE APPROVED SUBJECT TO THE IMPOSITION OF THE FOLLOWING CONDITIONS: 1. Statutory 3 year condition. 2. Development to be built in accordance with approved plans and documents. 3. Permission granted for a period of 40 years from first export of electricity and site decommissioned and restored after this period. 4. Decommissioning Scheme to be submitted and approved no later than 39 years from the date of the first export of electricity and implemented as approved. 5. In the event of site is no longer required for purposes of electricity generation or ceases to operate for a continuous period of 12 months prior to the expiry of the 40 year period; a Decommissioning Scheme shall be submitted and approved. 6. Programme of archaeological work to be completed to include initial trial trenching to inform a final archaeological mitigation scheme. 7. Development to be carried out in accordance with the details given on the Landscape and Ecological Management Plan (LEMP) by Amalgam Architects. Plan to be adhered to for the lifetime of the development. 8. Detailed scheme for landscaping the site to be submitted and approved and implemented in accordance with plan. 9. Landscaping to be implemented by end of first planting season following commencement of development. 10. Biodiversity Management Plan to be submitted and approved. Strategy to be based on submitted Biodiversity Net Gain metric and LEMP and adhered to for lifetime of the development. 11. Arboricultural Method statement to be submitted and approved and adhered to during construction and decommissioning periods. 12. Details of any external lighting to be submitted and approved prior to its installation. 13. Construction Environmental Management Plan to be submitted and agreed and subsequently adhered to. 14. Methodology for soil stripping, storage and replacement to be submitted and agreed. 15. Method of construction of the solar panels to be in strict accordance with the submitted details showing the “post-driven” method only and not concrete foundations method. 16. Materials and finish, including colour, of ancillary buildings equipment and all enclosures/fencing to be submitted and agreed and subsequently complied with. 17. Details of surface water drainage to be submitted and approved. 18. Details of management of surface water during construction to be submitted and approved. 19. Details of long-term maintenance of surface water drainage system to be submitted and approved. 20. Details of infiltration testing confirming suitability of site for use of infiltration drainage to be ... view the full minutes text for item 48.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Planning Committee

Recommendation

2.1That the recommendations listed within paragraph 3.2 below and detailed in the attached report be approved.

3. Matters to consider

3.1To avoid unnecessary delay in the processing of planning applications, the recommendations included in this list must often be prepared in advance of the closing date for the receipt of representations. This list was prepared on 20 June 2023 and information of representations received will be updated at your meeting. This updating will also cover any other information which may come to hand in the intervening period. Closing dates are given where they fall on or after the day of preparation of the list.

3.2Application No. Page Address Recommendation No. 21/1386/FUL 13 Land at Hill Farm, Approve Earl Shilton Road, Thurlaston

19/1610/OUT 49 Land North of Hinckley Approve Road, Kirby Muxloe

22/0827/RM 158 Tay Road, Approve Lubbesthorpe

3.3Appropriate Consultations

Details of organisations / persons consulted in relation to the applications are included in the reports for each individual application. Members will be aware that full copies of correspondence received are available to view on the respective planning file and through the planning portal https://w3.blaby.gov.uk/online-applications/ 3.4 Resource Implications

There are no specific financial implications arising from the contents of this report.

4. Other options considered

These are included where appropriate as part of the reports relating to each individual application.

5. Background paper(s)

Background papers are contained in files held in the Planning Division for each application being considered and are available for public inspection.

6. Report author’s contact details Ian Davies and Stephen Dukes Development Services Team Leaders [email protected] 0116 272 7705 21/1386/FUL Registered Date Hill Farm Solar Ltd 22 March 2018

Construction of a 36.1 hectare solar park to include the installation of solar photovoltaic panels to generate electricity (up to 22MW) with associated substations, transformers, inverters, perimeter fencing, access tracks, CCTV and landscaping.

Land at Hill Farm, Earl Shilton Road, Thurlaston, LE9 7TG

Report Author: Helen Wallis, Senior Planning Officer

Contact Details: Council Offices. 0116 272 7698

THAT APPLICATION 21/1386/FUL BE APPROVED SUBJECT TO THE IMPOSITION OF THE FOLLOWING CONDITIONS:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Applications for DeterminationReport 1.6 MB DownloadRead as text
PDF
Officers PresentationReport 9 MB Download

At this meeting

Whole meeting
47MinutesOn the agenda
48Applications for DeterminationThis decision

Who was there

9 of 21 attended
LB
Councillor Lee Breckon JPChairman, present
MS
Councillor Mike ShirleyVice-Chair, present
CC
Councillor Cheryl CashmoreMember, apologies
TD
Councillor Tony DeakinMember, apologies
RH
Councillor Richard HoldridgeMember, apologies
DS
Councillor Dillan ShikotraMember, present
BW
Councillor Bob WatertonMember, present
BW
Councillor Bev WelshMember, present
NW
Councillor Neil WrightMember, apologies
JF
Councillor Janet ForeySubstitute, present
HG
Councillor Helen GambardellaSubstitute, present
RS
Councillor Roger SteadSubstitute, present

All 21 on the meeting page

On this subject at Blaby

Search all
  1. Applications for DeterminationThis decision
  2. Applications for DeterminationApproved
  3. Applications for DeterminationApproved
  4. Applications for DeterminationApproved
  5. Applications for DeterminationRefused
  6. Applications for DeterminationApproved

More from Blaby Planning Committee

All decisions
MeetingDecisionOutcome
30 Apr 2026 25-0532-FUL - Land to the West of Springwell Lane, WhetstoneDECISION THAT APPLICATION 25-0532-FUL BE DEFERRED ON THE GROUNDS OF PROXIMITY CONCERNS OF PLOTS 24, 25 AND 32 TO NO. ... Deferred Open
30 Apr 2026 24-0957-FUL - Land off Butler Close, SharnfordDECISION That the application be approved, subject to the applicant entering into a Section 106 agreement to secure t... Approved Open
30 Apr 2026 25-0942-VAR - 5 And 7 Groby Road, GlenfieldDECISION That the application be approved in line with conditions and reasons outlined in the report and subject to a... Approved Open
30 Apr 2026 25-0785-FUL - Whiteacres, WhetstoneDECISION That the application be approved in line with conditions reasons outlined in the report, and the applicant e... Approved Open
12 Mar 2026 Applications for DeterminationDECISION That Application 24/0869/FUL be approved subject to the applicant entering into a section 106 agreement to s... Approved Open