IFRS 16 Leasing Policy

Approved Executive 2 papers

Cabinet Executive approved this item on Monday 24 June 2024. Below is the council's own wording, with the papers it was decided on.

Item31

Resolved

DECISION That the leasing policy at Appendix A is approved. Reason: To ensure that the Council only enters a lease arrangement where it offers best value for money, and after having fully explored all alternative procurement options.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Blaby District Council Cabinet Executive

Date of Meeting 24 June 2024 Title of Report IFRS 16 Leasing Policy This is not a Key Decision and is on the Forward Plan Lead Member Cllr. Maggie Wright - Finance, People & Performance (Deputy Leader) Report Author Finance Group Manager Strategic Themes Ambitious and well managed Council, valuing our people

1. What is this report about?

1.1The report seeks approval of a new policy covering lease arrangements, following the introduction of a new accounting standard, IFRS 16, effective from 1st April 2024.

2. Recommendation(s) to Cabinet Executive

2.1That the leasing policy at Appendix A is approved.

3. Reason for Decisions Recommended

3.1To ensure that the Council only enters a lease arrangement where it offers best value for money, and after having fully explored all alternative procurement options.

4. Matters to consider

4.1Background From 1st April 2024, a new International Financial Reporting Standard, IFRS 16, came into effect for Local Authorities. IFRS 16 introduces a new ‘Right of Use’ asset class to the balance sheet from 2024/25 onwards and recognises the corresponding lease liability. This applies to all leases - property, land, vehicles, plant, and equipment.

IFRS 16 was primarily intended to bring more transparency to leases in companies’ financial statements. By reducing the number of leases that are off balance sheet and allowing users of financial statements to make more informed comparisons between companies in particular sectors, this should lead to greater transparency. However, despite not having the same comparative and investment requirements as the private sector, IFRS 16 has also been rolled out to the public sector. This means that whilst finance leases are already accounted for as an asset and corresponding lease liability, from 1st April 2024 any operating leasing commitments must also be accounted for on the balance sheet (aside from some exemptions). Most existing operating leases will come on to the balance sheet.

Any new and existing operating leases now create a new debt in the Council’s accounts over the life of the lease. This has financial implications for the Council’s Treasury Management Strategy, its Capital Programme, and its Financial Statements. Under IFRS 16, all leases are now classified as capital expenditure, and must be included in the Capital Programme (requiring either Full Council or a delegated approval).

The standard also considers 'Embedded Leases' which exist if there is an explicit or implicit asset identified in the contract and the customer controls the use of the asset, to continue the service. An example of this is where an authority contracts out its refuse service, but the vehicle used by the contractor bear the authority’s livery.

IFRS 16 only covers leases where the Council is the lessee, not those where we lease assets to other parties.

4.2Proposal(s)

When a lease contract is signed, this commits the Council to a debt liability in exchange for the control of an asset for a fixed period. It is, therefore, important that the correct ‘value for money’ procedures are undertaken, and the correct approvals are in place for the value of the lease agreement.

Under the new standard a lease will require a budget in the Capital Programme for the total value of the leased asset and, therefore, contracts previously paid through revenue will now need to be included in the Capital Programme at their total cost over the life of the scheme and funded through the creation of a debt, which is equivalent to the total lease liability.

This is a significant change to the current approach, and it may be that the Council has some lease agreements that have not had such an approval in place in the past. This is a fairly low risk, but it may be that these agreements have not been correctly assessed for cost and perhaps do not represent the best value for money to the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lease PolicyAppendix A 198 KB Download
PDF
IFRS 16 Leasing PolicyReport 129 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 18 attended
TR
Councillor Terry RichardsonLeader, present
MW
Councillor Maggie WrightDeputy Leader, present
CC
Councillor Cheryl CashmoreMember, apologies
NG
Councillor Nigel GrundyMember, present
LP
Councillor Les PhillimoreMember, present
BT
Councillor Ben TaylorMember, present
JS
Julia SmithOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
LH
Louisa HortonOfficer, in attendance
MG
Marc GreenwoodOfficer, in attendance
CH
Caroline HarbourOfficer, in attendance
GM
Gary MorrisOfficer, in attendance

All 18 on the meeting page

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies