CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blackburn with Darwen Borough Council
Executive Board, Thursday 14 February 2019 at 6.00pm

Capital Budget Monitoring: Quarter 3

Approved Executive 3 papers

Executive Board approved this item on Thursday 14 February 2019. Below is the council's own wording, with the papers it was decided on.

Item8.3

Resolved

The Executive Board is asked; · to approve the revised capital programme as per Appendix 1, · to approve the variations to the programme shown in Appendix 2
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

EXECUTIVE BOARD DECISION REPORT OF: Executive Member for Resources

LEAD OFFICERS: Director of Finance and Customer Services

DATE: 14th February 2019

PORTFOLIO/S All AFFECTED:

WARD/S AFFECTED: All

KEY DECISION: YES NO

SUBJECT: CORPORATE CAPITAL BUDGET AND BALANCE SHEET MONITORING REPORT 2018/19 – Quarter 3 (9 months to 31st December 2018)

1. EXECUTIVE SUMMARY To report the overall financial position of the Council in respect of the capital programme as at 31st December 2018, highlighting key issues and explaining variations in the first 9 months of the financial year.

2. RECOMMENDATIONS The Executive Board is asked;  to approve the revised capital programme as per Appendix 1,  to approve the variations to the programme shown in Appendix 2

3. BACKGROUND All portfolios are required to examine their capital budget position on a monthly basis.

4. KEY ISSUES & RISKS a) The projected aggregate cost of the Council’s capital investment programme for 2018/19 has now decreased from £33.578 million, as approved by Executive Board on 8th November 2018, to £28.656 million. The net variation of £4.922 million (detailed in Appendix 2) reflects;  variations made to reflect the approval of programmes during the third quarter of the year of £65,000.  slippage and re-profiling of budgets during the third quarter of the year (£4.987 million).

b) As at 31st December 2018, the capital expenditure across the portfolios was £12.398 million (43.3% of the current, revised projected spend).

c) The estimate of capital receipts expected in 2018/19 is £2.3 million; to date £1.291 million has been received.

5. POLICY IMPLICATIONS The information contained within the report accords with the capital strategy and the three year budget forecast within the Medium Term Financial Strategy 2018-21, as approved at Finance Council on 26th February 2018.

EBD: V1/16 Page 1 of 8 6. FINANCIAL IMPLICATIONS

6.1CAPITAL PROGRAMME The variations in projected spend and resource availability for 2018/19 are summarised by portfolio in Appendix 1. Variations in spending are set out in Appendix 2.

The capital programme for 2018/19 has decreased by £4.922 million in the third quarter of the year, with the major capital variations to note as follows:

6.1.1 New Approved Capital Schemes

The following capital schemes have been approved and are now added to the capital programme:

Portfolio Scheme Amount Approved by Date Approved Leisure & Culture Witton Park Arena – Car £40,000 Executive Member September 2018 Park lighting Resources Regeneration Pottery Farm Flood £10,000 Grant Application - 11.1.19 Alleviation Scheme Director Of Environment & Operations Children, Young Feniscowles Disabled £25,000 Senior Policy Team 27.11.18 People and Changing Facilities – Education funded from within the Schools existing capital programme Children, Young Belmont Ramp - funded £10,000 Senior Policy Team 27.11.18 People and from within the Schools Education existing capital programme

6.1.2 Health & Adult Social Care

Adults Disabled Facilities Grant (DFG)

Changes to the Adults Disabled Facilities grant are reported as per the table below:

£’000 Approved Disabled Facilities Grant Scheme as per the November Executive 2,535 Board Report Changes to the scheme: Additional Grant Funding from MHCLG 207 Removal of main programme borrowing budget as this will not be utilised (796) New Scheme total as at 31.12.18 1,946

Riverside Heights Extra Care Scheme A request is made to draw back £80,000 from future years to cover the predicted spend in 2018/19.

6.1.3 Children, Young People & Education

Disabled Facilities Grant As for the Adult’s Disabled Facilities Grant scheme, a reduction of £37,000 is also reported in respect of the Children’s scheme in respect of Main Programme Borrowing that will no longer be required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring: Quarter 3Report 172 KB DownloadRead as text
PDF
Capital Monitoring Appendix 1Appendix 66 KB Download
PDF
Capital Monitoring Appendix 2Appendix 102 KB Download

At this meeting

Whole meeting

Who was there

9 of 16 attended
HC
Harry CatherallOfficer, expected
DP
Denise ParkOfficer, expected
MB
Councillor Maureen Bateson MBECommittee Member, present
SH
Councillor Shaukat HussainCommittee Member, present
AK
Councillor Andy KayCommittee Member, present
MK
Councillor Mohammed KhanCommittee Member, present
PR
Councillor Phil RileyCommittee Member, present
JS
Councillor John SlaterCommittee Member, present
JS
Councillor Jim SmithCommittee Member, present
DT
Councillor Damian TalbotCommittee Member, present
BT
Councillor Brian TaylorCommittee Member, present
JM
Councillor Julie Margaret DaleyCommittee Member, expected

All 16 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Capital Budget Monitoring: Quarter 3This decision
  2. EB Corporate Capital Budget and Balance Sheet 2025/26 – OutturnApproved
  3. EB Corporate Capital Budget Monitoring 2025/26 Quarter 3Approved

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies