EB Corporate Capital Budget Monitoring 2025/26 Quarter 3

Approved Executive 3 papers

AI summaryBlackburn with Darwen Executive Board approves revised 2025/26 capital programme showing a £39.152 million decrease in the third quarter.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVariations to the programme also approved
Money£39.152 million decreaseCapital programme reduced in quarter three
What happens nextSchemes re-profiled to 2026/27Slippage requests approved across portfolios
Who it affectsSchools, roads, town centres, ICTMultiple capital schemes across council portfolios

What was decided

The revised capital programme set out in Appendix 1 was approved. Report P2, P3

The variations to the programme shown in Appendix 2 were approved. Report P2, P3

Why

The Council has a duty to monitor its budgets during the year and act if potential deterioration is identified, under the Local Government Act 2003. Report P82, P83

The Section 151 Officer has confirmed the recommendations do not incur unlawful expenditure and comply with equality legislation. Report P90

What happens next

Schemes not expected to be completed this year will be re-profiled into 2026/27, including school works, road schemes, town centre projects and ICT upgrades. Report P11, P12, P13, P26, P27, P37, P38, P42, P43, P47, P48, P49

Several new scheme budgets will be created using transfers from the Asset Management Strategy budget and other sources. Report P22, P23, P24, P25, P33, P45

The money

  • £39.152 million Decrease in the 2025/26 capital programme in quarter three Report P3
  • £2,624,706 Total of new capital scheme approvals since quarter two Report P7
  • £10,704,600 Total slippage to 2026/27 for Children's, Young People and Education schemes Report P13
  • £500,000 Total slippage to 2026/27 for Environmental Services schemes Report P27
  • £23,693,000 Total slippage to 2026/27 for Growth and Development schemes Report P38
  • £2,276,500 Total slippage to 2026/27 for Digital and Customer Services schemes Report P43
  • £4,313,000 Total slippage to 2026/27 for Earmarked and Contingent Schemes Report P49
  • £3.260 million Actual capital receipts at the end of December 2025 Report 6.2

Options considered

  • Chosen: Approve the revised capital programme and the variations to the programme. Required to reflect the current spending position and re-profile schemes into 2026/27 Report P3, P82
  • Rejected: Not approve the variations

Implications

  • Financial: The 2025/26 capital programme has decreased by £39.152 million in the third quarter. Report P3
  • Financial: Capital receipts of £3.260 million at the end of December 2025 will support the Minimum Revenue Provision. Report 6.2
  • Legal: The report has been prepared in accordance with the Local Government Act 1972 (Section 151) and the Local Government Act 2003, which set the legal framework for capital expenditure. Report P82, P83
  • Equalities: An Equality Impact Assessment checklist has been completed and no EIA is required. Report P86
  • Risk: Any forecast overspends across school schemes will need to be covered by a transfer from the Capital Allocations Fund. Report P18

Who and where

  • Schools and education providers receiving capital investment, including Lower Darwen, Stansfeld Centre, Newfield School, Daisyfield Primary, Griffin, St Thomas CE, Roe Lee and Intack Report P12
  • Residents and businesses in Growth and Development scheme areas, including Bank Top, Griffin, the Cotton Exchange, King George's Hall, Brokenstone Road, North East Blackburn, Darwen Town Centre and Blackburn Town Centre Report P29, P30, P31, P32, P33, P34, P35, P36, P38
  • Users of environmental services schemes including Blakewater Car Park, food waste collection, crematorium and burial space Report P27
  • Users of council ICT and digital services affected by re-profiled schemes Report P41, P42, P43
  • Council tax and business rates payers, as collection rates are reported Report P80, P81

Timeline

  • 2025-10-09: Executive Board approved the budget for developing provision for children with complex needs and the Brokenstone Road Drainage scheme Report P7, P19, P34
  • 2025-11-28: Executive Board Member approved the Better Youth Spaces (YIF) scheme Report P7
  • December 2025: Bank of England base rate reduced by 0.25% to 3.75% Report P58
  • 2025-12-11: Executive Board approved the Arboricultural Maintenance scheme and the £4.5 million budget increase for King George's Hall Report P7, P25, P32
  • 31/12/2025: Capital receipts of £3.260 million recorded; borrowing and investment position reported Report 6.2, P68, P69, P70, P71, P72, P73, P74
  • 2026/27: Schemes not completed in 2025/26 will be re-profiled into this year Report P11, P13, P27, P38, P43, P49

Plain English for the jargon

  • Capital programme: The council's planned spending on long-term assets such as buildings, roads and equipment.
  • Slippage: Spending that is delayed from one year into a later year.
  • S106 monies: Funding from developers provided under Section 106 of the Town and Country Planning Act, used to mitigate the impact of development.
  • MRP: Minimum Revenue Provision, the minimum amount the council must set aside each year to repay debt.
  • PFI: Private Finance Initiative, a way of funding public infrastructure through private sector contracts.
  • IFRS16: The accounting standard for leases, which brought some leases on to the balance sheet.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item169.4

Resolved

RESOLVED (1) That the revised capital programme as set out in Appendix 1 attached to the report be approved. (2) That the variations to the programme shown in Appendix 2 attached to the report be approved.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Financial implications

6.1CAPITAL PROGRAMME

The variations in actual spend and resource availability for 2025/26 are summarised by portfolio in Appendix 1. Variations in spending are set out in Appendix 2.

The capital programme for 2025/26 has decreased by £39.152 million in the third quarter of the year. The main points to note are as follows:

6.1.1 New Approved Capital Schemes

Several capital schemes (new schemes and amendments to existing schemes) have been approved since the Capital Programme was reported at Quarter 2 in November 2025, and have now been added to the current programme as follows:

Table 1: New Scheme approvals Scheme Portfolio Amount Approved By Date £ Approved

Develop provision for children Children’s, Young People & with complex needs and 1,915,406 Executive Board 09/10/25 Education challenging behaviour Children’s, Young People & Executive Board Better Youth Spaces (YIF) 69,300 28/11/25 Education Member Brokenstone Road Drainage Growth & Development 400,000 Executive Board 09/10/25 Environment & Arboricultural Maintenance 240,000 Executive Board 11/12/25 Communities Total 2,624,706

6.1.2 Children’s, Young People & Education

Schools Capital Schemes Unallocated schools capital grant allocations are retained in an overarching Capital Allocations Fund within the capital programme until bids against this have been approved.

EBD: V1/16 Page 2 of 10 Classified as Official\Anyone

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 161 KB Download
PDF
Appendix 2Appendix 2 510 KB Download
PDF
EB Corporate Capital Budget Monitoring 2025/26 Quarter 3Report 201 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
MD
Councillor Mustafa DesaiCommittee Member, apologies
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, present
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, present
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present
PR
Councillor Phil RileyChair, present

All 18 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. EB Corporate Capital Budget Monitoring 2025/26 Quarter 3This decision
  2. EB Corporate Capital Budget and Balance Sheet 2025/26 – OutturnApproved
  3. Corporate Capital Programme and Balance Sheet Monitoring Quarter 3 2024/25Noted

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies