(1) That the list of projects, as detailed in Appendix 2 attached to the report, be approved for inclusion in the 2024/25 Schools and Education Capital Programme funded from the School Condition Allocation and Devolved Formula Capital. (2) That the variations to the 2023/24 Capital Programme for schemes at the following sites be approved: · Newfield School - £650,000 · Shadsworth Junior School - £1,700 · St. Michael with St. John Primary School - £70,000 (3) That delegated authority be granted to the Strategic Director of Children’s and Education in consultation with the Executive Member for Children, Young People and Education to undertake the procurement for the works in accordance with the Contracts and Procurement Procedure Rules in the Council’s Constitution. (4) That subject to (5) below, the expenditure to be incurred on individual projects be approved in line with the Council’s Financial Procedure Rules. (5) That it be agreed that projects proposed to be funded from S106 Agreements would not commence until funding under those agreements had been received in full by the Council. (6) That it be noted reports would be provided for the Executive Member for Children, Young People and Education detailing any variations/amendments to programmes of work and seeking necessary approvals where these were required to ensure compliance with financial instructions and the Constitution.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
EXECUTIVE BOARD DECISION REPORT OF: Executive Member for Children, Young People and Education LEAD OFFICERS: Strategic Director of Children & Education (DCS)
DATE: 2025 9 January 2025
PORTFOLIO/S Children, Young People and Education AFFECTED:
WARD/S AFFECTED: (All Wards);
KEY DECISION: Y
SUBJECT: Schools Capital Programme 2024 - 2025
1. EXECUTIVE SUMMARY To present for consideration and approval the capital programme for Schools and Education for 2024 - 2025 academic year as detailed within this report.
2. RECOMMENDATIONS That the Executive Board: 1: Approves the attached list of projects as detailed in Appendix 2 for inclusion in the 2024 - 2025 Schools and Education capital programme funded from School Condition Allocation and Devolved Formula Capital.
2: Approves the variations to the 2023 - 2024 capital programme for schemes at: • Newfield School - £650,000 • Shadsworth Junior School - £1,700 • St Michael with St John Primary School - £70,000
3: Delegates authority to the Strategic Director of Children’s & Education in consultation with the Executive Member for Children, Young People and Education to undertake the procurement for the works in accordance with the Contracts & Procurement Procedure Rules in the Council’s Constitution.
4: Subject to (5) below, approves expenditure to be incurred on individual projects, in line with the Council’s Financial Procedure Rules.
5: Agrees that projects proposed to be funded from s106 Agreements will not commence until funding under those agreements has been received in full by the Council.
6: Notes that reports will be provided for the Executive Member detailing any variations/amendments to programmes of work and seeking necessary approvals where these are required to ensure compliance with financial instructions and the Constitution.
EBD: V3/23 Page 1 of 5 3. BACKGROUND The Council receives capital funding from Government to meet the responsibilities placed upon it by the Education Acts and the School Standards and Framework Act.
Schools Condition Funding – Local Authorities are given an annual funding allocation for Community Controlled and Voluntary Controlled school buildings. This funding is targeted in the first instance at concerns relating to the condition of school buildings as highlighted through individual school’s asset management plans. Funding can however also be used to make environmental improvements that will enhance teaching and learning spaces and can also be used to address schools’ capacity issues.
Schools Basic Need Funding - this is allocated to LA’s based on pupil projection forecasts to specifically support demands for increased capacity for school places. The funding can be used to fund and/or part fund an increase in the capacity of school places at maintained schools, free schools and academies.
High Needs Provision Grant – this is allocated to LAs proportionally, based on each local authority’s estimated share of future growth in the high needs pupil population.
Devolved Formula Capital Funding – this is allocated for individual schools to spend on capital projects.
4. KEY ISSUES & RISKS
The Schools and Education capital programme is driven by capital priorities raised from the Condition, Suitability and Sufficiency sections of individual school’s asset management plans (AMP’s), which are inclusive of information derived from compliance condition/audit reports e.g. asbestos surveys, legionella reports. In addition, the boroughs information on pupil place sufficiency is used to understand the demand for any required school place growth. As set out in the authority’s scheme of financial delegation for schools, the Council retains the responsibility for “capital” improvements valued over £10,000 in all schools.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.