Blackburn with Darwen Borough Council
Executive Board, Thursday 9 January 2025 at 6.00pm

Blackburn M65 Junction 5 Improvements – Enabling Works and Service Diversions

Noted Executive 2 papers

Executive Board noted this item on Thursday 9 January 2025. Below is the council's own wording, with the papers it was decided on.

Item66

Resolved

(1) That the award of £20m Government funding to support the delivery of the Blackburn Growth Axis Transport Package (South East) and the funding for the following two projects be noted: · Project 1 – South East Blackburn Active Travel (Walking and Cycling) Network (report submitted to the Executive Board in December 2024). · Project 2 – M65 Junction 5 Improvement Scheme (2) That the progress made agreeing the acquisition terms for two parcels of third-party land required to deliver the M65 Junction 5 Improvement Scheme be noted. (3) That the placing of orders with statutory utility providers to commence service diversions and instructing Balfour Beatty to commence mobilisation activities and enabling works for the M65 Junction 5 Improvement Scheme be approved.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Background

In January 2023 the Council secured £20m of Government funding, formerly referred to as Levelling-Up funding, for its Blackburn Growth Axis Transport Package (South East). The funding supports the Council's strategic Growth Axis ambitions, as outlined in the Local Plan, and will support growth in Southeast Blackburn.

The Council appointed Balfour Beatty through the Scape Civil Engineering Framework as a Design & Build Contractor and entered into Scape Gen 3 Framework NEC4 Engineering and Construction Contract Option C (Target Cost) delivery agreement including secondary option NEC4 X22 to cover pre-construction and construction works.

Key Stages - progress to date

• Stage 1: Feasibility Stage (Completed 2023)

• Stage 2a: Preconstruction Activities Designer Procurement (Completed 2023)

• Stage 2b: Preconstruction Activities Proof of Concept (Completed Feb 2024)

• Stage 2c: Preconstruction Activities Preliminary Design (Completed July 2024)

• Stage 3: Preconstruction Activities / Works Detailed Design (Completed Dec 2024)

• Stage 4: Construction On site activities (July 2025 to Dec 2027)

• Stage 5: In Use Monitoring & Evaluation of Project KPI’s (2028+)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackburn M65 Junction 5 Improvements: Enabling Works and Service DiversionsReport 163 KB DownloadRead as text
PDF
EB Blackburn M65 Junction 5 Improvements: Enabling Works and Service DiversionsReport 163 KB Download

At this meeting

Whole meeting

Who was there

11 of 15 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnCommittee Member, present
MH
Councillor Mahfooz HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, present
DL
Dean LangtonOfficer, present
QM
Councillor Quesir MahmoodCommittee Member, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, apologies
DP
Denise ParkOfficer, present
PR
Councillor Phil RileyChair, present
SR
Simon RossOfficer, expected

All 15 on the meeting page

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies