Resolved
RESOLVED; That the contents of the report be noted.
Audit & Governance Committee noted this item on Wednesday 2 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED; That the contents of the report be noted.
2.1The Audit and Governance Committee is asked to note the contents of this report. 3. BACKGROUND
3.1Under Rule 13 of the Council’s Contract and Procurement Procedure Rules waivers from those rules are permitted for specific reasons set out in the rules.
3.2Since 2022, the Contracts and Procurement Team have monitored closely the number of waivers to ensure that, as set out in CPRs, they are agreed by exception rather than become the norm.
3.3The Team has provided reports previously on this matter to the Audit and Governance Committee with the most recent one being provided in September last year. This report provides an update on the waivers for this financial year to the end of January.
4. RATIONALE
4.1The use of waivers from Contract and Procurement Procedure Rules should be the exception not the rule. That said, there are legitimate circumstances where waivers are necessary to ensure that service delivery continues.
4.2Officer are aware of issues in other Councils where excessive and inappropriate use of waivers can be an indication of wider governance issues. Acknowledging this, action is there being taken to address and reduce the number of waivers wherever possible. Given the Council’s ‘starting’ position on this matter, and recognising the capacity constraints that exist, it is likely that the efforts to reduce the number of waivers may well take some time to resolve.
5. KEY ISSUES
5.1The previous reports to this Committee indicated the following:-
• 89 waivers were approved in 2022/23. • 60 waivers were approved in 2023/24. • 22 waivers had been approved in the first 5 months of this financial year.
5.2In October of this year the rules for approving waivers changed with only the Strategic Director Finance and Resources and the Deputy Director, Legal & Governance having the powers to approve waivers. This is intended to put additional scrutiny into the waiver process whilst also ensuring that the decision- making process is devolved from the departments requesting them.
5.3Up to the end of January 2024, 48 waivers had been approved in the 2024/25 financial year compared with 47 in the same period in the 2023/24 financial year. This does indicate that the amount of waivers has levelled off compared to previous years.
5.4For 2024/25, the number of waivers is likely to increase towards the end of the financial year. With the new Procurement Act having become law on the 24th February 2025, engagement has taken place with key stakeholders and officers of the Council to reinforce the requirements under the Act and also of the Contract and Procurement procedures in place within the Council; this could result in additional waivers being received.
5.5The average value of contract waived has increased to £166k (from £101k) and the median value of contracts waived has reduced slightly since last year to £32k (from £34k). These figures reflect that the significant majority of waivers are for contracts of relatively low value where we would normally obtain 3 quotes via the Chest. It should be noted that the average value of waivers approved has been impacted by 2 large value waivers. The first for £3mil for the ongoing appointment of Counsel for social care proceedings to ensure value for money and fair selection of barristers. The second for £2.6mil for the extension of contracts in the Adults portfolio as previously reported to the committee last year (and since reported to the Executive Board).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Use of WaiversReport | 92 KB | DownloadRead as text |
Follow Audit & Governance Committee at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | Minutes of previous meeting held on 24th March 2026That the minutes of the meeting held on Tuesday, 24 March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 23 Jun 2026 | Significant Partnerships Register 2025/26That the report be noted. 2. That committee reviewed the Significant Partnerships Register (SPR) | Noted | Open |
| 23 Jun 2026 | Annual Report on Health & Safety 2025/26That the report be deferred to the next meeting as the reporting Officer was not present at the committee meeting. | Deferred | Open |
| 23 Jun 2026 | Treasury Management Annual Report 2025/26That the report be noted. | Noted | Open |
| 23 Jun 2026 | Audit & Assurance - Progress & Outcomes to May 2026That members discussed, reviewed and challenged the internal audit outcomes achieved to 31 March 2026 against the ann... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.