Resolved
Approve the contract award of the ITB, BSIP and S106 funded A6119 Lammack Signal Junction Improvement project.
Officer Decisions approved this item on Friday 4 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Approve the contract award of the ITB, BSIP and S106 funded A6119 Lammack Signal Junction Improvement project.
RECORD OF DECISION TAKEN UNDER DELEGATED AUTHORITY FROM EXECUTIVE/COUNCIL/COMMITTEE ☒ DELEGATED POWERS OUTLINED IN THE CONSTITUTION ☐
DELEGATED OFFICER Strategic Director of Growth & DECISION TAKEN BY: Development DELEGATED BY: Executive (February 2025) IN CONSULTATION WITH: Executive Member PORTFOLIO AREA: Growth and Development
SUBJECT: A6119 Lammack Signal Junction Contract Award
1. DECISION Approve the contract award of the ITB, BSIP and S106 funded A6119 Lammack Signal Junction Improvement project.
2. REASON FOR DECISION The project is necessary to improve the accessibility, functionality and capacity of this junction for all intended uses, with priority integrated to reduce the journey time of buses through this key junction. The project has been designed internally by the Highways Design Team
On design completion, a high-level project estimate was prepared and sufficient budget allocated to undertake the project. It was apparent that the valuation of the civils work and surfacing work was equal. Therefore, we proceeded to procure the project on Lot 1 (Surfacing) and Lot 2 (Civils) on the approved framework.
This enabled us to invite Tarmac, Bethell’s, Aggregate Industries, Multevo and AE Yates to tender for the project. This offered more competition and ensured the council got the best value.
Tenders were received by Bethell’s, Multevo and AE Yates, of which were evaluated based on price and the submission of required documents that were stated in the Works Information.
The contract is to be awarded to Multevo as they have submitted the lower tender price and provided all required documentation at the time of submission.
3. BACKGROUND A framework has been set up, consisting of 4 lots to ensure we have a wide range of solutions for civil works and surfacing works. The contractors appointed to the framework were scored
RDA: V6/23 Page 1 of 3 based on their quality and social value submissions. Each individual package of works/contract goes onto the framework for a mini competition which is based 100% on price.
4. KEY ISSUES AND RISKS The main risk lies within the delivery timeframe for the project and the implications on the highway network due to the duration and location of the works. We have commissioned bespoke traffic management that utilises the existing signal system to maintain traffic flow as safely and efficient as practicable.
5. FINANCIAL IMPLICATIONS No major financial implications – The tender return was lower than the available budget for the projects and there is risk allowance for any unforeseen compensation events or alterations required during construction.
6. LEGAL IMPLICATIONS There are no legal implications, the procurement process has been carried out in accordance with the Council’s Contract and Procurement Procedure rules and the Public Procurement Regulations
7. RESOURCE IMPLICATIONS There are no major resource implications, the contract will be managed by existing staff within the Highways service.
8. OPTIONS CONSIDERED AND REJECTED No other options were considered, the project has been included in the “Highways Capital Programme 25/26”, and BSIP which has been approved by Executive Board and the contract has been procured through the agreed framework for such works.
9. CONSULTATIONS None
10. DECLARATION OF INTEREST All Declarations of Interest of the officer with delegation and any Member who has been consulted, and note of any dispensation granted should be recorded below:
VERSION: 1
CONTACT OFFICER: Paul Fletcher
DATE: 24/03/2025
Highways Capital Programme 2025-26 (13 Feb 2025) BACKGROUND DOCUMENTS: Bus Service Improvement Plan (22 October 2021)
RDA: V6/23 Page 2 of 3 RDA: V6/23 Page 3 of 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
A6119 Lammack Signal Junction Contract AwardReport | 136 KB | DownloadRead as text |
Follow Officer Decisions at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 May 2026 | Oral Health Improvement Service Tender AwardTo award a 3 (+1) year contract for provision of an Oral Health Improvement Service to the provider AP Smilecare. Del... | Decided | Open |
| 22 May 2026 | Contract Award – Capital Surfacing 2026 - 2027 Project (Phase 1)To award Phase 1 of the Carriageway Surfacing Programme 2026 – 2027 to Tarmac Trading Limited. | Decided | Open |
| 15 May 2026 | Conflict Resolution Service with Blackburn With Darwen Family HubsTo approve the commissioning of a Conflict Resolution Service delivered through Blackburn with Darwen Family Hubs, fu... | Approved | Open |
| 24 Apr 2026 | Award of Contracts for a Community Bereavement Support Service, part of the Public Mental wellbeing commission.• To award Lot 1 – Community Bereavement Support Service For Children, Young People And Families to the provider Lanc... | Decided | Open |
| 27 Mar 2026 | Contract Award – Active Travel Project (Phase1)To approve award of Phase 1 of the Active Travel Programme to Bethell Construction Limited Approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.