Blackburn with Darwen Borough Council
Officer Decisions, Friday 22 May 2026 at 10.00am

Contract Award – Capital Surfacing 2026 - 2027 Project (Phase 1)

Decided Committee 2 papers

AI summaryOfficer awards Phase 1 of the 2026-2027 carriageway surfacing programme to Tarmac Trading Limited, using a pre-established framework scored on 100% price, with costs met from existing capital budgets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPhase 1 of carriageway surfacing programme 2026-2027
MoneyNot statedMet from existing approved capital budgets
What happens nextDraw up contract and manage schemeContracts and Procurement and Highways teams to lead
Who it affectsRoad users in the boroughCarriageway resurfacing works under capital programme

What was decided

The officer awarded Phase 1 of the Carriageway Surfacing Programme 2026-2027 to Tarmac Trading Limited. Report P6

Why

The award uses a framework set up for the council's specific needs, which lets the council efficiently award high-value highways work to pre-vetted, experienced contractors on a 100% price evaluation. Report P6

The procurement followed the council's Contract and Procurement Procedure Rules and the Public Contract Regulations 2015, with no major legal implications identified. Report P2

What happens next

Contracts and Procurement and Highways teams will prepare the tender and contract documents and manage the scheme. Report P5

The contract will be put in a form approved by legal officers, and the agreed price will be held fixed for the duration of the scheme. Report P1, P3

Options considered

  • Chosen: Award through the pre-established framework on 100% price evaluation. Framework was set up for the council's specific needs and allows efficient award to pre-vetted contractors Report P6
  • Rejected: Consider other procurement routes. No major alternative options were considered because the framework already covers this need Report P6

Implications

  • Financial: The price is fixed for the duration of the scheme and will be met from existing approved capital budgets. Report P1
  • Legal: Procurement followed the council's Contract and Procurement Procedure Rules and the Public Contract Regulations 2015; contract to be in a form approved by legal officers. Report P2, P3
  • Staffing: Officers from the Contracts and Procurement Team and the Highways Team are needed to prepare documents and manage the scheme. Report P5

Who and where

  • The council's Contracts and Procurement and Highways teams, who will deliver the scheme Report P5
  • Road users in the borough, who will see carriageway resurfacing works carried out Report P6

Timeline

  • 23.04.2026: Report dated and submitted by the contact officer Report P12
  • 2026-2027: Duration of the Carriageway Surfacing Programme covered by this award

Plain English for the jargon

  • Framework: An arrangement that lets the council award work to pre-vetted contractors without running a full tender each time, scored here on 100% price.
  • Public Contract Regulations 2015: The UK regulations that set out the rules councils must follow when procuring public works, goods and services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

To award Phase 1 of the Carriageway Surfacing Programme 2026 – 2027 to Tarmac Trading Limited.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Officer Decisions

Financial implications

- The price for this works package will be fixed for the duration of the scheme. - The cost of the project will be met from existing approved capital budgets.

No major legal implications, the procurement process was conducted in accordance with the Council’s Contract and Procurement Procedure Rules and the Public Contract Regulations 2015.

The contract will be in a form approved by legal officers.

7. RESOURCE IMPLICATIONS

No major resource implications, officers from the Contracts and Procurement Team and the Highways Team are required to construct the appropriate tender and contract documents and effectively manage the scheme. 8. OPTIONS CONSIDERED AND REJECTED

No major alternative options were considered as this Framework was established for the specific needs of the Council by allowing us to efficiently award high-value highways works schemes to pre-vetted and experienced contractors based on an evaluation criterion of 100% price.

RDA: V6/23 Page 2 of 3 Classified as Official\Anyone

9. CONSULTATIONS

No consultations required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award: Capital Surfacing 2026: 2027 Project (Phase 1)Report 154 KB DownloadRead as text
PDF
EIA-Checklist Contract Award: Capital Surfacing 2026: 2027 Project (Phase 1)Report 216 KB Download

At this meeting

Whole meeting
6Contract Award – Capital Surfacing 2026 - 2027 Project (Phase 1)This decision

Who was there

2 of 14 attended
CF
Charlotte FrazerSecretary, expected
SG
Shannon GardinerSecretary, expected
JL
Councillor Julie Louise GunnCommittee Member, present
TK
Tina KuczerSecretary, expected
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, expected
NM
Nafisha MasterSecretary, expected
TM
Tayyab MullaSecretary, expected
DP
Denise ParkOfficer, expected
PR
Councillor Phil RileyCommittee Member, present
SS
Shelly SarwarSecretary, expected
JS
Jody Spencer-AnforthOfficer, expected

All 14 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Contract Award – Capital Surfacing 2026 - 2027 Project (Phase 1)This decision
  2. Award of Contracts for a Community Bereavement Support Service, part of the Public Mental wellbeing commission.Decided
  3. Contract Award for BwD Municipal, Food and Recyclable Waste TenderApproved
  4. Contract Award – Active Travel Project (Phase1)Approved
  5. Award of Extra Care contracts following procurement exerciseAgreed
  6. Contract Award – Capital Surfacing Project (Phase 3)Approved

More from Blackburn with Darwen Officer Decisions

All decisions
MeetingDecisionOutcome
29 May 2026 Oral Health Improvement Service Tender AwardTo award a 3 (+1) year contract for provision of an Oral Health Improvement Service to the provider AP Smilecare. Del... Decided Open
15 May 2026 Conflict Resolution Service with Blackburn With Darwen Family HubsTo approve the commissioning of a Conflict Resolution Service delivered through Blackburn with Darwen Family Hubs, fu... Approved Open
24 Apr 2026 Award of Contracts for a Community Bereavement Support Service, part of the Public Mental wellbeing commission.• To award Lot 1 – Community Bereavement Support Service For Children, Young People And Families to the provider Lanc... Decided Open
27 Mar 2026 Contract Award – Active Travel Project (Phase1)To approve award of Phase 1 of the Active Travel Programme to Bethell Construction Limited Approved. Approved Open
27 Mar 2026 Selective plumbing materials for disabled facilitiesTo approve award of a Contract to PROCare Ltd for the supply of selective plumbing materials for disabled facilities. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies