Blackburn Town Centre - Skills and Education Campus (Phase 1)

Noted Executive 3 papers

Executive Board noted this item on Thursday 10 April 2025. Below is the council's own wording, with the papers it was decided on.

Item119

Resolved

(1) That confirmation of the award of £20m in Government funding to deliver the Skills and Education Campus and the ongoing discussions with the Ministry of Housing, Communities and Local Government (MHCLG) to monitor progress be noted. (2) That the confirmation of the award of £6m by the Combined County Authority (CCA) towards two Council capital projects including £4m towards the refurbishment of St. John’s for a new Digital and Cyber Hub and £2m towards the Skills and Education Campus be noted. (3) That the provisional agreement of terms with the University of Central Lancashire (UCLAN) to occupy a new building (Building 1) as indicated on the site masterplan drawings attached to the report as Annex 1 (existing site plan) and Annex 2 (proposed site plan) be noted. (4) That it be noted the appointment of building contractors to construct Building 1 and the external public realm works would be presented to a future Executive Board meeting following the conclusion of a competitive tender process to finalise costs and programme. (5) That the site masterplan drawing attached to the report as Annex 2 illustrating outline plans for Building 2 with the Council in discussions with various parties to determine levels of interest with the delivery of Building 2, a follow-on phase be noted. It was also noted Maple Grove Development was granted a non-exclusive land option by the Executive Board in November 2024 for Building 2 to bring forward a speculative development should the opportunity arise. (6) That it be noted the estimated development costs for the Project were £45m which comprised £32m for Building 1 and £13m for external works which included highway realignment, service diversions, flood basins, landscaping and public realm. (7) That a capital budget of £45m (excluding VAT) be approved for the Project which included £20m of Government funding and £2m of CCA funding with the remaining £23m funded by the Council. (8) That £23m of capital funding, with £13m reallocated from the existing capital programme, together with £10m of supplementary capital (borrowings) which would be secured by way of a property lease to UCLAN with rental income covering the additional borrowing costs be approved. The lease agreement also included an option for UCLAN to pay an upfront premium to the Council in lieu of future rents and to acquire the freehold. Either way the Council would be covered for the additional borrowings. (9) That it be noted the Project would drawdown funding from the Government and CCA before using Council funding, thereby reducing costs to the Council by delaying borrowing costs. (10) That it be noted an updated planning application would be submitted under Section 73 of the Town and Country Planning Act 1990 to reduce the building height to reflect the latest requirements of UCLAN and to reduce capital costs. (11) That delegated authority be granted to the Strategic Director Finance and Resources and the Deputy Director of Legal and Governance to conclude the necessary legal formalities to satisfy compliance with the Subsidy Control ...
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Recommendations

That the Executive Board: -

1. Notes the confirmation of the award of £20m in Government funding to deliver the Skills and Education Campus and the ongoing discussions with the Ministry of Housing, Communities and Local Government(‘MHCLG’) to monitor progress;

2. Notes the confirmation of the award of £6m by the Combined County Authority (“CCA”) towards two Council capital projects including £4m towards the refurbishment of St John’s for a new Digital and Cyber Hub and £2m towards the Skills and Education Campus;

EBD: V3/23 Page 1 of 10 3. Notes the provisional agreement of terms with the University of Central Lancashire (‘UCLAN’) to occupy a new building (‘Building 1’) as indicated on the site masterplan drawings located at Annex 1 (existing site plan) and Annex 2 (proposed site plan); 4. Notes the appointment of building contractors to construct Building 1 and the external public realm works will be presented to a future Executive Board following the conclusion of a competitive tender process to finalise costs and programme;

5. Notes the site masterplan drawing at Annex 2 illustrates outline plans for Building 2 with the Council in discussions with various parties to determine levels of interest with the delivery of Building 2 a follow-on phase. It is also noted Maple Grove Developments was granted a non- exclusive land option by the Executive Board in November for Building 2 to bring forward a speculative development should the opportunity arise;

6. Notes the estimated development costs for the Project are £45m which comprises £32m for Building 1 and £13m for external works which includes highway realignment, service diversions, flood basins, landscaping and public realm;

7. Approves a capital budget of £45m (excluding VAT) for the Project which includes £20m of Government funding and £2m of CCA funding with the remaining £23m funded by the Council.

8. Approves capital funding of £23m, with £13m reallocated from the existing capital programme together with £10m of supplementary capital (borrowings) which will be secured by way of a property lease to UCLAN with rental income covering the additional borrowing costs. The lease agreement also includes an option for UCLAN to pay an upfront premium to the Council in lieu of future rents and to acquire the freehold. Eiether way the Council will be covered for the additional borrowings;

9. Notes the Project will drawdown funding from the Government and CCA before using Council funding, thereby reducing costs to the Council by delaying borrowing costs;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackburn Town Centre: Skills and Education Campus (Phase 1)Report 175 KB DownloadRead as text
PDF
Blackburn Town Centre Skills and Education Campus (Phase 1) Appendix 1Appendix 214 KB Download
PDF
Blackburn Town Centre Skills and Education Campus Appendix 2Appendix 4.5 MB Download

At this meeting

Whole meeting

Who was there

11 of 15 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, apologies
JL
Councillor Julie Louise GunnCommittee Member, present
MH
Councillor Mahfooz HussainCommittee Member, apologies
MK
Martin KellyOfficer, present
AL
Asad LaherOfficer, present
DL
Dean LangtonOfficer, apologies
QM
Councillor Quesir MahmoodCommittee Member, apologies
VE
Councillor Vicky Ellen McGurkCommittee Member, present
DP
Denise ParkOfficer, present
PR
Councillor Phil RileyChair, present
SR
Simon RossOfficer, present

All 15 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Blackburn Town Centre - Skills and Education Campus (Phase 1)This decision
  2. Award of Contract for Blackburn Old Town Hall Quadrangle – Listed building Rendering Works.Approved
  3. Blackburn Old Town Hall Quadrangle – Listed Building Rendering WorksApproved
  4. Blackburn Town Centre Campus DevelopmentAgreed

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies