That the Executive Member: · In consultation with the Deputy Director Legal & Governance, approved the terms of the appointment of Craftsman Restoration Ltd (UKR) to carry out the Listed Building rendering and sill replacement works to Blackburn Old Town Hall quadrangle
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
EXECUTIVE MEMBER DECISION REPORT OF: Executive Member for Growth and Development
LEAD OFFICERS: Growth Programme Director
DATE: Wednesday, 21 May 2025
PORTFOLIO/S Growth and Development AFFECTED:
WARD/S AFFECTED: Blackburn Central;
SUBJECT: Blackburn Old Town Hall Quadrangle Listed Building Rendering Works - Contractor Award
1. EXECUTIVE SUMMARY Urgent specialist rendering repairs are required to the internal courtyard at Blackburn Old Town Hall. Due to specialist nature of the works a selected number of heritage contractors with the relevant technical experience were invited to tender through The Chest Portal. Following a successful tender exercise the Growth team are now in a position to award the contract.
2. RECOMMENDATIONS That the Executive Member: In consultation with the Deputy Director Legal & Governance, approves the terms of the appointment of Craftsman Restoration Ltd (UKR) to carry out the Listed Building rendering and sill replacement works to Blackburn Old Town Hall quadrangle.
3. BACKGROUND The internal courtyard at Blackburn Old Town Hall has historically been rendered to protect the building from the elements. The render is in poor condition and survey results show multiple areas of hollow and loose render to all elevations. As the render is also cementitious, it is necessary to remove all the existing render and replace with a lime-based render. Due to the amount of hollow and loose areas, plus the use of cement on a historic building, a patch repair would be insufficient.
An Invitation to Quote was issued via the Chest to a select number of heritage contractors with the relevant technical experience to undertake the works. Two submissions were received which were evaluated and scored against the published criteria 60% Price/40% Quality with the results shown in the table below:
Criteria Scoring % Bidder A Bidder B Price 60% 55.86% 60.00% Quality 40% 38.75% 20.00% Total score 94.61% 80.00% %
EMD: V2/23 Page 1 of 3 It is therefore the intention to award the contract to Craftsman Restoration Ltd (UKR) who had the highest overall score.
4. KEY ISSUES & RISKS Blackburn Old Town Hall is arguably one of the Council’s most valued heritage assets and protecting and preserving it for future generations is important.
The current state of the quadrangle serves as an example of how substandard materials and workmanship can lead to the degradation of historic buildings and repeating this should be avoided where possible.
When taking into consideration the specialist nature of the works, listed building factor and logistical challenges of working within (including full scaffold set up) the quadrangle, it is imperative that a specialist contractor carries out the work.
5. POLICY IMPLICATIONS None
6. FINANCIAL IMPLICATIONS The submitted priced tender falls within the allocated budget for this scheme. The works are to be funded through the Old Town Hall refurbishment budget and has been approved by the Executive Board.
7. LEGAL IMPLICATIONS The procurement process has been carried out in accordance with the Council’s Contract and Procurement Procedure Rules. The contract is to be undertaken via the JCT Minor Works Building Contract 2016. The procurement process complies with the Public Contracts Regulations 2023.
8. RESOURCE IMPLICATIONS No additional resources are required.
9. EQUALITY AND HEALTH IMPLICATIONS Please select one of the options below. Where appropriate please include the hyperlink to the EIA.
Option 1 x Equality Impact Assessment (EIA) not required – the EIA checklist has been completed.
Option 2 In determining this matter the Executive Member needs to consider the EIA associated with this item in advance of making the decision. (insert EIA link here)
Option 3 In determining this matter the Executive Board Members need to consider the EIA associated with this item in advance of making the decision. (insert EIA attachment)
10. CONSULTATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive Member Decisions at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
Coalition to End Gambling Ads (CEGA)That the Executive Member: Authorised the Public Health Team to take the necessary steps to enable Blackburn with Dar...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.