RESOLVED (1) That the Department for Transport 2025/26 Active Travel England and Bus Service Improvement Plan funding be added to the Highways Capital Programme. (2) That subject to (1) above, the apportionment of the 2025/26 Department for Transport Active Travel England funding of £565,134 as detailed in Appendix A Part 2 be approved. (3) That subject to (1) above, the apportionment of the 2025/26 Department for Transport Bus Service Improvement Plan funding of £5,041,774 as detailed in Appendix A Part 2 be approved. (4) That the Highways Active Travel England and Bus Service Improvement Plan for 2025/26 be approved. (5) That delegated authority be granted to the Strategic Director of Growth and Development in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
EXECUTIVE BOARD DECISION REPORT OF: Executive Member for Growth and Development
LEAD OFFICERS: Strategic Director of Growth & Development
DATE: Thursday, 12 June 2025 wi
PORTFOLIO/S Growth and Development AFFECTED:
WARD/S AFFECTED: (All Wards);
KEY DECISION: N
SUBJECT: Bus Service Improvement Plan (BSIP) and Active Travel England (ATE) Programme 2025/26
1. EXECUTIVE SUMMARY To seek the Executive Board’s approval for the allocation of funds detailed in the Highways BSIP and ATE programme for the financial year 2025/26.
2. RECOMMENDATIONS That the Executive Board: (i) Approves that the Department for Transport 2025/26 ATE and BSIP funding is added to the Highways Capital Programme. (ii) Subject to approval at (i) above, approve the apportionment of the 2025/26 Department for Transport ATE funding of £565,134 as detailed in Appendix A Part 2. (iii) Subject to approval at (i) above, approve the apportionment of the 2025/26 Department for Transport BSIP funding of £5,041,774as detailed in Appendix A Part 2. (iv) Approves the Highway ATE and BSIP Programme for 2025/26. (v) Delegates authority to the Strategic Director of Growth & Development, in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.
3. BACKGROUND The Council approved its Local Transport Plan 3 (LTP3) in April 2011 with the following goals, to: • Support the economy • Tackle climate change • Increase safety and security
EBD: V1/21 Page 1 of 5 • Promote equality of opportunity • Promote quality of life, health and the natural environment • Promote the management of the Council’s transport assets.
These goals are aligned to our overall corporate priorities as outlined below: • A more prosperous borough where no one is left behind • Every child and young person to have opportunities to fulfil their potential • Deliver our climate emergency action plan • Build happier, healthier and safer communities
The Council is currently working alongside Lancashire County Council and Blackpool Borough Council to ensure that a new joint LTP (LTP4) is prepared in line with any relevant timescales, and in accordance with any government guidance issued by the Department for Transport.
Funding Sources
The Department for Transport (DfT) Active Travel England (ATE) funding aims to promote walking, wheeling, and cycling as viable and sustainable modes of transport. This funding supports Blackburn with Darwen Borough Council in developing and constructing infrastructure that encourages active travel, such as improved crossing facilities, infrastructure to support walking and wheeling and pedestrian-friendly spaces. Additionally, investing in infrastructure to support these funding aims facilitates behaviour change initiatives, capability-building measures, and other measures that integrate active travel into everyday life. By investing in these projects, the ambition is to improve public health, reduce carbon emissions, enhance air quality, and create more accessible and inclusive transport options
The DfT Bus Service Improvement Plan (BSIP) funding is designed to enhance bus services, making them more frequent, reliable, and accessible. This funding will enable us to implement measures such as bus priority schemes, improved infrastructure, and better passenger information systems to encourage greater use of public transport. By investing in these improvements, in parallel to ATE funding, aims to reduce congestion, lower emissions, and provide communities with more sustainable and efficient transport options.
The schemes identified within this programme are consistent with our approved LCWIP and BSIP frameworks and compliant with DfT guidance.
Funding Amounts
2025/26 Funding £ 2025/26 DfT BSIP Capital 2,522,065 2025/26 DfT BSIP Revenue 2,519,709 2025/26 DfT ATE Capital 437,093 2025/26 DfT ATE Revenue 128,041 Total 2025/26 Funding 5,606,908
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.