RESOLVED (1) That the Department for Transport 2025/26 Local Transport Fund and Integrated Transport Block be added to the Highways Capital Programme. (2) That subject to (1) above the apportionment of the 2025/26 Department for Transport Fund of £6.550m, as detailed in Appendix A attached to the report, be approved. (3) That subject to (1) above the apportionment of the 2025/26 Department for Transport Integrated Transport Block of £1.435m, as detailed in Appendix A attached to the report, be approved. (4) That the supplementary schemes and the updated Highways Capital Programme for 2025/26 be approved. (5) That delegated authority be granted to the Strategic Director of Growth and Development, in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
EXECUTIVE BOARD DECISION REPORT OF: Executive Member for Growth and Development
LEAD OFFICERS: Strategic Director of Growth & Development
DATE: Thursday, 12 June 2025
PORTFOLIO/S Growth and Development AFFECTED:
WARD/S AFFECTED: (All Wards);
KEY DECISION: Y
SUBJECT: Highways Capital Programme 2025/26 - Updated
1. EXECUTIVE SUMMARY To seek the Executive Board’s approval for the allocation of additional funding to deliver supplementary schemes for the 2025/26 financial year as part of the existing agreed Highways Capital Programme.
2. RECOMMENDATIONS That the Executive Board:
(i) Approves that the Department for Transport 2025/26 Local Transport Fund and Integrated Transport Block is added to the Highways Capital Programme. (ii) Subject to approval of (i) above, approve the apportionment of the 2025/26 Department for Transport Local Transport Fund of £6.550m as detailed in Appendix A. (iii) Subject to approval of (i) above, approve the apportionment of the 2025/26 Department for Transport Integrated Transport Block of £1.435m as detailed in Appendix A. (iv) Approves the supplementary schemes and the updated Highways Capital Programme for 2025/26. (v) Delegates authority to the Strategic Director of Growth & Development, in consultation with the Executive Member for Growth and Development, to amend, seek and accept tenders subject to adequate budget provision.
3. BACKGROUND In early 2025, the Department for Transport confirmed an additional funding allocation of £6.550 million for the "Local Transport Fund" and £1.435 million for the "Integrated Transport Block" for the 2025/26 financial year.
EBD: V1/21 Page 1 of 5 This new funding is in addition to and supplements the existing allowance of £3.8m and the previously approved Highways Capital Program.
This report serves an update to the previously approved programme. This report and the decision address the allocation of the additional funding.
The attached Appendix A details the additional schemes proposed forming the updated 2025/26 Highways Capital Program.
All additional proposed schemes and projects conform with the requirements, recommendations and aims of the initial 2025/26 Highways Capital Program and approved Executive Member Decision.
All additional proposed schemes and projects are aimed at achieving our overall corporate priorities along with our statutory obligations to maintain the highway network in the most effective and cost- efficient way based upon the Council’s overall asset management strategy and best practice.
This has enabled additional schemes to be proposed for incorporation into the existing agreed Highways Capital Program resulting in an update to the program requiring Executive Board decision and approval.
4. KEY ISSUES & RISKS All additionally proposed schemes and projects conform with the requirements, recommendations, proposals and selection criteria and share the same overall aims of the initial 2025/26 Highways Capital Program and approved Executive Member Decision.
Any further changes or updates to the 2025/26 programme will be reported via the Council’s Executive Member for Growth and Development.
All proposed changes to the Highways Capital programme as detailed within this report and Appendix A will be resourced from within the programme. As such there will be no additional impact on Council finances.
The proposed supplementary schemes will be closely monitored to ensure they are delivered cost effectively, within budget representing a full and frugal spend of the funding available.
The equality impacts of each scheme are considered and assessed at the scheme design stage.
5. POLICY IMPLICATIONS All schemes proposed directly accord with the Local Transport Plan 3 Strategy and support the balanced growth which is identified within the adopted Local Plan to 2037 for Blackburn with Darwen.
Climate Emergency Action Plan: The proposed capital programme will have a negative effect on carbon usage which is currently difficult to quantify.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.