Executive Board, Thursday 12 February 2026 at 6.00pm

St John's Refurbishment Scheme

Approved Executive 2 papers

AI summaryBlackburn with Darwen Executive Board appoints Barnfield Construction to refurbish fire-damaged St John's Church into a digital business centre, with £8,850,000 total project cost.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBarnfield Construction Limited approved as main contractor
Money£8,850,000 total project costIncludes construction, fees, surveys, furniture, contingency
What happens nextMobilisation March 2026Works summer 2026, complete early 2028, operational summer 2028
Who it affectsSt John's Church, Blackburn town centreBecoming a digital and cyber business creative hub

What was decided

The Executive Board approved the appointment of Barnfield Construction Limited as main contractor following a competitive tender through the Council's Growth Framework, in which they scored 90% against Eric Wright's 84.6%. Report P10, P11, P43

The Board noted a total project cost of £8,850,000 (excluding VAT) and approved reallocations including £800,000 from the Pride in Place Programme (former Levelling-Up Partnership fund) and £510,000 from existing capital programme schemes. Report P12, P15, P16, 6.7

The Board noted funding of £3,540,000 from a Zurich insurance settlement and a £4,000,000 grant from the Lancashire Combined County Authority, with the Growth Programme Director authorised to finalise contract terms. Report P13, P14, P19, 3.4

Why

St John's is a Grade II listed former church owned by the Council that has stood empty since a fire in April 2019 caused significant damage including roof collapse over the main hall and chancel area. Report P1, 3.1, 3.2, 3.3

The redevelopment will create high-specification flexible workspaces focused on digital and cyber businesses as a new creative hub, complementing the Blackburn Skills Campus and the wider Business Innovation District. Report P3, P5, 3.8

Two tenders were received and assessed on an 80% price, 20% quality split, with Barnfield Construction Limited selected as the most economically advantageous bid following value engineering to bring costs within budget. Report 4.2, 4.3, 4.4, 4.5, 4.7, 4.8

What happens next

The Growth Programme Director, with the Deputy Director of Legal and Governance, will finalise contract terms using a JCT Standard Building Contract (without Quantities), 2024 edition. Report P19, 7.3

The contractor will commence mobilisation in March 2026, with construction works starting summer 2026, completing early 2028 and becoming operational by summer 2028. Report P20, 4.12

An amendment to the original planning approval will be progressed in parallel with mobilisation to reflect scheme changes made to reduce costs, and a social value delivery plan will be agreed with the contractor. Report 4.10, 4.13

The money

  • £8,850,000 Total project cost covering construction, fees, surveys, loose furniture and contingency Report P12, 6.1
  • £800,000 Costs to date included in total project cost Report P12, 6.4
  • £3,750,212 Gross insurance settlement agreed with Zurich for fire damage in April 2019 Report P13, 3.4
  • £210,212 Post-fire stabilisation costs deducted from Zurich settlement Report 3.4
  • £3,540,000 Net insurance balance set aside to progress the project (40% of total funding) Report P13, 3.4, P18, P65
  • £4,000,000 Grant from the Lancashire Combined County Authority (45% of total funding) Report P14, P18, P65, 6.5
  • £800,000 Reallocation of Government's Pride in Place Programme (former Levelling-Up Partnership fund) from Bridge House project (9% of total funding) Report P15, P18, 6.6, P65
  • £510,000 Total transfer from existing capital programme (6% of total funding) Report P16, P18, 6.7, P65
  • £200,000 Underspent capital from completed demolition schemes within Growth and Development Report P16, 6.7
  • £75,000 Remaining budget from the 2025/26 Development Investment Fund Report P16, 6.7
  • £235,000 Budget reallocation from the 2026/27 Development Investment Fund Report P16, 6.7
  • £6,826,000 Funding already profiled in the capital programme over 25/26, 26/27 and 27/28 Report 6.5
  • £8,050,000 Remaining construction costs, fees, furniture and contingency after costs to date Report P66

Options considered

  • Chosen: Appoint Barnfield Construction Limited as main contractor (scored 90%, 80% price, 10% quality). Highest scoring bidder on price/quality assessment; submitted final revised tender on 27 January 2026 within budget after value engineering Report P11, 4.4, 4.5, 4.8, 4.11, P43
  • Rejected: Appoint Eric Wright Construction Ltd (scored 84.6%, 69.6% price, 15% quality). Lower total score on 80%/20% price/quality split Report 4.4, P43
  • Chosen: Reallocate £800,000 from Pride in Place Programme (former Levelling-Up fund) from Bridge House, with Bridge House to be funded by Section 106 monies. Bridge House project now expected to be funded from existing Section 106 funding, freeing up the £800,000 for St John's Report P15, 6.6
  • Chosen: Transfer £510,000 from existing capital programme (demolition underspends and Development Investment Fund). Existing capital programme funds available from completed schemes and current Development Investment Fund allocations Report P16, 6.7

Implications

  • Financial: Total capital funding of £8,850,000 confirmed, with £6,826,000 already profiled in the capital programme over financial years 25/26 to 27/28; any future revenue implications from the start-up phase will come to a future Executive Board. Report 6.1, 6.5, 6.8, 6.9, P66
  • Legal: Procurement followed a mini-competition through the Council's Growth Framework under Contract and Procurement Procedures Rules; a JCT Standard Building Contract (without Quantities) 2024 edition will be used; written approval received from the Church Commissioners for the proposed commercial use, to be formalised in title documents at HM Land Registry. Report 7.1, 7.2, 7.3, 7.4, 7.5, P74
  • Equalities: An Equality Impact Assessment checklist has been completed and no EIA is required; recommendations are compliant with equality legislation. Report P77, P81
  • Risk: An amendment to the original planning approval will be required to reflect scheme changes to reduce costs and will progress in parallel with contractor mobilisation. Report 4.13, P21
  • Other: The project is a key strategic initiative in the Local Plan and Growth Plan for the Lancashire Combined County Authority; the scheme aligns with existing Council policies and strategies. Report P5, P55
  • Other: The Growth Framework will expire in March 2026 after 8 years, so St John's will be the final project procured through it; a social value delivery plan will be agreed with the contractor. Report 7.2, 4.10

Who and where

  • Digital and cyber businesses in Blackburn seeking workspace Report P5, 3.8
  • Visitors to and users of Blackburn town centre, given the prominent corner location at Ainsworth Street and Richmond Terrace Report P1, 3.2
  • Bridge House project, which will instead be funded from Section 106 monies Report P15, 6.6
  • The Church Commissioners for England, who have approved the proposed commercial use subject to formalisation in title documents Report 7.5, P74
  • Council Growth, Highways, Procurement and Legal teams delivering the project alongside external consultants and contractors Report P75

Timeline

  • 1787: St John's Church built Report 3.1
  • 1975: Building transferred to the Council from the Church Commissioners for England Report 3.1
  • April 2019: Fire engulfed the property causing significant damage including roof collapse Report P2, 3.3
  • November 2023: Planning and Listed Building consent granted (approval references 10/23/0777 and 10/23/0778) Report P3, 3.7, P80
  • 15 May 2025: Tender documents issued via the Chest portal to the Growth Framework Report 4.1
  • 1 September 2025: Tenders returned from Barnfield Construction Ltd and Eric Wright Construction Ltd Report 4.3
  • 14 November 2025: Both bidders informed of tender result Report 4.6
  • 27 January 2026: Barnfield submitted final revised tender price Report 4.8
  • 12 February 2026: Executive Board considered and approved the report
  • March 2026: Contractor mobilisation planned to commence Report P20, 4.12
  • summer 2026: Construction works planned to commence Report P20, 4.12
  • early 2028: Scheme complete Report P20, 4.12
  • summer 2028: Scheme operational Report P20, 4.12

Plain English for the jargon

  • Growth Framework: The Council's procurement framework used for this tender; it expires in March 2026 after 8 years, and St John's will be the final project procured through it.
  • JCT Standard Building Contract (without Quantities), 2024 edition: A standard form of building contract published by the Joint Contracts Tribunal that the Council intends to use for the contractor appointment.
  • Pride in Place Programme (former Levelling-Up Partnership fund): A Government funding stream from which £800,000 has been reallocated from the Bridge House project to St John's.
  • Section 106 monies: Planning obligation payments from developers that will replace the Pride in Place funding for the Bridge House project.
  • Option to Tax: An existing election on the site for VAT purposes, meaning the increased scheme budget will not harm the Council's partial exemption position.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item169.3

Resolved

RESOLVED (1) That following competitive tenders to progress designs and planning work with planning approval obtained in November 2023, the appointment of OMI Architects and design consultants be noted. (2) That following a competitive tender process, the two tenders received by the Council for the construction work using the Council’s Growth Framework which concluded with Barnfield Construction Limited being the successful contractor, be noted. (3) That the appointment of Barnfield Construction Limited be approved. (4) That the total project cost of £8,850,000 to cover construction, fees, surveys, loose furniture and contingency be noted and that the included £800,000 costs to date be noted. (5) That the Council’s agreed financial settlement with Zurich of £3,750,212 for damage sustained during the fire in April 2019 be noted and that the balance after costs resulted in a sum of £3,540,000 set aside to progress the project be noted. (6) That it be noted that the Council received a grant of £4,000,000 from the Lancashire Combined County Authority towards the project. (7) That the £800,000 budget reallocation of the Government’s Pride in Place Programme (the former Levelling-Up Partnership fund) from the Bridge House project, with the funding for Bridge House to be provided by Section 106 monies, with full details of the costs and funding for this project to be detailed in a report for a future Executive Board to consider in 2026, be approved. (8) That the transfer of £510,000 from the existing capital programme into the project as detailed below be approved: a. An underspent capital of £200,000 from completed demolition schemes within Growth and Development; b. The remaining budget of £75,000 from the 2025/26 Development Investment Fund; c. A budget reallocation of £235,000 from the 2026/27 Development Investment Fund. (9) That the total capital funding of £8,850,000 allocated for the project, with the majority of the funding sourced from a Government grant and a ring-fenced settlement payment from the insurance provider, be noted. (10) That the Growth Programme Director be authorised in liaison with the Deputy Director of Legal and Governance to finalise any contract terms of the contractor appointment. (11) That following confirmation of appointment, it be noted that the contractor would commence mobilisation in March 2026 with works planned to commence summer 2026 with an 18 month build and fit-out programme with the scheme complete early 2028 and operational by summer 2028. (12) That it be noted that the amendment to the original planning approval would be required to account for changes to the scheme to reduce costs and would progress in parallel with the contractor mobilisation.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

St John’s is a Grade II listed former church building in the ownership of the Council and located in a prominent position on the corner of Ainsworth Street and Richmond Terrace in Blackburn town centre, as indicated on Annex A attached.

The St John’s building has stood empty since a fire engulfed the property in April 2019 causing significant damage. Following the fire, the Council agreed an insurance settlement with Zurich and established a project plan to progress a scheme to redevelop the building and bring back into use.

The Council appointed OMI Architects, an award-winning design practice with experience in modernising historic buildings, to progress designs for the redevelopment with planning approval eventually obtained in November 2023 following extensive consultations with historic building stakeholders. The redevelopment proposals create high-specification flexible workspaces through repair, restoration and refurbishment works.

Detailed design and cost assessment work progressed through 2024 with opportunities to secure funding necessary to accelerate the delivery of the project. To this end, the Council secured from the Lancashire Combined County Authority the additional funding to enable the project to proceed to procurement stage.

The development of a new St John’s Business Centre will focus on digital businesses forming a new creative hub to promote emerging opportunities, including the new Blackburn Skills Campus and the wider Business Innovation District, the largest development opportunity of its kind in the Lancashire region, and a key strategic initiative in our Local Plan and the Growth Plan for the Lancashire Combined County Authority.

This report provides an update of the work completed to date and seeks approval to finalise the funding and appoint a building contractor to undertake the construction and fit-out works.

Recommendations

That the Executive Board:

EBD: V1/21 Page 1 of 6 Classified as Official\Anyone

1. Notes the appointment of OMI Architects and design consultants following competitive tenders to progress designs and planning work with planning approval eventually obtained in November 2023;

2. Notes the Council received two tenders for the construction work following a competitive tender process, using the Council’s Growth Framework which concluded with Barnfield Construction Limited being the successful contractor;

3. Approves the appointment of Barnfield Construction Limited;

4. Approves a total project cost of £8,850,000 to cover construction, fees, surveys, loose furniture and contingency and notes this includes £800,000 costs to date.

5. Notes the Council agreed a financial settlement with Zurich of £3,750,212 for damage sustained during the fire in April 2019 and further notes that the balance after costs resulted in a sum of £3,540,000 being set aside to progress the project;

6. Notes the Council received a grant of £4,000,000 from the Lancashire Combined County Authority towards the project;

7. Approves £800,000 budget reallocation of the Government’s Pride in Place Programme (the former Levelling-Up Partnership fund) from the Bridge House project, with the funding for Bridge House to be provided by section 106 monies. Full details of the costs and funding for this project will be detailed in a report for a future Executive Board to consider in 2026;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 201 KB Download
PDF
St John's Refurbishment SchemeReport 172 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
MD
Councillor Mustafa DesaiCommittee Member, apologies
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, present
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, present
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present
PR
Councillor Phil RileyChair, present

All 18 on the meeting page

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies