CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blackburn with Darwen Borough Council
Audit & Governance Committee, Wednesday 25 February 2026 at 6.00pm

Risk Management - 2025/26 Quarter 3 Review

Noted Finance 1 paper

AI summaryBlackburn with Darwen's Audit & Governance Committee noted the 2025/26 Quarter 3 risk management update, listing 26 open corporate risks and naming balanced budget failure, ICB care service impact, SEND High Needs, and tree management as the top four.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ3 2025/26 risk management report noted by committee
MoneyNot stated
What happens nextNext review 31-Mar-26Next risk register review scheduled
Who it affectsAll portfolios and wardsRisk register covers whole council

What was decided

The committee noted the Q3 2025/26 risk management report covering 1 October to 31 December 2025. Report P8

Why

The committee's terms of reference require it to review progress on risk management at least annually and to receive regular reports on corporate risk management action plans. Report P10

The Corporate Risk Register contained 26 open risks as at 31 December 2025, with the top four being failure to deliver a balanced budget and Medium Term Financial Strategy, the impact of Lancashire and South Cumbria's Integrated Care Board budget deficit on care services, the SEND High Needs Budget and EHCPs, and tree management. Report P11, P12

One new risk, Risk 43 on the 2026 Elections, was added during the quarter, alongside the council's request for central government to postpone the elections due to planned local government reorganisation. Report P12

What happens next

The next review of the Corporate Risk Register is scheduled for 31-Mar-26, with risk owners and key contacts continuing to monitor risks under the Management Accountability Framework. Report P22, P12

The committee will continue to receive risk management updates to satisfy its terms of reference and the Corporate Risk Management Strategy and Framework. Report P10

Options considered

  • Chosen: Note the report. The committee accepted the recommendations to review and discuss the register and note the risk management activity. Report P9

Implications

  • Financial: The top corporate risk is failure to deliver a balanced budget and Medium Term Financial Strategy, which could result in a Government-appointed Commission taking control of the council's finances. Report P12
  • Risk: A total of 26 corporate risks were open at 31 December 2025, with one new risk (Risk 43 on 2026 Elections) added during the quarter. Report P11, P12
  • Legal: Risks include SEND High Needs and EHCPs, equal pay claims from failure to re-evaluate roles, and Building Control compliance with the Building Safety Regulators Operational Standards Rules. Report P25
  • Equalities: Risks include the impact of the Lancashire and South Cumbria ICB 2023/24 budget deficit on care services and community wellbeing, and the breakdown of community relations or hate crime and extremism. Report P12, P25
  • Staffing: Risks include workforce capacity to support the Lancashire Combined County Authority while managing local government reorganisation, and equal pay exposure from failure to re-evaluate roles every five years. Report P25
  • Other: The council has asked central government to postpone the 2026 Elections due to planned local government reorganisation, arguing it would maintain political stability, maximise resources and reduce expenditure. Report P12
  • Other: The report itself states there are no policy, financial, legal, resource, or equality and health implications arising from it. Report P12, P13, P14, P15, P16

Who and where

  • All council departments, staff, and residents across all wards of Blackburn with Darwen Report P5, P6
  • Care service users and the wider community affected by Lancashire and South Cumbria ICB decisions Report P12
  • Children and young people with SEND and their families Report P12, P25
  • Members of the public and council staff in relation to uncontrolled tree failure on council owned or managed land Report P12, P25
  • Residents and users of the vacant Tower Block building and the wider Building Control service Report P25

Timeline

  • 1 October 2025 to 31 December 2025: Reporting period for the Q3 2025/26 risk management review Report P8
  • 30-Sep-25: Date of last review of the Corporate Risk Register Report P22
  • 31-Dec-25: Date of the Q3 risk register snapshot Report P22
  • 01-Dec-25: Risk 43 on 2026 Elections added to the register Report P25
  • 25 February 2026: Date of the Audit and Governance Committee meeting Report P4
  • 31-Mar-26: Scheduled date of the next review of the Corporate Risk Register Report P22

Plain English for the jargon

  • BwD: Blackburn with Darwen (Borough Council)
  • MTFS: Medium Term Financial Strategy
  • SEND: Special Educational Needs
  • EHCP: Education, Health and Care Plan
  • ICB: Integrated Care Board
  • LGR: Local Government Reorganisation
  • LCCA: Lancashire Combined County Authority
  • S151 Officer: Statutory Chief Finance Officer with duties under section 151 of the Local Government Act 1972
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40

Resolved

RESOLVED That the report be noted.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Audit & Governance Committee

Classified as Official\Anyone

TO: Audit & Governance Committee

FROM: Head of Audit & Assurance

DATE: 25 February 2026

PORTFOLIOS AFFECTED: All

WARDS AFFECTED: All

TITLE OF REPORT: Risk Management – 2025/26 Quarter 3 Update

1. PURPOSE 1.1 To provide the Committee with details of the risk management activity that has taken place in the period from 1 October 2025 to 31 December 2025.

2. RECOMMENDATIONS 2.1 The Committee is asked to: • Review and discuss the Corporate Risk Register as at the end of December 2025; and • Note the risk management activity that has occurred during the period. 3. BACKGROUND 3.1 The Council recognises that risk management is not simply a compliance issue, but rather it is a process to help ensure the successful delivery of the Council’s Corporate Plan priorities and service plan objectives. Effective risk management arrangements should be embedded in the Council’s culture and decision-making processes as well as being an inherent part of the operational and financial management arrangements operating within the Council. Risk management helps to demonstrate openness, integrity and accountability in all of the Council’s activities.

4. RATIONALE 4.1 The Audit & Governance Committee terms of reference require it to review progress on risk management at least annually and to promote risk management throughout the Council. The Corporate Risk Management Strategy & Framework requires that the Audit & Governance Committee receives regular reports setting out progress against corporate risk management action plans. This report satisfies both these requirements.

5. KEY ISSUES AND RISKS 5.1 The Corporate Risk Register contained 26 open risks as at 31 December 2025. A summary of the corporate risk details is set out in Exhibit 1 of Appendix 1 to this report. A Strategic Risk Heat Map is included at Exhibit 2. This plots each risk in a 5x5 matrix and RAG rates them, based on their likelihood of occurrence and Classified as Official\Anyone

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management: 2025/26 Quarter 3 ReviewAgenda 361 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
NA
Councillor Neil Andrew SlaterCommittee Member, present
CF
Colin FergusonOfficer, in attendance
EW
Councillor Elaine WhittinghamCommittee Member, present
CF
Charlotte FrazerSecretary, in attendance
WH
Councillor Waqar HussainCommittee Member, present
MJ
Councillor Matthew JacksonCommittee Member, present
LJ
Councillor Liz JohnsonCommittee Member, apologies
AS
Councillor Anthony ShawCommittee Member, present
JS
Jody Spencer-AnforthOfficer, in attendance
SR
Simon RossOfficer, in attendance

On this subject at Blackburn with Darwen

Search all
  1. Risk Management - 2025/26 Quarter 3 ReviewThis decision
  2. Risk Management Annual Report 2025/26Agreed
  3. Risk Management Annual Report 2024/25Noted
  4. Risk Management - 2023/24 Quarter 3 ReviewNoted
  5. Annual Risk Management Report 2020/21Noted
  6. Risk Management - 2020/21 Quarter 2 ReviewNoted

More from Blackburn with Darwen Audit & Governance Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 Minutes of previous meeting held on 24th March 2026That the minutes of the meeting held on Tuesday, 24 March 2026 be approved as a correct record and signed by the Chair. Approved Open
23 Jun 2026 Significant Partnerships Register 2025/26That the report be noted. 2. That committee reviewed the Significant Partnerships Register (SPR) Noted Open
23 Jun 2026 Annual Report on Health & Safety 2025/26That the report be deferred to the next meeting as the reporting Officer was not present at the committee meeting. Deferred Open
23 Jun 2026 Treasury Management Annual Report 2025/26That the report be noted. Noted Open
23 Jun 2026 Audit & Assurance - Progress & Outcomes to May 2026That members discussed, reviewed and challenged the internal audit outcomes achieved to 31 March 2026 against the ann... Approved Open