Award of Extra Care contracts following procurement exercise
AgreedCommittee4 papers
AI summaryBlackburn with Darwen's Strategic Director of Adults and Health has awarded two Extra Care contracts across five housing schemes at a tendered cost of £3,482,692.85, with services to start on 1 June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFor Extra Care across five housing schemes
Money£3,482,692.85Total tendered cost across both lots
What happens next1 June 2026New contracts start, for up to five years
Who it affectsExtra Care residentsAcross five housing schemes in Blackburn and Darwen
What was decided
Lot 1 was awarded to Housing 21 for Kingsway and Springbank Court, and Lot 2 to Guardian Homecare for Riverside Heights, Albion Mill and Pembroke Court. Report P10, P36, P38
Both contracts will run for up to five years from 1 June 2026, with an initial three year term and possible extensions of one plus one year. Report P11, P14
The decision puts into effect the earlier Executive Board plan to remodel the borough's Extra Care portfolio, decommission three schemes and reprocure care in the five that remain. Report P3, P7, P8
Why
A commissioning review found too much Extra Care housing for the level of demand, some properties that were not fit for purpose, and inconsistent care and support models across schemes. Report P5, P6
The new contracts are intended to make the best use of resources, meet current and future demand, and provide a consistent care and support model. Report P6, P7
Awarding the contracts now avoids a gap in service when current contracts end on 31 May 2026 and gives the new providers time to mobilise safely. Report P13, P15
What happens next
The new providers will mobilise from 1 June 2026, overseen by the Commissioning team with support from Finance and Performance and Business Transformation teams. Report P11, P29
Social work reviews will be carried out in Q1 26/27 for Pembroke Court residents with a care package, to support their move to extra care lite. Report P7, P31
A separate paper on the future use of Cotton Spinners and how money freed up from decommissioning will be reinvested will go to Executive Board in Q1 26/27. Report P8
The money
£3,482,692.85 Total tendered cost across both lots Report P21
£3,455,002 Original financial envelope agreed in the 2024 Executive Board paper Report P18
£3,703,762.14 Revised financial envelope after 7.2% uplift Report P17, P18
£1,197,643.73 Total cost for Lot 1 (Kingsway and Springbank Court) at Housing 21 Report P21
£2,285,049.12 Total cost for Lot 2 (Riverside Heights, Albion Mill and Pembroke Court) at Guardian Homecare Report P21
Options considered
Chosen: Lot 1 awarded to Housing 21. Highest score at 83.53% across eight compliant bids from 23 received Report P10, P35, P36
Chosen: Lot 2 awarded to Guardian Homecare. Highest score at 77.28% across six compliant bids from 20 received Report P10, P37, P38
Rejected: Other 41 bids across both lots. Deemed non-compliant before or during evaluation, or did not meet essential criteria Report P34, P35, P37
Implications
Financial: Tendered total of £3,482,692.85 sits within the revised financial envelope of £3,703,762.14 and is costed through the Adults Social Care budget. Report P16, P18, P21, P28
Legal: Tender complied with the Council's Contract and Procurement Procedure Rules and the Public Procurement Act 2023; contracts approved in a form by legal officers; Care Act 2014 duties apply. Report P22, P24, P25
Legal: Transfer of Undertakings (Protection of Employment) Regulations 2006 (TUPE) was considered as part of the tender process. Report P26
Risk: Risk of delayed award or gap in service has been addressed by short contract extensions to 31 May 2026, approved by Strategic Commissioning Board on 3 September 2025 with waivers on 8 October 2025. Report P13, P15
Other: New providers may identify changed needs during their own assessments, which could bring forward planned reviews for some residents. Report P32
Who and where
Residents of Kingsway, Springbank Court, Riverside Heights, Albion Mill and Pembroke Court, who will receive care from the new providers Report P7, P10
Pembroke Court residents with a care package, who will move to extra care lite and be offered social work reviews in Q1 26/27 Report P7, P31
Former residents of Lees Court, Hindle Court and Cotton Spinners, which have been decommissioned as Extra Care Report P7, P8
Staff affected by the change of provider, covered by TUPE Report P26
Timeline
8 August 2024: Executive Board decision on future extra care commissioning plans Report P3
3 September 2025: Strategic Commissioning Board approved extensions to existing contracts Report P13
8 October 2025: Waivers approved by corporate procurement Report P13
1 December 2025: Lees Court and Hindle Court returned to sheltered housing Report P8, P23
Q1 26/27: Social work reviews for Pembroke Court residents and Executive Board paper on Cotton Spinners future use Report P8, P31
31 May 2026: Current Extra Care contracts end Report P13, P15
1 June 2026: New contracts at Housing 21 and Guardian Homecare commence Report P1, P11
Plain English for the jargon
Extra Care: Housing with on-site care and support, aimed at older people or adults over 18 with specific needs
Extra Care lite: A scheme without 24-hour background care and no onsite overnight care, as planned for Pembroke Court
Block contract: A fixed payment to a provider for a set amount of background and planned care, separate from variable one to one hours
TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, which move staff to a new employer when a contract changes hands
EIA: Equality Impact Assessment, listed as a background document for the remodelling work
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item1
Resolved
Delegated Officer Decision taken by: The Strategic Director of Adults and Health in consultation with Executive Member; Awarded two contracts for the delivery of Extra Care across 5 Extra Care housing schemes following the recent procurement and tender exercise. And to conclude any agreements necessary to facilitate the recommendations which included: • Remodelling the Extra Care portfolio in Blackburn with Darwen • Decommissioning 3 extra care schemes • Reprocuring the care within the 5 remaining schemes
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
To allow the two contracts to be awarded and the providers to commence delivery of Extra Care from 1 June 2026.
Background
RDA: V6/23 Page 1 of 6 Classified as Official\Anyone
On 8 August 2024, an Executive Board decision was made regarding the future extra care commissioning plans; EBD1: Executive Board Decision
At the time of writing, there were eight designated Extra Care (housing and care) tenancy-based schemes in the borough: three schemes in Blackburn (174 units of accommodation) and five schemes in Darwen (190 units). Seven schemes were for older people, and one was all age i.e. for people over 18 with a specific housing and care need. The Authority currently commissions two providers (three contracts with one a block contract arrangement and two a mixed block contract for background support and spot for 1:1 care hours) to provide the on-site care provision, and all three contracts are due for renewal.
As part of the Commissioning cycle, a review of schemes took place which identified several issues which need to be addressed. These included an over provision of Extra Care Housing in relation to demand and usage; some properties which are not fit for purpose as Extra Care Housing; and inconsistencies across the different contracted care and support models which were in place.
A series of proposals were made in the paper aiming to make the best use of resources, meet current and future demand, and provide a consistent care and support model across schemes.
These recommendations included: • Recommissioning Extra Care Services at Kingsway, Spring Bank Court, Riverside Heights and Albion Mill. • Recommissioning Extra Care Services at Pembroke Court to support those who do not require 24-hour background care. No onsite overnight care will be provided, and the scheme will become “extra care lite”. • Seeking to award contracts to two providers which focus on geographic areas. • Contracts to be for a total of up to 7 years (3 years with extension options of 2 + 1 + 1) and to start from November 2025. • Decommissioning as Extra Care Housing facilities; Lees Court, Hindle Court and Cotton Spinners and the future use will be: o Lees Court and Hindle Court – return to Sheltered Housing o Cotton Spinners – scope for Mental Health Supported Living (subject to a separate paper) • As part of the transitional plan, service users at Pembroke Court, Lees Court and Hindle Court, will be offered a social care review which will include how needs will continue to be met, through care and telecare options.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.