Preparation for procurement of design and construction services for Children Home Provision
ApprovedExecutive1 paper
AI summaryBlackburn with Darwen Executive Board approves design team and procurement route for a new 3-bed children's home, backed by DfE match funding up to £0.958 million.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSeven firms named for design disciplines
Money£0.958 million DfE match cap50/50 grant for capital investment
What happens nextTender building contractorVia Chest portal, JCT Intermediate contract
Who it affectsChildren with complex mental health needs3-bed home in the borough
What was decided
The Executive Board appointed the Design Team covering cost management, architecture, civil and structural engineering, mechanical and electrical engineering, acoustics, fire engineering, and CDM principal designer roles, naming seven specific firms. Report P3, P25
The route to procuring and appointing a building contractor was approved, with tenders to be invited via the Chest e-tendering portal, appropriate notices on Find a Tender, and evaluation on Cost, Quality and Social Value. Report P4, P27, P42
The contract used for the building contractor will be a JCT Intermediate Building Contract, managed by the Council's Procurement Team under the Council's Contract and Procurement Procedure Rules. Report P42
Why
The Council received a Grant Offer Letter from the Department for Education on 27 January 2026 and now needs to appoint a Design Team and agree a procurement strategy to meet the grant terms. Report P2, P8, P9
The grant is part of the DfE's Regional Care Cooperatives strategy, which aims to improve placement sufficiency, cut spot purchasing, and create local residential children's homes. Report P6, P7
Not proceeding carries safeguarding, operational and strategic risks, including continued reliance on unregulated provision, out-of-borough placements, and reputational exposure. Report P30, P31, P32, P33, P35
What happens next
Tender for the building contractor will be run through the Chest e-tendering portal with notices on Find a Tender, using Cost, Quality and Social Value evaluation. Report P27, P42
The Council will submit payment claim forms, complete monthly project monitoring reports, and inform the DfE of any changes, delays or overspends. Report P10
Further public consultation will take place once a design proposal is finalised, with planning consultations already begun on site selection. Report P49, P50
The money
£0.958 million Capped DfE 50/50 match funding grant Report P6
£225,000 Design team costs, estimated from market research Report P39
£1,500,000 Construction costs, as in the DfE grant application Report P40
£200,000 Estimated for contingencies, fixtures, fittings, surveys and planning or building control fees Report P41
Options considered
Chosen: Proceed with the new children's home via the DfE grant and appointed Design Team. Needed to meet DfE grant terms and address safeguarding, operational and strategic risks Report P2, P8, P9, P30, P35
Rejected: Do not pursue the new development. Risk of continued use of unregulated provision, placement breakdowns, out-of-borough placements and reputational harm, plus any overruns after 31 March 2029 would fall entirely on the Council Report P31, P32, P33, P34
Implications
Financial: DfE grant is fixed; any costs above the approved amount must be met by the Council, and no further DfE funding is available after 31 March 2029. Report P34
Legal: Procurement must follow the Council's Contract and Procurement Procedure Rules; the building contract will be a JCT Intermediate Building Contract. Report P42
Equalities: An Equality Impact Assessment checklist has been completed and no EIA is required for this report. Report P45
Risk: Delays risk inflation and loss of DfE funding after 31 March 2029, with any overspends falling on the local authority. Report P34
Staffing: No resource implications: the building contractor tender will be managed within existing staffing resources. Report P43
Who and where
Children and young people in the borough with complex mental health needs and challenging behaviour Report P6, P10
The Council's Children's Services and social care teams Report P6, P7
Department for Education as funder and overseer Report P2, P8, P10
Lancashire and South Cumbria NHS Foundation Trust, which must be engaged in the development Report P10
Local residents near the proposed site, to be further consulted on the design Report P48, P50
Timeline
9 October 2025: Earlier Executive Board approval of grant acceptance, site and Capital Programme addition Report P6, P58
27 January 2026: DfE Grant Offer Letter received by the Council Report P2, P8
20/03/2026: Report dated by the contact officer Report P57
9 April 2026: Executive Board approves Design Team appointment and procurement route
31 March 2029: Deadline beyond which no further DfE funding is available, with overrun costs falling on the Council Report P34
5 years from when placements begin: Minimum operating period the Council must commit to for the new provision Report P10
Plain English for the jargon
DfE: Department for Education
RCC: Regional Care Cooperative, the DfE's model for commissioning children's placements
JCT Intermediate Building Contract: A standard form of building contract used between employer and contractor
CDM principal designer: The designer who plans, manages and coordinates health and safety during the pre-construction phase under the Construction Design and Management regulations
CPPRs: The Council's Contract and Procurement Procedure Rules
FTS: Find a Tender, the UK public sector procurement notice platform
LSCFT: Lancashire and South Cumbria NHS Foundation Trust
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item194.2
Resolved
RESOLVED (1) That the appointment of the Design Team be approved as follows: • Cost Management – GWB Consultants • Architect, Building Regulations Principal Designer and Planning Consultant – John Puttick Associates • Civil and Structural Engineer – Booth King Partnership • Mechanical and Electrical Engineer – SI Sealy • Acoustician – Atelier Crescendo • Fire Engineer – Seven.T. Fire Safety Solutions • CDM principal designer – RJD Associates (2) That, as set out in Section 3 of the report, the route to the procurement and appointment of a building contractor to deliver the works, be approved.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
On the 9th October 2025, the Executive Board approved a report which set out amongst other things, the underpinning principles of a Department for Education grant, based upon a ‘50/50’ ratio of match funding for capital investment to develop and deliver a facility for children with complex mental health needs and challenging behaviour.
Following a period of negotiation with representatives from the Department for Education, (DfE) on the 27th January 2026, the Council received a Grant Offer Letter from the DfE, which means the Council now needs to urgently appoint a Design Team and agree the route to the procurement and appointment of a building contractor in order to meet the terms of the Grant Funding Agreement.
Recommendations
That the Executive Board: 1. Approves the appointment of the Design Team as follows: • Cost Management – GWB Consultants • Architect, Building Regulations Principal Designer and Planning Consultant – John Puttick Associates • Civil and Structural Engineer – Booth King Partnership • Mechanical and Electrical Engineer – SI Sealy • Acoustician – Atelier Crescendo • Fire Engineer – Seven.T. Fire Safety Solutions • CDM principal designer – RJD Associates
2. Approves the route to the procurement and appointment of a building contractor to deliver the works as set out in Section 3.
EBD: V3/23 Page 1 of 6 Classified as Official\Anyone
3. BACKGROUND On the 9th October 2025 a Report was presented to the Executive Board which set out the risks, challenges and difficulties associated with access to and high costs of procuring residential placements for children and young people in the Borough who present with complex mental health needs and challenging behaviours. The Report explained the Council’s success in competing for and receiving a provisional 50/50 grant funding offer, up to a capped value of £0.958 million. The Report also sought approval for the use of the preferred site along with acceptance of the grant funding offer and the addition of the scheme to the Capital Programme. Executive Board approved all those recommendations. The grant funding regime forms part of the DfE’s wider strategy to develop Regional Care Cooperatives (RCCs) as the future model for placement forecasting, commissioning and delivering new homes with the aims of:
- Improved sufficiency, stability, and quality of placements. - Reduced spot purchasing and improved value for money. - Creation of new foster carers and residential children’s homes. - Enhanced joint working across social care, health, and youth justice.
Following a period of negotiation with representatives from the DfE, which also included a pause whilst Ministers reviewed elements of conditionality attached to the Grant, on the 27th January 2026, the Council received a Grant Offer Letter from the DfE.
This offer places the Council in the position of urgently needing to appoint a Design Team and also agree the procurement strategy in advance of procuring and appointing a building contractor to deliver the works. This in turn will ensure that the Council remains able meet the terms of the grant funding offer, including amongst other things:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.