Executive Board, Thursday 9 April 2026 at 6.00pm

Whalley Old Road New Roundabout- Appointment of Contractor

Noted Executive 1 paper

AI summaryBlackburn with Darwen Executive Board approves £2m budget and George Cox & Sons Ltd as preferred bidder for new Whalley Old Road roundabout, with completion aimed for December 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGeorge Cox & Sons Ltd for new Whalley Old Road roundabout
Money£2,000,000 total project budgetIncludes £201,000 spent to date; £1.5m from capital programme
What happens nextMobilisation May 2026, completion December 20267 month construction programme starting summer 2026
Who it affectsWhalley Old Road, BlackburnNew roundabout serving Bovis Homes and North East Blackburn SHS

What was decided

The Executive Board approved a total project budget of £2,000,000 covering construction, fees, surveys and contingency, including £201,000 already incurred. Report 2.2, 6.1

The Board approved the appointment of George Cox & Sons Ltd as preferred bidder for the highway works following a competitive tender. Report 2.6, 4.6

The Board approved an extra £130,800 of Section 106 funding and a £250,000 reallocation from the North East Blackburn capital budget, and noted Bovis Homes' £119,200 already approved in February 2026. Report 2.3, 2.4, 2.5, 6.4, 6.5

Why

A new roundabout on Whalley Old Road is needed to give a combined entrance to the Bovis Homes housing site (161 dwellings under construction) and the larger North East Blackburn Strategic Housing Site, an allocated site in the Local Plan (2021-2037) expected to deliver up to 1,250 homes. Report 1.1, 1.2, 1.3, 3.1, 3.2, 3.3, 3.4

One combined roundabout is preferred over two separate site entrances as it is safer, more efficient, better suited to the semi-rural road, and avoids abortive work by Bovis Homes on a now-redundant entrance. Report 3.4, 3.5, 6.4

The tender was run under the Procurement Act 2023 below-threshold route, with a 60/40 price/quality split; George Cox & Sons scored 90% against the lowest bid at 65.31%. Report 4.1, 4.3, 4.4, 4.5, 4.6, 7.2

What happens next

The Growth Programme Director, with the Deputy Director of Legal and Governance, will finalise contract terms, using the NEC Engineering and Construction Contract. Report 2.7, 7.3

Mobilisation will start in May 2026, with construction over the summer and a 7 month programme aiming for completion by December 2026. Report 2.8, 4.9

Around 55% of the Council's funding is expected to be recovered from the lead developer of the Strategic Housing Site; the final terms of the Collaboration Agreement between all landowners will come back to the Executive Board later in 2026. Report 2.9, 6.6, 7.4

The money

  • £2,000,000 Total project budget (construction, fees, surveys, contingency) Report 2.2, 6.1
  • £201,000 Costs incurred to March 2026 Report 2.2, P51
  • £1,500,000 Council funding within the capital programme Report 2.3, 6.4, P50
  • £119,200 Section 106 funding from Bovis Homes, approved February 2026 Report 2.3, 6.4
  • £130,800 Additional Section 106 funding to be added to capital budget Report 2.4, 6.4
  • £250,000 Reallocation from North East Blackburn capital budget Report 2.5, 6.5
  • £1,000,000 Earlier capital allocation across 2024/25 to 2026/27 for the Strategic Housing Site Report 2.5, 6.5
  • £550,000 Funds still available within the North East Blackburn capital budget as of March 2026 Report 2.5, 6.5
  • £1,750,000 Construction costs element of project budget Report P51
  • £49,000 Fees/contingency element of project budget Report P51

Options considered

  • Chosen: Build one combined roundabout for both sites (recommended). Safer, more efficient, avoids abortive entrance works by Bovis Homes and fits the semi-rural character of Whalley Old Road. Report 3.4, 3.5
  • Rejected: Two separate site entrances. Less safe and efficient than a roundabout; would duplicate entrance works. Report 3.4
  • Rejected: Tender bidders: Eric Wright, Casey, Bethell, AE Yates and George Cox & Sons. George Cox & Sons scored highest at 90% in the 60/40 price/quality assessment. Report 4.1, 4.5, 4.6

Implications

  • Financial: Project cost of £2,000,000 to be met from £1.5m Council capital, £250,000 Section 106 from Bovis Homes and £250,000 reallocated from the North East Blackburn capital budget; around 55% may later be recovered from the lead developer. Report 2.2, 2.3, 2.4, 2.5, 6.4, 6.5, 6.6
  • Legal: Procurement followed the Procurement Act 2023 below-threshold invitation only route; contract will be the NEC Engineering and Construction Contract; Collaboration Agreement between landowners to come back to Executive Board. Report 7.1, 7.2, 7.3, 7.4
  • Equalities: EIA checklist completed; recommendation is that an Equality Impact Assessment is not required. Report P64
  • Other: Scheme savings of up to 10% may be realised through a compensation event, reflecting a lower housing yield on the Strategic Housing Site, and used to cover fees and contingency. Report 4.7, 6.3
  • Other: Pedestrian and cycle connectivity is included, with splitter islands on each arm and a parallel crossing; the former bus turnaround will be converted to a 'Pocket Park' greenspace subject to planning consent. Report 3.6, 3.10, 3.11

Who and where

  • Residents and future residents of the North East Blackburn Strategic Housing Site (up to 1,250 homes planned) Report 1.3, 5.1
  • Residents of the Bovis Homes development (161 dwellings, 112 open market and 49 affordable with Together Housing) Report 3.3
  • Road users and pedestrians/cyclists on Whalley Old Road, Blackburn Report 1.1, 3.4, 3.6
  • Seven landowners of the Strategic Housing Site, including Blackburn with Darwen Borough Council (largest landowner, around 45%) Report 1.2
  • Bovis Homes and Together Housing as partner housing provider Report 3.3, 2.3

Timeline

  • 2022: Bovis Homes obtained planning consent for 161 dwellings off Whalley Old Road Report 3.2
  • January 2024: Blackburn with Darwen Local Plan (2021-2037) adopted, allocating the North East Blackburn SHS under Policy H195 Report 3.1
  • 2024: Feasibility studies and surveys for the new roundabout commenced; public consultation on SHS masterplan in June/July 2024 Report 3.7, P69
  • May/June 2025: Public consultation on draft SHS masterplan and design code Report P69
  • December 2025: Consent granted to fell a tree covered by a Tree Preservation Order; tree removed in February 2026 Report 3.9
  • End of 2025: Detailed design, site investigations and utility studies completed Report 3.7
  • 26 January 2026: Tender documents issued via the Chest portal to five bidders Report 4.1
  • February 2026: Planning consent granted for the roundabout under Article 39 (application 10/25/1262); £119,200 of Bovis Homes Section 106 funding approved by Executive Board at Quarter 3 Report 3.8, 2.3
  • 20 March 2026: Tenders returned Report 4.4
  • 9 April 2026: Executive Board approves George Cox & Sons Ltd as preferred bidder and total budget of £2,000,000 Report 2.2, 2.6
  • May 2026: Contractor mobilisation to commence Report 2.8, 4.9
  • Summer 2026: Construction works planned to start Report 2.8, 4.9
  • December 2026: Target completion of all roundabout works (7 month construction programme) Report 2.8, 4.9
  • Later in 2026: Final terms of the Collaboration Agreement between landowners to be presented to Executive Board Report 2.9, 7.4
  • By 2030: Works on the Strategic Housing Site expected to commence on site Report 1.3

Plain English for the jargon

  • SHS: Strategic Housing Site, here the North East Blackburn SHS allocated in the Local Plan (2021-2037) under Policy H195, expected to deliver up to 1,250 homes.
  • Section 106 Agreement: A planning obligation under which a developer (here Bovis Homes) provides funding or works, used here to cover the cost of the combined entrance.
  • NEC Engineering and Construction Contract: The standard form of construction contract approved by Council legal officers for this appointment.
  • Collaboration Agreement: Legal agreement between all landowners (including the Council) for the Strategic Housing Site, setting out pre-development cost estimates, funding and obligations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item196.2

Resolved

RESOLVED (1) That it be noted that the proposed roundabout on Whalley Old Road, Blackburn, as illustrated on the plan, and attached as Annex A to the report, was required to provide a new entrance to the housing site off Whalley Old Road (currently under construction by Bovis Homes) and to the North East Blackburn Strategic Housing Site, an allocated site in the Blackburn with Darwen Local Plan (2021-2037). (2) That the total project budget of £2,000,000 to cover construction, fees, surveys and contingency be approved and that it be noted that this included £201,000 costs incurred to date. (3) That it be noted that the Council had £1,500,000 allocated funding within the capital programme, with an additional £119,200 funding approved by Executive Board at Quarter 3 in February 2026, provided by Bovis Homes under a Section 106 Agreement. The funding provided by Bovis Homes was equivalent to the cost of the entrance works which were omitted from their scheme to prevent abortive work due to the proposed roundabout works now providing a combined entrance for the two sites. (4) That the addition of a further £130,800 to the capital budget funded by Section 106 contributions be approved. (5) That the reallocation of £250,000 capital funding from the North East Blackburn capital budget which had in excess of £550,000 of funds available as of March 2026 following the Executive Board, at its February 2024 meeting, which approved a capital allocation of £1,000,000 in total across the financial years 2024/25, 2025/26 and 2026/27 to bring forward the North East Blackburn Strategic Housing Site to cover all pre-development work including masterplanning , surveys, site investigations and any other design or site enabling infrastructure, be approved. (6) That, following a competitive tender process, the appointment of George Cox & Sons Ltd as preferred bidder for the highway works be approved. (7) That the Growth Programme Director, in liaison with the Deputy Director of Legal and Governance, be authorised to finalise the contract terms for the appointment of the preferred bidder. (8) That it be noted that the contractor would commence mobilisation in May 2026 following confirmation of appointment with works planned to commence over the summer with a 7 month construction programme with all works aimed for completion by December 2026. (9) That it be noted that a proportion of the Council funding required to construct the new roundabout would eventually be recovered from the developer for the North East Blackburn Strategic Housing Site and reinforced in the infrastructure delivery strategy/masterplan. The proportion would be in the region of 55% and would be recovered from the lead developer with the details agreed with the co-landowners in the Collaboration Agreement. The Collaboration Agreement was a legal agreement between all landowners (including the Council) which set out estimates of pre-development cost, funding and obligations. The final terms of the Collaboration Agreement would be presented to the Executive Board later this year.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

1.1This report details the outcome of the tender exercise for the appointment of a civil engineering contractor to construct a new roundabout on Whalley Old Road at Sunny Bower in Blackburn. The new roundabout will provide an entrance to both the Bovis Homes housing site (currently under construction off Whalley Old Road) and the proposed North East Blackburn Strategic Housing Site ('SHS’).

1.2The SHS is a long term development site in multiple land ownership (seven landowners, including the Council). The Council is the largest landowner, with approximately 45% of the site in its ownership, by area. The SHS is allocated in the Blackburn with Darwen Local Plan (2021- 2037) under Policy H195.

1.3The SHS is approximately 100 hectares in area and is expected to deliver up to 1,250 high quality new homes along with supporting complementary uses and associated infrastructure. Development of the site will be delivered over multiple phases, with works expected to commence on site by 2030 and take approximately 20 years to complete.

1.4The Council is lead land promoter for the SHS and is working alongside the other landowners and consultants Stantec to develop a masterplan, infrastructure delivery plan and design code for the site. This will ensure development of the site, including infrastructure delivery, is brought forward in a comprehensive manner across all phases.

1.5This report also provides details of the estimated capital costs of the works and the sources of funding required to deliver the new roundabout.

Recommendations

That the Executive Board:

EBD: V1/21 Page 1 of 7 Classified as Official\Anyone

2.1Notes the proposed roundabout on Whalley Old Road, Blackburn, as illustrated on the plan attached at Annex A, is required to provide a new entrance to the housing site off Whalley Old Road (currently under construction by Bovis Homes) and to the North East Blackburn Strategic Housing Site (‘SHS’), an allocated site in the Blackburn with Darwen Local Plan (2021-2037);

2.2Approves a total project budget of £2,000,000 to cover construction, fees, surveys and contingency and notes this includes £201,000 costs incurred to date;

2.3Notes the Council has £1,500,000 allocated funding within the capital programme with an additional £119,200 of funding approved by Executive Board at Quarter 3 in February 2026, provided by Bovis Homes under a Section 106 Agreement. The funding provided by Bovis Homes is equivalent to the cost of the entrance works which are omitted from their scheme to prevent abortive work due to the proposed roundabout works now providing a combined entrance for the two sites;

2.4Approves the addition of a further £130,800 to the capital budget funded by S106 contributions.

2.5Approves the reallocation of £250,000 capital funding from the North East Blackburn capital budget which has in excess of £550,000 of funds available as of March 2026 following the Executive Board, at February 2024 meeting, which approved a capital allocation of £1,000,000 in total across the financial years 2024/25, 2025/26 and 2026/27 to bring forward the North East Blackburn SHS to cover all pre-development work including masterplanning, surveys, site investigations and any other design or site enabling infrastructure.

2.6Approves the appointment of George Cox & Sons Ltd as Preferred Bidder for the highway works following a competitive tender process;

2.7Authorises the Growth Programme Director in liaison with the Deputy Director of Legal and Governance to finalise the contract terms for the appointment of the Preferred Bidder;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Whalley Old Road New Roundabout- Appointment of ContractorReport 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
MD
Councillor Mustafa DesaiCommittee Member, apologies
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, absent
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, absent
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, expected
VE
Councillor Vicky Ellen McGurkCommittee Member, present
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present

All 19 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Whalley Old Road New Roundabout- Appointment of ContractorThis decision
  2. Planning Application 10/26/0307 - Turning Head off Whalley Old Road, BlackburnApproved
  3. EMD Whalley Old Road New Roundabout – Procurement StrategyNoted
  4. Minor modification to Section 106 Agreement pursuant to the ongoing housing development on land to the south of Whalley Old Road, BlackburnNoted

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies