The Executive resolved as follows: To agree to Prudentially Borrow £4.5m to make a secured loan to Create Development (Blackpool) Ltd to facilitate the development of a 135 bedroom hotel to an agreed standard. To delegate the approval of the loan agreement to the Chief Executive to the borrowing limits referred to in the report at Paragraph 9.3, following consultation with the Leader of the Council
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Notice of: EXECUTIVE Decision Number: EX36/2016 Relevant Officers: Alan Cavill, Director of Place and Steve Thompson, Director of Resources Relevant Cabinet Member: Councillor Simon Blackburn, Leader of the Council
Date of Meeting 18 July 2016
OPTIONS FOR THE DEVELOPMENT OF BOURNE CRESCENT 1.0 Purpose of the report:
1.1To appraise members of the options available to resolve the condition of properties at Bourne Crescent on South Promenade and seek a decision on the preferred option.
2.0Recommendation(s):
2.1To agree the preferred option from three options as set out a Paragraph 5.7.
2.2Subject to 2.1, to delegate the approval of any loan agreement to the Chief Executive to the borrowing limits referred to in the report, following consultation with the Leader of the Council.
3.0Reasons for recommendation(s):
3.1The condition of the properties around Bourne Crescent is detrimental to the town and the surrounding area in terms of appearance and the continued safety requirements. This situation needs to be resolved and the Executive is requested to support the one of the three options outlined to resolve this.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
3.2b Is the recommendation in accordance with the Council’s approved Yes budget? 3.3 Other alternative options to be considered:
As outlined in the Background Information section.
4.0Council Priority:
4.1The relevant Council Priority is “The economy: Maximising growth and opportunity across Blackpool”
5.0Background Information
5.1Following its closure for over 12 months the Palm Beach Hotel was damaged by fires in 2014 and then again in 2015. The first of these was the worst and caused significant damage to the corner of the property which was further damaged by high winds in the winter of 2014/15. The hotel is beyond economic repair and its condition has now affected that of the Bourne Hotel. The Warwick Hotel is also in a state of disrepair. The Council has been trying to keep the site safe since the first fire and has made regular security and condition survey visits to the site which is frequently being further vandalised. The previous owners were in possession of the Palm Beach and the Bourne Hotel at the point of closure and did not have the resources to secure or demolish these properties despite the actions of the Council’s Enforcement Team over the years.
5.2In 2015 Create Construction Ltd and Create Developments (Blackpool)Ltd (‘Create Construction’) two local companies) put together a scheme for the development of a hotel with 135 bedrooms. The companies received full planning permission for this earlier this year. The proposed funding package for this project is used in the hotel sector but fairly complex. In effect, Create Construction Ltd would build the hotel which would be owned by the first funder who in return for this freehold ownership of the land would invest the cost of construction into the project as the first funder during the construction period. Create Construction is also providing funds to the project. However, there is a gap in the funding which will be required to be met by a second funder who would benefit from the security of a legal charge over a 99 year lease from the first funder to Create Developments (Blackpool) Ltd. Create Construction has asked the Council to consider providing this gap funding. The amount of the loan sought is £4.5m. The business plan presented by Create Construction suggests that the value of the security for the second funder would be worth more than the amount of the loan sought. The Council is currently awaiting further independent verification of the valuation. Create Construction would be granted a loan only if the independent valuation is deemed to be satisfactory by the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.