The Executive agreed the recommendations as outlined above namely: To agree in principle to the proposal for the development of a new conference and exhibition centre situated at the Winter Gardens complex. That the Director of Place be given delegated authority to progress the first stage of the delivery of a new conference and exhibition centre situated within the Winter Gardens complex, as set out in this report, to include the completion of all due diligence associated with the project and the submission of an outline planning application. That in order to deliver the proposed project within the associated time constraints, up to £50,000 of funding is made available from August 2016 to be used in finalising the scheme designs and completing due diligence, financed from the Leisure Assets portfolio. To note that a further report will be brought to the Executive once decisions from other organisations on grant funding have been made to agree the further steps in the delivery of the conference and exhibition centre.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Decision Number: EX34/2016 Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member: Councillor Simon Blackburn, Leader of the Council Date of Decision: 18 July 2016
WINTER GARDENS CONFERENCE AND EXHIBITION CENTRE 1.0 Purpose of the report:
1.1To consider the proposal for a new conference and exhibition centre to be situated at the Winter Gardens complex.
2.0Recommendation(s):
2.1To agree in principle to the proposal for the development of a new conference and exhibition centre situated at the Winter Gardens complex.
2.2That the Director of Place be given delegated authority to progress the first stage of the delivery of a new conference and exhibition centre situated within the Winter Gardens complex, as set out in this report, to include the completion of all due diligence associated with the project and the submission of an outline planning application.
2.3That in order to deliver the proposed project within the associated time constraints, up to £50,000 of funding is made available from August 2016 to be used in finalising the scheme designs and completing due diligence, financed from the Leisure Assets portfolio.
2.4To note that a further report will be brought to the Executive once decisions from other organisations on grant funding have been made to agree the further steps in the delivery of the conference and exhibition centre.
3.0Reasons for recommendation(s):
3.1To deliver a fit for purpose twenty-first century conference centre, allowing Blackpool to compete in the economically important business tourism sector and significantly contribute toward attaining the Council vision for Blackpool of being the UK’s number one family resort with a thriving economy that supports a happy and healthy community who are proud of this unique town. Contribute toward maximising growth and opportunity within Blackpool, helping to create stronger communities and increasing resilience.
Further stabilisation of the Winter Gardens building complex.
Potential enhancement of the Blackpool Entertainment Company business.
3.2a Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No
3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
Delivery of a new conference and exhibition Centre, fit for the twenty-first century and allowing Blackpool to compete in this highly competitive market is considered the next essential, logical step in the economic progress of Blackpool and the development of the town as a visitor destination.
A number of alternative locations for a conference and exhibition centre have been considered. The Winter Gardens site provides the optimal solution when evaluating together:
Strategic development of the town centre. The identified site provides future options to physically link newly developed areas, providing further opportunities in improving the cohesion, look and feel of the town centre
Financial considerations. The Winter Gardens site offers the most affordable option from a capital expenditure perspective as it allows improved utilisation of the existing asset thereby reducing the requirement for new build. The essential business priority associated with the operation of the conference centre is new incremental trade however, clear opportunities in enhancing existing business delivered via the Winter Gardens also present themselves.
Physical space. Investigation into alternative available locations has revealed the space associated with those sites is insufficient to provide adequate conferencing facilities able to cope with conference and exhibition market demands.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.