The Executive agreed the recommendations as outlined above namely: That £500,000 expenditure is authorised in order to fund an enabling works package for the proposed Conference and Exhibition Centre. To delegate approval of the detailed programme of enabling works to the Director of Place. To note that a further report will be brought to the Executive once the Growth Deal 3 grant funding application evaluation process is completed.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Decision of: EXECUTIVE Decision Number: EX20/2017 Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member: Councillor Simon Blackburn, Leader of the Council Date of Meeting: 19 June 2017
WINTER GARDENS CONFERENCE AND EXHIBITION CENTRE 1.0 Purpose of the report:
1.1To consider the authorisation of £500,000 expenditure in order to fund an enabling works package for the proposed Conference and Exhibition Centre.
2.0Recommendation(s):
2.1That £500,000 expenditure is authorised in order to fund an enabling works package for the proposed Conference and Exhibition Centre.
2.2To delegate approval of the detailed programme of enabling works to the Director of Place.
2.3To note that a further report will be brought to the Executive once the Growth Deal 3 grant funding application evaluation process is completed.
3.0Reasons for recommendation(s):
3.1To progress the delivery of a fit for purpose 21st century conference centre which once delivered will allow Blackpool to compete in the economically important business tourism sector and significantly contribute toward attaining the Council vision for Blackpool of being the UK’s number one family resort with a thriving economy that supports a happy and healthy community who are proud of this unique town.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
3.2b Is the recommendation in accordance with the Council’s approved Yes budget? 3.3 Other alternative options to be considered:
Do not complete the enabling works package.
The time constraints associated with completing the project are extremely tight. This course of action would increase the possibility of deviation from project schedule.
4.0Council Priority:
4.1The relevant Council Priority is: “The economy: Maximising growth and opportunity across Blackpool”
5.0Background Information
5.1Following receipt of delegated authority allowing the Director of Place to progress the project, a number of significant steps toward delivering the scheme have been made including:
Full planning approval including listed building consent Progress of scheme designs to technical stage Selection of the preferred bidder for the main contract works £2,900,000 Coastal Communities grant funding award £15,000,000 Growth Deal 3 grant funding application evaluation is now at an advanced stage
5.2The next step in delivery of the project is the completion of an enabling works package. This work will assist in ensuring the site is prepared for commencement of construction works later this year and support adherence to project plan. The Conference Centre is presently scheduled to open Spring 2019. A further report will be submitted to the Executive to confirm the final project plan once the result of the grand funding application is known.
5.3The exact content of the enabling works package is currently being organised and will be approved by the Director of Place however, activities are likely to include:
Further survey work Utility diversions Existing building elevation repairs Demolitions Site clearance 5.4 Authority for up to £500,000 expenditure is now sought in order to fund the enabling works package.
5.5Does the information submitted include any exempt information? No
5.6List of Appendices:
None.
6.0Legal considerations:
6.1The Council’s contracting and commissioning procedures will apply. A suitable contract will be developed in consultation with the Council’s Legal Services team.
7.0Human Resources considerations:
7.1None.
8.0Equalities considerations:
8.1None.
9.0Financial considerations:
9.1The £500,000 expenditure for which authority is sought in this report will initially be classified as a revenue expense. Reclassification of the £500,000 will take place once the full financing package is in place and it will form part of the Conference Centre capital expenditure.
10.0Risk management considerations:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.