The Executive agreed the recommendations as outlined above namely: That the principles in delivering the remaining stages of the Blackpool Conference and Exhibition Centre project are agreed as set out in the Executive report and Appendix 3a, to the Executive report. That the Director of Place be provided with delegated authority to complete the delivery of the scheme as set out in the Executive report and Appendix 3a to the Executive report to include the completion of all due diligence associated with the project. That authority is provided to complete the project funding package through debt finance in the form of Prudential Borrowing, as detailed in Appendix 3a to the Executive report.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Decision of: EXECUTIVE Decision Number: EX29/2017 Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member: Councillor Simon Blackburn, Leader of the Council Date of Meeting: 11 September 2017
WINTER GARDENS CONFERENCE AND EXHIBITION CENTRE 1.0 Purpose of the report:
1.1To agree in principle the remaining stages in the delivery of the Blackpool Conference and Exhibition Centre project as set out in this report.
To seek delegated authority allowing the Director of Place to progress the scheme to completion.
To request authority to complete the project funding package through debt finance in the form of Prudential Borrowing, as detailed in the financial appendix to this report.
2.0Recommendation(s):
2.1That the principles in delivering the remaining stages of the Blackpool Conference and Exhibition Centre project are agreed as set out in the Executive report and Appendix 3a, to the Executive report.
2.2That the Director of Place be provided with delegated authority to complete the delivery of the scheme as set out in the Executive report and Appendix 3a to include the completion of all due diligence associated with the project.
2.3That authority is provided to complete the project funding package through debt finance in the form of Prudential Borrowing, as detailed in Appendix 3a to the Executive report.
3.0Reasons for recommendation(s):
3.1To deliver a fit for purpose 21st century conference centre which once delivered will allow Blackpool to compete in the economically important business tourism sector and significantly contribute toward attaining the Council vision for Blackpool of being the UK’s number one family resort with a thriving economy that supports a happy and healthy community who are proud of this unique town.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council? 3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
None, other than not to proceed with Conference Centre which would lose the Council grant funding already committed and not achieve the Council’s objectives.
4.0Council Priority:
4.1The relevant Council Priority is:
“The economy: Maximising growth and opportunity across Blackpool”
5.0Background Information
5.1Following receipt of delegated authority under Executive decision EX34/2016 allowing the Director of Place to progress the project, a number of significant steps have been taken toward delivery of the scheme including:
Full planning approval including listed building consent Completion of scheme designs to technical stage Selection of the preferred bidder for the main construction works Coastal Communities grant funding award in full Growth Deal 3 grant funding award in full Derelict properties situated on Leopold Grove have been demolished creating the construction site compound Commencement of the enabling works project
5.2The next major milestone for this project is to begin the main construction period, due to start in October this year.
5.3The programme of construction works has been developed in conjunction with Blackpool Entertainment Company Limited, so as to minimise business disruption while continuing to meet the forecast project time schedule and will follow the summary, indicative plan set out below:
October 2017. Commencement of remaining demolition and existing building repairs December 2017. New build construction commences August 2018. Internal fit-out begins January 2019. External landscaping to be undertaken March - April 2019. Testing and commissioning to take place April 2019. Complete construction and handover 5.4 On completion of the associated due diligence, entry into a formal contract with the main construction contractor (selected preferred bidder), will be required prior to beginning the main construction work package.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.