The Executive agreed the recommendations as outlined above namely: To approve and adopt the Masterplan (as set out at Appendix 7a to the Executive report) as the strategic framework for project delivery and for use as part of the planning process. To delegate to the Director of Place the authority to make minor amendments as necessary, after consultation with the relevant Cabinet Member, that may result from the adoption and approval process with partner organisations.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member: Councillor Mark Smith, Cabinet Member for Regeneration, Enterprise and Economic Development Date of Meeting: 5 February 2018
BLACKPOOL AIRPORT ENTERPRISE ZONE MASTERPLAN 1.0 Purpose of the report:
1.1To approve and adopt the Blackpool Airport Enterprise Zone Masterplan (as set out at Appendix 7a to this report and as amended) as the Masterplan to provide the strategic framework for the development and delivery of the Enterprise Zone and to be given appropriate weight by the decision taker and/or policy maker as part of the planning process.
Appendix 7a contains the Masterplan and a Masterplan Summary Report as published for public consultation. The Blackpool Airport Enterprise Zone Masterplan Consultation Report sets out a number of changes to both the Masterplan and Masterplan Summary Report. Once approved by each partner organisations both the Masterplan and the Masterplan Summary Report will be edited and published.
2.0Recommendation(s):
2.1To approve and adopt the Masterplan (as set out at Appendix 1 to this report) as the strategic framework for project delivery and for use as part of the planning process.
2.2To delegate to the Director of Place the authority to make minor amendments as necessary, after consultation with the relevant Cabinet Member, that may result from the adoption and approval process with partner organisations.
3.0Reasons for recommendation(s):
3.1The reasons for the above recommendations are as follows; a. To give weight to the document in the planning process and to allow project delivery to continue b. To deal with minor practical amendments which may become necessary as the document is approved/adopted by the various partner organisations 3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
The Masterplan proposes industrial development on land which is current allocated as green belt land in the Blackpool Local Plan Part 1: Core Strategic 2012-2027. The Masterplan does not change or alter the Local Plan, rather it is a material consideration and any review of the Local Plan would take account of the Masterplan.
3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
If the document were to not be adopted/approved there would be a lack of a strategic framework to support delivery of the Enterprise Zone project and no account would be given the Masterplan in the planning process.
4.0Council Priority:
4.1The relevant Council Priority is:
“The economy: Maximising growth and opportunity across Blackpool”
5.0Background Information
5.1The area of the Enterprise Zone straddles the boundary of both Blackpool and Fylde Local Planning Authorities and although joint working arrangements are in place and evolving as necessary to support the delivery of the Enterprise Zone it was considered appropriate that both Councils undertake public consultation on the Masterplan in their respective local authority areas.
5.2The public consultation was managed as a joint undertaking commencing on 9th November 2017 and concluding on 21st December 2017. The consultation was completed in conformity with the Statement of Community Involvement (November 2014, Blackpool Council) and the Statement of Community Involvement (2015, Fylde Council). The timings, approach and method of public consultation was approved by both Councils in advance; the Executive at Blackpool Council (7 November 2017) and the Planning Committee at Fylde Council (8 November 2017). 5.3 Blackpool Council sent consultation letters to 378 properties and Fylde Council sent consultation letters to 188 properties. A joint press release was issued to local media and notices placed in two local newspapers. An additional 9 consultation letter (emails) were sent to other interested parties or bodies such as business organisations or parties who had previously expressed an interest in the Enterprise Zone.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.