BLACKPOOL AIRPORT ENTERPRISE ZONE: ANNUAL REVIEW

Agreed Executive 2 papers

AI summaryBlackpool Council Executive approves £8.55m carry forward for Airport Enterprise Zone to March 2027, notes a £2.92m whole life shortfall, and backs the approach for developing the Silicon Sands data centre campus.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCarry forward and Silicon Sands approach
Money£8.55m carry forwardApproved to end March 2027
What happens nextQuarter 2 2026Updated job census due
Who it affectsFylde coastEnterprise Zone jobs and businesses

What was decided

The Executive approved the carry forward of circa £8.55m to March 2027 and a total cumulative expenditure envelope of circa £64.85m to March 2028, alongside the approach to site assembly, investment and infrastructure needed to deliver Silicon Sands. Report P4, P12, P13, P14

The Director of Place and the Section 151 Officer were authorised to explore all methods of mitigating the forecast cash flow shortfall, with any further approvals brought back to the Executive. Report P11

Appendices 5a, 5b and 5c were treated as exempt from publication because they contain detailed costings whose release could prejudice continuing and future negotiations. Report P45

Why

To progress the Blackpool Airport Enterprise Zone masterplan in line with its aspirations, targets and key performance indicators. Report 3.1

The project has supported more than 2,700 new jobs to the end of December 2025 against a lifetime target of 5,000, with a potential cumulative Gross Value Added of circa £2bn for the local economy. Report P2, P9, P17, 6.1

Enabling infrastructure must be put in place ahead of third party commercial development, which is expected to exceed £300m of private investment and is the source of the business rates growth that funds the scheme. Report 3.2, P18, 8.1

What happens next

An updated job census will be undertaken in Quarter 2 2026. Report P2, 6.1

The three remaining Eastern Gateway development plots are to be released to the market in Quarter 2 or 3 2026, with the conceptual masterplans for Silicon Sands and the airport relocation to return to the Executive in September. Report P30, P32

A further report setting out agreed mitigations for prudential borrowing repayment costs will be submitted to a future Executive meeting, and any expenditure beyond 5% of the £54.17m already approved will also return to the Executive for approval. Report P5, P25

The money

  • £64.85m Total estimated cumulative expenditure from April 2016 to end of March 2027 Report P3, P4, P6
  • £8.55m Carry forward approved for Eastern Gateway and Airport East works into next financial year Report P4, P12
  • £2.92m Estimated whole life shortfall at today's prices to March 2041 Report P6
  • £88.15m Whole life cumulative expenditure estimate to March 2041 at present values Report P6, 8.1
  • £88m Overall estimated whole life Enterprise Zone budget envelope Report P3
  • £54.17m Planned expenditure approved by Executive on 17 March 2025 to year end 2025/26 Report P4
  • £45.62m Current anticipated spend by end of current financial year Report P4, 8.1
  • £135.00m Total Enterprise Zone cost including estimated prudential borrowing, with £46.85m of interest Report 8.3

Options considered

  • Rejected: Approve the full £88.15m required to complete all revised works in one go. Ongoing economic turbulence, demand fluctuations and new opportunities such as data centres require a more flexible, responsive approach Report 4.1
  • Rejected: Limit further activity to completing existing committed contracts with no further enabling infrastructure or operational support. Would prevent responding to short lead time occupier requirements, undermine income generation, threaten 5,000 jobs target, weaken Silicon Sands and risk airport systems failure Report 4.2

Implications

  • Financial: The whole life Enterprise Zone is forecast to deliver a lifetime cash deficit of £1.06m before mitigations, with prudential borrowing costs expected to exceed net income from retained rates and land sales over the next five years. Report 8.3, P7, P20
  • Financial: The cash flow shortfall may have to be met through Council reserves, phasing of expenditure or additional government support; the Q1 2026 delivery plan shows forecast income of £94.14m against total costs of £88.15m plus borrowing. Report P21, P22, 8.1
  • Risk: Higher levels of financial risk are noted because of the 25 year project lifespan, the impact of external influences, possible changes to the national business rates system, and uncertainty over planning consents from Fylde Borough Council. Report P8, 10.3, 10.4, 10.5
  • Legal: Construction and utility contracts, wayleaves, easements, non-disclosure agreements and specialist external legal support will be required as individual development elements progress. Report 9.1, P54, P55, P56
  • Equalities: The Enterprise Zone is the primary vehicle for creating higher value growth sector job opportunities for Blackpool's young people, contributing to the Council's economy priority. Report 5.1, 11.1
  • Climate: Solar farm, battery storage, potential offshore wind connections, district heating and low carbon data centres are expected to make a considerable contribution to the Council's net zero targets, with new commercial buildings required to meet BREEAM 'Very Good' equivalent. Report 12.1, P70, P71
  • Other: Pursuing AI Growth Zone designation for Silicon Sands is a strategic opportunity; the Council is awaiting a Development Consent Order decision on offshore wind farms and BP has withdrawn from one wind farm proposal. Report P27

Who and where

  • Job seekers and residents on the Fylde coast Report P2, P9, 11.1
  • Blackpool Airport Operations Ltd and airport tenants Report P30, 13.1
  • Third party commercial developers and occupiers of the seven Eastern Gateway plots Report P32
  • Data centre, technology and digital sector investors interested in Silicon Sands Report P13, P27
  • Fylde Borough Council as the planning authority for most Silicon Sands and airport works Report 10.5, P30
  • Offshore wind farm and solar farm developers, including those whose Development Consent Order is awaited Report P33
  • Blackpool Council itself, through potential use of reserves and prudential borrowing Report P21, P25

Timeline

  • April 2016: Enterprise Zone project start Report P3, 8.1
  • 17 March 2025: Previous Executive approval of £54.17m planned expenditure to year end 2025/26 Report P4
  • Mid January 2026: Cumulative spend reached £39.65m including airport acquisition Report 8.1
  • 6 March 2026: Scrutiny Committee Chair informed of the report Report P84
  • 16 March 2026: Executive decision taken
  • Quarter 2 2026: Updated job census of the Enterprise Zone to be undertaken Report P2, 6.1
  • Quarter 2 or 3 2026: Three remaining Eastern Gateway plots to be released to market Report P32
  • September 2026: Conceptual masterplans for Silicon Sands and airport relocation to be presented to the Executive Report P30
  • End of March 2027: End of current approval period with total expenditure of £64.85m Report P3, P12
  • End of March 2028: Some project elements, particularly Airport Infrastructure, will continue to require expenditure Report P14, 8.1
  • By 2030: Bulk of Enterprise Zone infrastructure expenditure expected to be incurred Report 8.1
  • March 2041: End of the Enterprise Zone project lifetime Report 8.1, P6

Plain English for the jargon

  • BAEZ: Blackpool Airport Enterprise Zone
  • BREEAM Very Good: A standard for assessing the environmental sustainability of buildings
  • CAP791: Civil Aviation Authority regulatory process for changes at licensed aerodromes
  • DCO: Development Consent Order, the consenting regime for nationally significant infrastructure projects
  • NPV: Net Present Value, the difference between present value of cash inflows and outflows
  • Prudential Borrowing: Borrowing by a local authority under the prudential framework, repaid from its own income streams
  • Silicon Sands: Emerging digital and data centre business campus planned on the former airport operational land
  • SUDS: Sustainable Urban Drainage Systems for managing surface water run off
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

The Executive resolved as follows: 1. To agree that Appendices 5a, 5b and 5c to the Executive report, are not for publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 as these document included detailed costings that enable the Blackpool Enterprise Zone to be viable. The publication of such information could prejudice continuing and future negotiations. 2. To note: a) The progress made on the delivery of the Enterprise Zone Masterplan including supporting more than c2700 new jobs to the end of December 2025, with an updated job census due to be undertaken Quarter 2 2026. b) The total estimated cumulative expenditure from April 2016 to end of March 2027 of circa £64.85m, which remains within the overall estimated whole life Enterprise Zone budget envelope of £88m. c) To note the funding approved on 17th March 2025 in Executive Decision outlined planned expenditure of £54.17m to year end 25/26. The current anticipated spend at the end of this financial year will be circa £45.62m, with circa £8.55m carry forward into next financial year to complete the Eastern Gateway access road and associated works, Airport East highway and utility provision. The further request for authority to spend up to £64.85m (inclusive of the £8.55m carry forward) will provide the relevant funding to commence initial implementation plans and site assembly for the delivery of Silicon Sands. d) To note that only the carry over expenditure of £8.55 million will be committed as a result of this report. Any expenditure beyond that of more than 5% of the £54.17m will be brought back to the Executive for approval along with clarity on how that will be funded. e) The forecast expenditure budget set out in Appendix 5a, to the Executive report, illustrates the position to the end of March 2027 (£64.85m). The increased whole life cumulative expenditure estimate remains at £88.15m at present values to March 2041, resulting in an estimated whole life shortfall of £2.92m at today’s prices. f) That the anticipated cost of prudential borrowing required to meet approved expenditure will exceed the net income from retained rates growth and lands sales income over the next five years and will require additional funding to be identified. g) The higher levels of financial risk associated with the overall whole life expenditure and income forecasts, given the length of the project and impact of external influences. h) The potential for the Enterprise Zone to support more than 5,000 job opportunities across the Fylde coast and generate circa £2bn of cumulative Gross Value Added and achieve a whole life operating surplus. 3. To approve: a) The authorisation of the Director of Place and the Section 151 Officer to explore all methods of mitigating the forecast cash flow shortfall as shown in Appendix 5a, to the Executive report, and seek any subsequent approvals that may be necessary. b) The carry forward of the remaining approved total budget of circa £8.55m to the end March 2027, as ...
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive

Recommendations

2.1To note:

a) The progress made on the delivery of the Enterprise Zone Masterplan including supporting more than c2700 new jobs to the end of December 2025, with an updated job census due to be undertaken Quarter 2 2026.

b) The total estimated cumulative expenditure from April 2016 to end of March 2027 of circa £64.85m, which remains within the overall estimated whole life Enterprise Zone budget envelope of £88m.

c) To note the funding approved on 17th March 2025 in Executive Decision outlined planned expenditure of £54.17m to year end 25/26. The current anticipated spend at the end of this financial year will be circa £45.62m, with circa £8.55m carry forward into next financial year to complete the Eastern Gateway access road and associated works, Airport East highway and utility provision. The further request for authority to spend up to £64.85m (inclusive of the £8.55m carry forward) will provide the relevant funding to commence initial implementation plans and site assembly for the delivery of Silicon Sands.

d) To note that only the carry over expenditure of £8.55 million will be committed as a result of this report. Any expenditure beyond that of more than 5% of the £54.17m will be brought back to the Executive for approval along with clarity on how that will be funded.

e) The forecast expenditure budget set out in Appendix 5a, illustrates the position to the end of March 2027 (£64.85m). The increased whole life cumulative expenditure estimate remains at £88.15m at present values to March 2041, resulting in an estimated whole life shortfall of £2.92m at today’s prices.

f) That the anticipated cost of prudential borrowing required to meet approved expenditure will exceed the net income from retained rates growth and lands sales income over the next five years and will require additional funding to be identified.

g) The higher levels of financial risk associated with the overall whole life expenditure and income forecasts, given the length of the project and impact of external influences.

h) The potential for the Enterprise Zone to support more than 5,000 job opportunities across the Fylde coast and generate circa £2bn of cumulative Gross Value Added and achieve a whole life operating surplus.

2.2To approve:

a) The authorisation of the Director of Place and Section 151 Officer to explore all methods of mitigating the forecast cash flow shortfall as shown in Appendix 5a and seek any subsequent approvals that may be necessary.

b) The carry forward of the remaining approved total budget of circa £8.55m to the end March 2027, as noted in para 2.1 ©.

c) The approach in relation to the site assembly, investment and development of infrastructure within the Blackpool Airport Enterprise Zone, which is required to enable the development of Silicon Sands as set out in Section 3.4.

d) The total estimated cumulative expenditure from April 2016 to end of March 2027 of circa £64.85m to March 2028 inclusive of the estimated £8.85m carry over included within the existing approval. 3.0 Reasons for recommendations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BLACKPOOL AIRPORT ENTERPRISE ZONE: ANNUAL REVIEWReport 568 KB DownloadRead as text
PDF
EX13 Blackpool Airport EZ Annual ReviewReport 583 KB Download

At this meeting

Whole meeting

Who was there

6 of 14 attended
LB
Lennox BeattieSecretary, expected
KB
Councillor Kath BensonCommittee Member, absent
NB
Councillor Neal BrookesVice Chair, present
PB
Councillor Paula BurdessCommittee Member, present
SB
Scott ButterfieldOfficer, expected
SC
Sarah ChadwickSecretary, expected
JF
Councillor Jo FarrellCommittee Member, present
JH
Councillor Jim HobsonCommittee Member, present
JH
Councillor Jane HugoVice Chair, absent
LH
Lorraine HurstSecretary, expected
NJ
Neil JackCommittee Member, expected
MS
Councillor Mark SmithCommittee Member, present

All 14 on the meeting page

On this subject at Blackpool

Search all
  1. BLACKPOOL AIRPORT ENTERPRISE ZONE: ANNUAL REVIEWThis decision
  2. Application number 25/0876 - plot 7a (blackpool airport enterprise zone) land bounded by amy johnson way and common edge road, blackpool, fy4 5dyApproved
  3. Blackpool airport enterprise zone: annual reviewAgreed
  4. Blackpool airport enterprise zone: annual reviewAgreed
  5. Blackpool airport enterprise zone: annual reviewAgreed
  6. Blackpool airport enterprise zone: annual reviewAgreed

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies