Resolved
Decision Taken The Board considered and noted the progress report and noted that the report would be used to update the LEP EZ Governance Committee on 16 May.
Blackpool, Fylde and Wyre Economic Prosperity Board noted this item on Wednesday 2 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Taken The Board considered and noted the progress report and noted that the report would be used to update the LEP EZ Governance Committee on 16 May.
I
Report to: Blackpool, Fylde and Wyre Economic Prosperity Board Report Author: Rob Green, Head of Enterprise Zones, Blackpool Council Date of Meeting: 2nd May 2018
BLACKPOOL AIRPORT ENTERPRISE ZONE – UPDATE REPORT
1. Main progress on the Enterprise Zone
a. Masterplan
Consultation on the Masterplan closed in December 2017. 117 responses were received in total and seven substantive changes were recommended to Blackpool Council Executive and Fylde Council Planning Committee.
Blackpool Council approved the Masterplan on 5th February and Fylde Council on 7th February.
Final changes are being made by Mott Macdonald and then the document will be published on the dedicated website.
b. Blackpool Airport
Blackpool Council have appointed York Aviation to prepare a strategic business plan for the airport to secure its future and maximise growth opportunities in consultation with a wide variety of interested parties. The commission is due to complete in late May. Their initial work is focused on the strategic aspects of the airport business plan and will provide the basis to look in detail at the physical interventions required to deliver a long term sustainable airport. This is likely to result in some modifications to the masterplan in terms of the current indicative locations for control tower, aprons and hangar accommodation and offshore helicopter terminal facility.
c. Marketing and Administration Officer
Interviews took place on Friday 23rd March for recruitment of a Marketing and Administration Officer and Nicole Billington commences in post on the 1st May. Reporting to the Head of Enterprise Zones she will be responsible for enquiry handling and promotion of the EZs amongst other things, and will be the primary point of contact with Marketing Lancashire.
Site signage is also being progressed and signs should be in situ in May. d. Delivery Plan
Work is continuing on the detailed EZ Delivery Plan essential to secure the outputs from the approved Masterplan in conjunction with consultants Genecon LLP. It has undergone many variations to reflect sensitivity analysis impacted by alternative delivery assumptions. The approach to modelling is credible and robust and has benefitted from input from across Blackpool and Fylde Councils.
Overall the plan, based on costings provided by Mott McDonald, suggests that capital investment in primary enabling infrastructure, including some key property acquisitions for infrastructure site assembly, together with revenue expenditure to support delivery and marketing will be many millions over the life of the EZ, with the bulk of expenditure required in the crucial early years.
The Delivery Plan provides a broad framework for one particular model of development and concludes that the EZ ‘benefit’ of retained business rates growth across both Fylde and Blackpool sectors should, over the lifetime of the EZ, just be sufficient to cover costs including the costs of prudential borrowing by Blackpool Council as EZ accountable body. The viability for the infrastructure led development proposed in the Masterplan is, however, marginal and will be reviewed on an annual basis, with each element of enabling infrastructure being subject to a detailed business case prior to approval
This work is sensitive to assumptions but represents a credible estimation of the likely cost and potential revenues of the remaining 23 years of the EZ.
The initial early year’s gap between projected cost and revenue generated will necessitate substantial levels of prudential borrowing to be undertaken by Blackpool Council and will therefore require a commitment of funds by the Council to meet the initial cost of prudential borrowing.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BLACKPOOL AIRPORT EZ PROGRESS REPORTReport | 285 KB | DownloadRead as text |
Follow Blackpool, Fylde and Wyre Economic Prosperity Board at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2024 | Appointment of chairmanThat Councillor Mark Smith be appointed Chairman for the meeting. | Decided | Open |
| 14 Mar 2024 | Exclusion of public and pressThat the public and press be excluded from the meeting whilst the agenda items 7 and 8 are considered, on the ground ... | Decided | Open |
| 14 Mar 2024 | Minutes of the last meeting held on 7 december 2023That the minutes of the meeting held on 7 December 2023 be approved and signed by the Chair as a correct record. | Approved | Open |
| 14 Mar 2024 | Fylde coast green growth updateThat the update be noted. | Noted | Open |
| 7 Dec 2023 | Appointment of chairThat Councillor Mark Smith be appointed Chair of the Blackpool Fylde and Wyre Economic Prosperity Board for the meeting | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.