The Executive agreed the recommendations as outlined above namely: 1. To note the progress against the recommendations of the Blackpool Airport Enterprise Zone Masterplan and Delivery Plan. 2. To approve a revised expenditure forecast as set out in paragraph 10.1 in respect of the previously approved £28.8 million, to fund delivery of the essential enabling infrastructure extending the original three year phase one period by one year to 2021 to reflect progress to date against the approved delivery plan, external influences beyond the direct control of the Council as Enterprise Zone accountable body and emerging opportunities within the Enterprise Zone. 3. To approve a partial review of the Enterprise Zone Masterplan and Delivery Plan to reflect changed circumstances with a further report and recommendations to be presented for consideration by March 2020. *
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Alan Cavill, Director of Communications and Regeneration
Relevant Cabinet Member Councillor Mark Smith, Cabinet Member for Business, Enterprise and Job Creation
Date of Meeting 15 July 2019
BLACKPOOL AIRPORT ENTERPRISE ZONE: ANNUAL REVIEW 1.0 Purpose of the report:
1.1On 18 June 2018 the Executive considered a report in respect of Blackpool Airport Enterprise Zone and approved seven recommendations including agreement to the Enterprise Zone delivery and marketing plans and a funding allocation of £28.8m plus the cost of Prudential Borrowing to support capital investment and associated revenue costs for an initial three year period to 2020/21 (Decision EX26/2018 refers). This report sets out the progress that has been made since then.
2.0Recommendation(s):
2.1To note the progress against the recommendations of the Blackpool Airport Enterprise Zone Masterplan and Delivery Plan.
2.2To approve a revised expenditure forecast as set out in paragraph 10.1 in respect of the previously approved £28.8 million, to fund delivery of the essential enabling infrastructure extending the original three year phase one period by one year to 2021 to reflect progress to date against the approved delivery plan, external influences beyond the direct control of the Council as Enterprise Zone accountable body and emerging opportunities within the Enterprise Zone.
2.3To approve a partial review of the Enterprise Zone Masterplan and Delivery Plan to reflect changed circumstances with a further report and recommendations to be presented for consideration by March 2020.
3.0Reasons for recommendation(s):
Since the approval significant progress has been made with the delivery of the Enterprise Zone Delivery Plan highlights of which have been included in paragraph 5.1.
Nevertheless, as with any major regeneration programme there have been some delays and changes. It is beneficial to explain to Executive the reasoning behind the delays and the actions being taken to minimise, mitigate and work round them.
These unavoidable delays have resulted in an underspend against the programme in the first year but it is expected that it will be possible to recover to a position close to the original forecasts by the end of the initial three year period, with a small amount of the expenditure rolling over into 2021/22. It is for this reason that approval is sought to extend the phase one programme by one year.
It is still anticipated that the programme can still be undertaken within the originally approved funding of £28.8m. It is however, likely that some expenditure will run beyond the original three year programme and up to a further 12 months may be needed to complete the phase.
In light of the potential impacts of the change of ownership of the former bomber factory, the completion of phase one on the sports village, highway design works and the anticipated recommendations from the data centre feasibility study, it is proposed that the masterplan be reworked and the delivery plan and financial forecasts be updated with a view to bringing a full report and recommendations back to Executive in early 2020. This work would see relatively light touch changes and would be funded from within existing allocations for specialist consultant expenditure
3.2a Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?
3.2b Is the recommendation in accordance with the Council’s approved budget? Yes
3.3Other alternative options to be considered:
Approvals obtained in June 2018 were for a three year programme of activity. This report identifies progress in the first year and makes recommendations for a further review of both masterplan and delivery plan to reflect significant changes impacting on ability and opportunity to deliver in accordance with these initial approvals.
4.0Council priority:
4.1The relevant Council priority is: “The economy: Maximising growth and opportunity across Blackpool”. 5.0 Background Information
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.