The Executive resolved as follows: 1. To agree that Appendix 5a, to the Executive report, financial detailed figures is not public for publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 as the costings would undermine the Council’s position in continuing and future negotiations. 2. To note the progress made on the delivery of the Enterprise Zone Masterplan. 3. To approve the revised draft Masterplan, with its proposed two phase delivery strategy for further consultation and presentation to the Blackpool Fylde and Wyre Economic Prosperity Board and the Local Enterprise Partnerships Enterprise Zone Governance Sub-Committee for approval. 4. To note the updated detailed expenditure and income forecast as set out in the revised delivery plan and summarised at paragraph 6.12 in respect of the overall project and the anticipated expenditure to the end of the project in 2041 of £72.6m at present value. 5. To confirm the forecast expenditure of up to £19.2m plus associated costs of Prudential Borrowing for the period to the end of financial year 2021/22, to enable continued development of the Phase 1 enabling infrastructure, together with site assembly and preparatory works for phase two which are within the terms of the existing approval . 6. To reconfirm and note the delegation to the Chief Executive, after consultation with the Leader of the Council, to authorise expenditure on individual schemes and property acquisitions within the Enterprise Zone and inter-related airport holdings of Blackpool Airport Properties Ltd (BAPL).
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Alan Cavill, Director of Communications and Regeneration
Relevant Cabinet Member: Cllr Mark Smith, Executive Member for Business, Enterprise and Job Creation
Date of Meeting 7 December 2020
BLACKPOOL AIRPORT ENTERPRISE ZONE: ANNUAL REVIEW 1.0 Purpose of the report:
1.1This report sets out the further progress in the delivery of the Enterprise Zone, revisions to the Masterplan and Delivery Plan and outlines activity planned for the next twelve months. The still emerging economic impacts of the Covid-19 pandemic and the uncertainties which surround Brexit make future forecasting and planning of Enterprise Zone investment difficult and therefore an enhanced risk-based approach to delivery is being adopted for the next twelve months until greater certainty exists.
2.0Recommendation(s):
2.1To note the progress made on the delivery of the Enterprise Zone Masterplan.
2.2To approve the revised draft Masterplan, with its proposed two phase delivery strategy for further consultation and presentation to the Blackpool Fylde and Wyre Economic Prosperity Board and the Local Enterprise Partnerships Enterprise Zone Governance Sub-Committee for approval.
2.3To note the updated detailed expenditure and income forecast as set out in the revised delivery plan and summarised at paragraph 6.12 in respect of the overall project and the anticipated expenditure to the end of the project in 2041 of £72.6m at present value.
2.4To confirm the forecast expenditure of up to £19.2m plus associated costs of prudential borrowing for the period to the end of financial year 2021/22, to enable continued development of the Phase 1 enabling infrastructure, together with site assembly and preparatory works for phase two which are within the terms of the existing approval .
2.5To reconfirm and note the delegation to the Chief Executive, after consultation with the Leader of the Council, to authorise expenditure on individual schemes and property acquisitions within the Enterprise Zone and inter-related airport holdings of Blackpool Airport Properties Ltd (BAPL). 3.0 AReasons for recommendation(s):
3.1Since the original approval in June 2018 of the Masterplan and Delivery Plan (based on three phases which allocated up to £28.8m to deliver Phase 1 works and enabling property acquisition), and the first annual review in July 2019 which agreed an extension of the Phase 1 expenditure programme to 2021, a number of factors influencing delivery of the EZ have altered. This is unsurprising as whilst significant progress has been made with the EZ Delivery Plan it is inevitable that with a long-term regeneration programme of this scale and complexity there will be many changes over its duration, hence the commitment to an annual review.
This last year has seen a specific intensity of change, additionally complicated by the Covid-19 pandemic which has itself delayed the scheduled annual review (from July). These changes have also necessitated the preparation of both a revised Masterplan and Delivery Plan.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
4.1a) Maintain the existing approval for expenditure of up to £28.8m and extend the timeframe for undertaking this expenditure by a further two years to the end of FY22/23. However, this would not be sufficient to complete the whole of the revised Phase 1 works which will be completed only by 2025/6 and would create difficulty in committing to some elements of the extended Phase 1 works where these might extend beyond FY22/23.
b) Approve the full £72.6m required to complete all the revised Phase 1 and Phase 2 works In the light of the current economic turbulence there is a high probability that there will be delays and reduced demand as well as new emerging opportunities such as the data management sector which will require a more flexible and responsive approach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.