Resolved
Resolved : That the Chair of the Audit Committee give further consideration as to the role of the Committee in relation to contract management and procurement arrangements , in conjunction with [name removed], Head of Audit and Risk.
Audit Committee decided this item on Thursday 29 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved : That the Chair of the Audit Committee give further consideration as to the role of the Committee in relation to contract management and procurement arrangements , in conjunction with [name removed], Head of Audit and Risk.
Report to: AUDIT COMMITTEE Relevant Officer: Steve Thompson, Director of Resources
Date of Meeting: 29 April 2021
ANNUAL GOVERNANCE STATEMENTS - CONTRACT MANAGEMENT AND PROCUREMENT ARRANGEMENTS 1.0 Purpose of the report:
1.1To provide updates in respect of Contract Management and Procurement arrangements from the Annual Governance Statements.
2.0Recommendation(s):
2.1To note the updates in respect of Contract Management and Procurement arrangements from the Annual Governance Statements.
3.0Reasons for recommendation(s):
3.1The Procurement Team has undertaken a number of actions in relation to Contract Management and Procurement arrangements as outlined in section 6 of this report.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
4.1None
5.0Council priority:
5.1The relevant Council priorities are: The economy: Maximising growth and opportunity across Blackpool. Communities: Creating stronger communities and increasing resilience.
6.0Background information
6.1In 2018/2019 an action to ‘Strengthen contract management across the Council including improved measurement of social value, launch of an iPool course and exploration of software tools’ was identified. The following actions have been undertaken following those recommendations: 6.2 In January 2020 a dedicated Social Value Co-ordinator post was established on a two-year fixed term basis.
A number of Social Value documents have been reviewed and updated. On Monday 12 April 2021 Executive approval was received for the updated Social Value Policy and the Suppliers Charter. In addition the Social Value Guide issued to all Suppliers at tender stage has been updated. The revised documents will be issued with all tender opportunities with immediate effect.
A set of Blackpool Social Value Themes, Outcomes and Measures are now being developed to assist in focussed tracking and monitoring of social value delivered by providers to the Council.
In spite of the impacts of the Covid-19 pandemic, the Social Value Co-ordinator has been in liaison with a number of key providers to ensure the continued delivery of social value.
6.3A Contract Management iPool training course has been developed. To date 32 members of staff have completed the training. Further work will be undertaken to target areas of the Council where staff should be actively encouraged to complete the training. In addition, further work will be undertaken to promote and market the course internally.
A trial of the contract management module on the Council’s e-tendering portal ‘The Chest’ was undertaken with staff from the Council’s Contract Monitoring Officers in Adults and Children’s Social Care. The trial demonstrated that the system did not meet the requirements of those services who participated.
6.4In 2019/2020 an action to ‘continue to explore procurement opportunities with local suppliers and look to provide training to local suppliers and Elected Members on procurement’ was identified. The following actions have been undertaken following the recommendation:
Engagement with suppliers, including local suppliers takes place where appropriate and where circumstances permit on specific tender opportunities.
Often stakeholders do not allow sufficient time between requiring a contractor to be in place and making an initial approach to the procurement team to enable supplier engagement to take place.
The impacts of the Covid-19 pandemic has made engagement with local suppliers more challenging.
A training event for Elected Members in relation to Procurement is scheduled for January 2022.
6.5Does the information submitted include any exempt information? No
7.0List of Appendices:
7.1None
8.0Financial considerations:
8.1None 9.0 Legal considerations:
9.1None
10.0Risk management considerations:
10.1Should effective contract management not take place there is a risk that the Council may be exposed to poor performance, impacting on delivery of key projects.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ANNUAL GOVERNANCE STATEMENTS: CONTRACT MANAGEMENT AND PROCUREMENT ARRANGEMENTSReport | 3 pages | DownloadRead as text |
Follow Audit Committee at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. | Approved | Open |
| 24 Sep 2026 | Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - creditor payment financial control assurance testingTo note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing. | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. | Noted | Open |
| 24 Sep 2026 | Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.