The Executive resolved as follows : To recommend to Council: To approve the Capital Programme for 2022/23 as set out in this report and in Appendices 4a and 4b, to the Executive report. To agree that Executive approval will continue to be required for all Prudential borrowing schemes (reference paragraph 6.10). To approve the Single Capital Pot approach as outlined with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11). To agree the Capital Prudential Indicators as identified in Appendix 4c, to the Executive report.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Steve Thompson, Director of Resources
Relevant Cabinet Member Councillor Lynn Williams, Leader of the Council
Date of Meeting 7 February 2022
CAPITAL PROGRAMME 2022/23 TO 2024/25 1.0 Purpose of the report:
1.1To consider the 2022/23, 2023/24 and 2024/25 Capital Programme.
2.0Recommendation(s):
2.1To recommend to Council:
1. To approve the Capital Programme for 2022/23 as set out in this report and in Appendices 4a and 4b.
2. To agree that Executive approval will continue to be required for all Prudential borrowing schemes (reference paragraph 6.10).
3. To approve the Single Capital Pot approach as outlined with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11).
4. To agree the Capital Prudential Indicators as identified in Appendix 4c.
3.0Reasons for recommendation(s):
3.1To ensure delivery of the Council’s key objectives and priorities in line with the other elements of the Council’s budget framework.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council? 3.3 Is the recommendation in accordance with the Council’s approved budget? Not applicable - the report once approved will become part of the Council’s new approved budget 4.0 Other alternative options to be considered:
4.1None.
5.0Council priority:
5.1The relevant Council priority is: “The economy: Maximising growth and opportunity across Blackpool”
6.0Background information
6.1The Council’s 2022/23 Capital Programme runs concurrently with the 2022/23 General Fund Revenue Budget. Capital schemes usually extend over a number of years and for that reason the programme projects forward indicative spending for 3 years. This report updates the programme reported in last year’s budget and seeks to ensure that capital expenditure is allocated to areas that will contribute to meeting the Council’s priorities. The Capital Programme submitted for approval for 2022/23 is £81m and over a three-year period is estimated at £263.5m (See Appendix 4a and 4b).
6.2The 2023/24 and 2024/25 programmes have been drawn up based upon known allocations and provisional bids. Government announcements in respect of some allocations have once again been delayed this year, due to this situation Blackpool Council has chosen to include estimates of these figures. An update will be provided to Executive once these allocations have been announced. These will be reviewed as part of the budget processes for 2023/24 and 2024/25 in the light of changing priorities and final funding levels, which means that no commitment can be made as yet in respect of those new schemes identified for 2023/24 and 2024/25.
6.3The Council has suffered from severe cuts in capital funding. It has continued to be proactive in seeking additional funding for schemes, and is seeking to take advantage of low level interest rates to facilitate investment and regeneration of the town.
6.4The status of the Capital Programme is reported monthly to the Corporate Leadership Team (CLT) and the Executive as well as the relevant Scrutiny Committees. 6.5 The Capital Programme now submitted is consistent with that agreed for 2021/22. It includes identified commitments for housing developments. The scale of these commitments means that there are very limited resources to deliver additional schemes that are not fully funded.
6.6The Capital Programme prepared for 2022/23 does not include budgeted expenditure that has previously been approved by Executive. Blackpool Council has approximately £38m available for capital projects, e.g. The Museum, Houndshill Phase 2 and Central Business District phase 2, that has been approved in previous years but not yet expended. The total capital budget therefore for 2022/23 is in reality approximately £118.8m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.