CAPITAL PROGRAMME 2024/25 TO 2026/27

Approved Executive 4 papers

Executive approved this item on Monday 5 February 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

The Executive resolved to recommend Council as follows: To approve the Capital Programme for 2024/25 and exemplifications for 2025/26 and 2026/27 as set out at Appendix 6a, to the Executive report To agree that Executive approvals will continue to be required for all prudential borrowing schemes (reference paragraph 6.10). To agree to continue with the Single Capital Pot approach as outlined in Section 6 with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11). To approve the Capital Prudential Indicators as identified in Appendix 6b, to the Executive report.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive, 11 pages

Report to: EXECUTIVE Relevant Officer: Steve Thompson, Director of Resources

Relevant Cabinet Member Councillor Lynn Williams, Leader of the Council

Date of Meeting 5 February 2024

CAPITAL PROGRAMME 2024/25 TO 2026/27 1.0 Purpose of the report:

1.1To consider recommending to Council the 2024/25, 2025/26 and 2026/27 Capital Programmes.

2.0Recommendation(s):

2.1To recommend to Council:

1. To approve the Capital Programme for 2024/25 and exemplifications for 2025/26 and 2026/27 as set out at Appendix 6a

2. To agree that Executive approvals will continue to be required for all prudential borrowing schemes (reference paragraph 6.10).

3. To agree to continue with the Single Capital Pot approach as outlined in Section 6 with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11).

4. To approve the Capital Prudential Indicators as identified in Appendix 6b.

3.0Reasons for recommendation(s):

3.1To ensure delivery of the Council’s key objectives and priorities in line with the other elements of the Council’s budget framework.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council? 3.3 Is the recommendation in accordance with the Council’s approved budget? Not applicable - the report once approved will become part of the Council’s new approved budget 4.0 Other alternative options to be considered:

4.1None.

5.0Council priority:

5.1The relevant Council priority is: “The economy: Maximising growth and opportunity across Blackpool”

6.0Background information

6.1The Council’s 2024/25 Capital Programme runs concurrently with the 2024/25 revenue budget and reports on both are submitted to this meeting for approval. Capital schemes usually extend over a number of years and for that reason the programme projects forward indicative spending for 3 years. This report updates the programme reported in last year’s budget and seeks to ensure that capital expenditure is allocated to areas that will contribute to meeting the Council’s priorities, the report also takes into account the effects of the impacts of Covid, labour shortfalls, supply chain bottlenecks and inflationary pressures on progress of the programme. The capital programme submitted for approval for 2024/25 is £25.6m and over a three-year period is estimated at £143.3m (See Appendix 6a).

6.2The 2025/26 and 2026/27 programmes have been drawn up based upon known allocations and provisional bids. Government announcements in respect of some allocations have once again been delayed this year due to this situation Blackpool Council has chosen to include estimates of these figures. An update will be provided to Executive once these allocations have been announced. These will be reviewed as part of the budget processes for 2025/26 and 2026/27 in the light of changing priorities and final funding levels, which means that no commitment can be made as yet in respect of those new schemes identified for 2025/26 and 2026/27.

6.3The Council has suffered from severe cuts in capital funding. It has continued to be proactive in seeking additional funding for schemes, and has been the beneficiary of a number of multi- million pound grants in recent years.

6.4The status of the Capital Programme is reported monthly to the Corporate Leadership Team (CLT) and the Executive as well as the Tourism, Economy and Communities Scrutiny Committee. 6.5 The Capital Programme now submitted is consistent with that agreed for 2023/24. It includes identified commitments for housing developments. The scale of these commitments means that there are very limited resources to deliver additional schemes that are not fully funded.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 6aAppendix 6a 9 pages Download
PDF
Appendix 6bAppendix 6b 1 pages Download
PDF
CAPITAL PROGRAMME 2024/25 TO 2026/27Report 11 pages DownloadRead as text
PDF
EX10 Capital ProgrammeReport 11 pages Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
LB
Lennox BeattieSecretary, expected
KB
Councillor Kath BensonCommittee Member, present
NB
Councillor Neal BrookesCommittee Member, present
PB
Councillor Paula BurdessCommittee Member, present
SC
Sarah ChadwickSecretary, expected
JF
Councillor Jo FarrellCommittee Member, present
PG
Councillor Paul GalleyCommittee Member, in attendance
JH
Councillor Jim HobsonCommittee Member, present
JH
Councillor Jane HugoCommittee Member, present
PH
Councillor Peter HunterCommittee Member, in attendance
LM
Councillor Laura MarshallCommittee Member, in attendance
MS
Councillor Michele ScottCommittee Member, in attendance

All 15 on the meeting page

On this subject at Blackpool

Search all
  1. CAPITAL PROGRAMME 2024/25 TO 2026/27This decision
  2. Capital programme 2026/27 to 2028/29Approved
  3. Capital programme 2025/26 to 2027/28Approved
  4. Capital programme 2023/24, 2024/25 and 2025/26Approved
  5. Capital programme 2022/23 to 2024/25Approved
  6. Capital programme 2021/2022Approved

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies