The Executive resolved to recommend Council as follows: To approve the Capital Programme for 2024/25 and exemplifications for 2025/26 and 2026/27 as set out at Appendix 6a, to the Executive report To agree that Executive approvals will continue to be required for all prudential borrowing schemes (reference paragraph 6.10). To agree to continue with the Single Capital Pot approach as outlined in Section 6 with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11). To approve the Capital Prudential Indicators as identified in Appendix 6b, to the Executive report.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Steve Thompson, Director of Resources
Relevant Cabinet Member Councillor Lynn Williams, Leader of the Council
Date of Meeting 5 February 2024
CAPITAL PROGRAMME 2024/25 TO 2026/27 1.0 Purpose of the report:
1.1To consider recommending to Council the 2024/25, 2025/26 and 2026/27 Capital Programmes.
2.0Recommendation(s):
2.1To recommend to Council:
1. To approve the Capital Programme for 2024/25 and exemplifications for 2025/26 and 2026/27 as set out at Appendix 6a
2. To agree that Executive approvals will continue to be required for all prudential borrowing schemes (reference paragraph 6.10).
3. To agree to continue with the Single Capital Pot approach as outlined in Section 6 with a top slice of 12.5% to allow for investment in key priority areas and overspends that are not otherwise fundable (reference paragraph 6.11).
4. To approve the Capital Prudential Indicators as identified in Appendix 6b.
3.0Reasons for recommendation(s):
3.1To ensure delivery of the Council’s key objectives and priorities in line with the other elements of the Council’s budget framework.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council? 3.3 Is the recommendation in accordance with the Council’s approved budget? Not applicable - the report once approved will become part of the Council’s new approved budget 4.0 Other alternative options to be considered:
4.1None.
5.0Council priority:
5.1The relevant Council priority is: “The economy: Maximising growth and opportunity across Blackpool”
6.0Background information
6.1The Council’s 2024/25 Capital Programme runs concurrently with the 2024/25 revenue budget and reports on both are submitted to this meeting for approval. Capital schemes usually extend over a number of years and for that reason the programme projects forward indicative spending for 3 years. This report updates the programme reported in last year’s budget and seeks to ensure that capital expenditure is allocated to areas that will contribute to meeting the Council’s priorities, the report also takes into account the effects of the impacts of Covid, labour shortfalls, supply chain bottlenecks and inflationary pressures on progress of the programme. The capital programme submitted for approval for 2024/25 is £25.6m and over a three-year period is estimated at £143.3m (See Appendix 6a).
6.2The 2025/26 and 2026/27 programmes have been drawn up based upon known allocations and provisional bids. Government announcements in respect of some allocations have once again been delayed this year due to this situation Blackpool Council has chosen to include estimates of these figures. An update will be provided to Executive once these allocations have been announced. These will be reviewed as part of the budget processes for 2025/26 and 2026/27 in the light of changing priorities and final funding levels, which means that no commitment can be made as yet in respect of those new schemes identified for 2025/26 and 2026/27.
6.3The Council has suffered from severe cuts in capital funding. It has continued to be proactive in seeking additional funding for schemes, and has been the beneficiary of a number of multi- million pound grants in recent years.
6.4The status of the Capital Programme is reported monthly to the Corporate Leadership Team (CLT) and the Executive as well as the Tourism, Economy and Communities Scrutiny Committee. 6.5 The Capital Programme now submitted is consistent with that agreed for 2023/24. It includes identified commitments for housing developments. The scale of these commitments means that there are very limited resources to deliver additional schemes that are not fully funded.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.