Resolved
That the report on progress against the recommendations made in the Internal Audit of Energy Management be noted.
Audit Committee noted this item on Thursday 19 October 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report on progress against the recommendations made in the Internal Audit of Energy Management be noted.
1.1To consider a progress report on the recommendations made in the internal audit report relating to Energy Management issued on the 4 October 2022.
2.0Recommendation(s):
2.1To consider the actions being implemented to address the audit recommendations relating to the Energy Management audit.
3.0Reasons for recommendation(s):
3.1To enable Audit Committee to consider an update and progress report on the audit recommendations.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
4.1None
5.0Council priority:
5.1This audit impacts on the Council’s organisational resilience priority.
6.0Background and Key Information
6.1The Energy Management Team is responsible for administering energy supplies, including the validation and payment of invoices, to schools, academies, wholly owned companies and some private organisations that occupy Council owned buildings.
The previous energy management review in 2021/22 identified a number of recommendations which resulted in inadequate assurance being given. In order to ensure that the actions were appropriately implemented a detailed follow-up of all recommendations was carried out in 2022/23.
6.2The scope and assurance statement of the audit was as follows:
Scope
The scope of this audit was to assess whether the recommendations of last year’s audit review have been appropriately addressed.
Assurance Statement
We consider that the controls in place remain inadequate given that there are still two outstanding priority one recommendations although we acknowledge that progress is being made to address these issues.
6.3Does the information submitted include any exempt information? No
7.0List of Appendices:
7.1Appendix 3(a): Internal Audit Recommendations and Agreed Actions.
8.0Financial considerations:
8.1The controls being implemented will be done so within current budget constraints.
9.0Legal considerations:
9.1Risks need to be effectively managed in order to comply with relevant legislation.
10.0Risk management considerations:
10.1To enable the Audit Committee to gain assurance that risks are being effectively managed.
11.0Equalities considerations and the impact of this decision for our children and young People:
11.1Where equality analysis is appropriate these will have been undertaken whilst making decisions relating to the subject.
12.0Sustainability, climate change and environmental considerations:
12.1Any matters relating to sustainability, climate change and environmental considerations will be considered when making decisions relating to the subject. 13.0 Internal/external consultation undertaken:
13.1The progress report has been prepared in conjunction with the relevant Head of Service and Chief Officer.
14.1None. Appendix 3(a) - Agreed Action Plan
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT FOLLOW-UP: ENERGY MANAGEMENTReport | 9 pages | DownloadRead as text |
Follow Audit Committee at Blackpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. | Approved | Open |
| 24 Sep 2026 | Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - creditor payment financial control assurance testingTo note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing. | Noted | Open |
| 24 Sep 2026 | Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. | Noted | Open |
| 24 Sep 2026 | Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.