MULTIVERSITY : APPROPRIATION OF LAND FOR PLANNING PURPOSES BOUNDED BY GEORGE STREET, GROSVENOR STREET, MILBOURNE STREET AND COOKSON STREET, BLACKPOOL
AgreedExecutive3 papers
AI summaryBlackpool Borough Council's Executive delegated authority to appropriate land for Multiversity Phase 1 and override easements and other rights. Owners of affected third party rights may claim compensation, and the Director of Place may settle claims. [D] [2.1] [6.11] [D] [2.2] [8.1]
Written from the decision and the officer reportPDF Pro
OutcomeAgreedExisting rights may be overridden, subject to compensation. [6.11]
MoneyCompensation may be payable [8.1]Successful claims are assessed by loss in value. [6.13]
What happens nextAuthority delegated to officers [D]Director of Place and Head of Legal Services. [D]
Who it affectsMultiversity Phase 1 development [3.1]Existing easements and rights may be overridden. [6.11]
What was decided
The Executive delegated authority to the Director of Place to appropriate the Subject Land for planning purposes under section 122 of the Local Government Act 1972. The delegation also covers sections 203 and 204 of the Housing and Planning Act 2016. Report 2.1
The Executive delegated authority to the Director of Place to settle any section 204 compensation claims arising from the section 203 overriding power. Report 2.2
The Executive authorised the Head of Legal Services to complete the documentation needed for the appropriation and any related compensation settlements. Report 2.3
Why
The Council needs to override easements and other rights so the Subject Land can begin development with the Multiversity Phase 1 building. Report 3.1, 6.7
The four statutory requirements for section 203 are met. The Council considers the powers proportionate and justified because they support the area's economic, social and environmental wellbeing. Report 6.14, P5, 11.4
Using the powers reduces the risk of an injunction and converts affected rights into compensation. Without them, significant delays could put the project or elements of it at risk. Report P6, P11
What happens next
The Director of Place is authorised to appropriate the Subject Land under section 122 and invoke sections 203 and 204 of the Housing and Planning Act 2016. Report 2.1
The Director of Place is authorised to settle any compensation claims made under section 204. Report 2.2
The Head of Legal Services is authorised to enter the documents needed to give effect to the appropriation and any related claim settlements. Report 2.3
Options considered
Chosen: Appropriate the Subject Land and invoke section 203. All four statutory requirements are met, and the powers are needed to facilitate the Multiversity development. Report 6.14, 3.1
Rejected: Negotiate and acquire any right to light by private agreement. Relevant parties would first need to be identified. Not invoking section 203 could delay delivery and put the project or elements of it at risk. Report 4.1, 24.1, P77
Rejected: Do not invoke section 203. The Multiversity scheme would be severely delayed or prevented from implementation. Report 10.1, P77
Implications
Financial: Owners of third party rights whose rights are interfered with or breached can claim compensation. Successful claims are assessed on the basis of loss in value. Report 8.1, 6.13
Legal: Appropriation under section 122 enables section 203 to override easements and other rights, subject to compensation under section 204. The Head of Legal Services may execute documents needed to give effect to the appropriation. Report 9.1, 6.11, 2.3
Risk: Without the appropriation and section 203 powers, the Multiversity scheme could be severely delayed or prevented from implementation. Report 10.1, P77
Equalities: The Council considers the interference necessary and proportionate, with the public interest outweighing private interests. It does not consider the development would cause undue, unacceptable or unlawful discrimination or inequitable access or treatment based on protected characteristics. Report 11.2, 11.4, 11.5
Climate: There are no direct sustainability, climate change or environmental considerations. Report 12.1
Other: The decision supports the Council priority of maximising growth and opportunity across Blackpool. Report 5.1, P14
Other: The statutory procedures do not require external consultation for appropriation for planning purposes. Report 13.1
Other: The recommendation is not contrary to a Council approved plan or strategy and is in accordance with the approved budget. Report 3.2, 3.3
10 May 2024: Hybrid planning consent was granted for the education led mixed use development. Report 6.4
30th January 2025: The Compulsory Purchase Order was confirmed by the Inspector, following the Secretary of State's authorisation. Report 6.1
5 March 2025: The General Vesting Orders for properties acquired by agreement were dated. Report 6.2
27 May 2025: The Planning Committee approved reserved matters for the Phase 1 height and external appearance. Report 6.5
3rd July 2025, 1st August 2025 and 8th September 2025: Ownership of further land passed to the Council under General Vesting Declarations. Report 6.1
10 November 2025: The Executive made the appropriation decision. Report 21.1
11 November 2025: The decision was published. Report 23.1
Plain English for the jargon
Subject Land: The land required for the Multiversity development and shown in Appendix 7a. [6.1] [7.1]
Appropriation: Changing the purpose for which the Council holds land so planning powers can be used. [6.10]
Easement: An existing right over the Subject Land that section 203 can override. [6.11]
Right to light: A right concerning light that the Council could acquire by negotiation and private agreement. [4.1]
Section 122: The Local Government Act 1972 power used to appropriate Council owned land for planning purposes. [6.10]
Section 203: The Housing and Planning Act 2016 power to override easements and other rights, subject to compensation. [6.11]
Section 204: The compensation provision used when section 203 interferes with rights. [6.11] [6.13]
Reserved matters: Planning details approved for the Phase 1 height and external appearance. [6.5]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
The Executive agreed the recommendations as outlined above namely: 1. To delegate authority to the Director of Place, to appropriate for planning purposes the Subject Land under section 122 of the Local Government Act 1972 hereby invoking section 203 and section 204 of the Housing and Planning Act 2016. 2. To delegate authority to the Director of Place to deal with the settlement of any claims for compensation made pursuant to section 204 of the Housing and Planning Act 2016 that may arise by virtue of the operation of the overriding power contained in Section 203 of the Housing and Planning Act 2016. 3. To authorise the Head of Legal Services to enter into any such documentation as may be necessary to give effect to or flowing from the appropriation for planning purposes of the Subject Land, including entering into any documentation in respect of the settlement of any claims under section 204 of the Housing and Planning Act 2016.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
2.1To delegate authority to the Director of Place, to appropriate for planning purposes the Subject Land under section 122 of the Local Government Act 1972 hereby invoking section 203 and section 204 of the Housing and Planning Act 2016.
2.2To delegate authority to the Director of Place to deal with the settlement of any claims for compensation made pursuant to section 204 of the Housing and Planning Act 2016 that may arise by virtue of the operation of the overriding power contained in Section 203 of the Housing and Planning Act 2016.
2.3To authorise the Head of Legal Services to enter into any such documentation as may be necessary to give effect to or flowing from the appropriation for planning purposes of the Subject Land, including entering into any documentation in respect of the settlement of any claims under section 204 of the Housing and Planning Act 2016. 3.0 Reason for recommendations
3.1To facilitate the commencement of Multiversity development by overriding easements and other rights over the Subject Land to allow the development of the Subject Land to commence with the Multiversity Phase 1 building.
The engagement of these powers is considered to be proportionate and justified, to facilitate the development of the Subject Land thereby achieving the promotion and/or the improvement of the economic social and environmental well-being of the area.
Appropriation for planning purposes of the Subject Land under section 122 of the Local Government Act 1972 and any subsequent use of section 203 and section 204 powers pursuant to the Housing and Planning Act 2016 will enable the development to proceed without the risk of an injunction and convert any rights into compensation.
3.2Is the recommendation contrary to a plan or strategy approved by the Council? No
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered
4.1Subject to being able to identify any such parties, including any such potential party, the Council could agree by negotiation and by way of private treaty the acquisition of any right to light which may exist in respect of the development of the Subject Land thereby meaning it will not be necessary to invoke section 203 of the Housing and Planning Act 2016.
Failure to invoke Section 203 of the Housing and Planning Act 2016 and subsequently convert any existing rights into compensation could result in significant delays to delivery of the development, putting the whole project or elements of it in jeopardy.
5.0Council priority
5.1The relevant Council priority is:
‘The economy: Maximising growth and opportunity across Blackpool’
6.0Background and key information
6.1The Executive will be aware that the land required for the Multiversity development was acquired over time with some of the land in Council ownership, other land acquired by agreement and other land vested in the Council’s name under General Vesting Declarations on 3rd July 2025 , 1st August 2025 and 8th September 2025 following confirmation of the Blackpool Borough Council (Multiversity) Compulsory Purchase Order 2024 which was confirmed by the Inspector authorised by the Secretary of State on 30th January 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
MULTIVERSITY : APPROPRIATION OF LAND FOR PLANNING PURPOSES BOUNDED BY GEORGE STREET, GROSVENOR STREET, MILBOURNE STREET AND COOKSON STREET, BLACKPOOLReport
7MULTIVERSITY : APPROPRIATION OF LAND FOR PLANNING PURPOSES BOUNDED BY GEORGE STREET, GROSVENOR STREET, MILBOURNE STREET AND COOKSON STREET, BLACKPOOLThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.