PRIDE IN PLACE PROGRAMME FUND and PRIDE IN PLACE IMPACT FUND
AgreedExecutive4 papers
AI summaryBlackpool Council's Executive accepted £20m for Little Layton and Little Carleton and £1.5m for wider Blackpool projects [D] [P15] [P16]. A Neighbourhood Board and Chair will shape the programme, while the Director of Place, in consultation with the Leader, will make final Impact Fund allocations [D] [P21].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedBoard, legal documents and external funding authorised [D]
Money£20m and £1.5m [P10]Programme over 10 years; Impact by March 2027 [P15] [P16]
What happens nextFurther report to Executive [D]Officers develop options, board and Chair arrangements [D]
Who it affectsNot stated
What was decided
The Executive agreed to accept both funds. Officers will explore how to use them with key stakeholders, including local MPs.
Final Impact Fund allocations were delegated to the Director of Place, in consultation with the Leader of the Council. The Executive approved the approach for developing the Programme Fund, including appointing a Neighbourhood Board and Chair, with a further report for final confirmation.
The Head of Legal Services was authorised to complete the required legal documents for both funds. Third party organisations may receive funding, subject to suitable procurement.
Why
Accepting the funds avoids returning them to Central Government and losing benefits for Blackpool's community and wider economy. Report 3.1
The decision supports the Council's priorities of economic growth and stronger, more resilient communities. Report 5.1
The Programme Fund gives local people a role in shaping their neighbourhood. The Impact Fund supports immediate, visible improvements to high streets and community spaces. Report P21, P31
What happens next
Council officers will explore options for using both funds with key stakeholders, including local MPs.
The Council will appoint a Neighbourhood Board and an independent Chair. The Executive will receive a further report when the arrangements are ready for final confirmation. Report P21
Legal Services will review both Memorums of Understanding and may need grant funding agreements for external partners. The Council will submit progress, spend and financial reports. Any external organisation funding will be subject to suitable procurement. Report 9.1, P36
The money
£20m Pride in Place Programme allocation for Little Layton and Little Carleton Report P15
£1.5m Pride in Place Impact Fund for wider Blackpool use, with draft schemes in Claremont, Town Centre, Revoe and South Shore Report P16, P35
£2m a year Programme funding anticipated from April 2026 over 10 years Report P15, P40
£750k in 2025/6 and £750k in 2026/7 Impact Fund spending in the two years Report P16
50% Impact Fund allocation in each of the two years Report 8.1
Approximately 37% Programme revenue funding, focused on the defined area Report P15
100% Impact Fund allocation is entirely capital funding Report 8.1
£5 billion UK Government Pride in Place Strategy Report 6.1
Options considered
Chosen: Accept both funds and develop local arrangements. This avoids returning the funding and losing benefits for the community and wider economy. Report 3.1
Rejected: Do nothing. Funding awards would not be accepted and would be returned to Central Government, causing a loss of funding for the Borough. Report 4.1, 24.1
Chosen: Authorise potential funding to external organisations
Implications
Financial: The Impact Fund must be spent by March 2027 and is 100% capital funding. Project and programme management costs must come from it. The Programme Fund runs from April 2026 over 10 years, with £2m a year anticipated, and an agreed management allocation would cover human resource costs if the Council oversees it. The Council is encouraged to seek match funding and leverage other support. Report P15, P16, P40, 8.1, P34
Legal: Legal Services must review both Memorums of Understanding. Some grant agreements with external delivery partners may need to mirror the Council's MHCLG grant terms. The Council's power under the Localism Act 2011 extends to acts an individual can do, unless prohibited. Report 9.1, P44
Risk: The main risks are eligible spend, fraud management and due diligence. A risk register will be established for both funds. Report P45
Equalities: Community engagement and equalities of access and benefit are key considerations for both schemes.
Climate: Climate impacts will be reviewed when schemes are developed. Low carbon schemes could be a key use of the funds. Projects will need to evidence how they work towards the government net zero policy. Report P50
Staffing: The Growth and Prosperity Team is proposed to manage the Impact Fund. The Programme Monitoring Office would oversee claims, monitoring and assurance locally. The Programme itself would be managed by the Corporate Development and Engagement Team. Report 8.1, P41
Other: The Neighbourhood Board would be led by an independent Chair and include the local MP and at least one ward councillor. It would develop the Regeneration Plan with the Council. Report P21
Other: The Council will be accountable for Impact Fund allocations, onward grants, payments and day to day monitoring. Report P35
Who and where
Residents of Little Layton and Little Carleton Report P15, P19
Residents in other deprived Blackpool neighbourhoods Report P31, P35
Local businesses Report P21
Grassroots campaigners, workplace representatives, faith groups and community leaders Report P21
Local MPs Report P21
Ward councillors Report P21
External delivery and partner organisations Report 9.1
Community organisations with legal status Report P35
Timeline
10 November 2025: The Executive accepted both funds and approved the delivery and delegation arrangements. The decision was published on 11 November 2025.
Winter 2025/26: Neighbourhood Boards and local authorities receive tailored data packs for the 3 strategic objectives. Report P24
February 2026: The Council must submit a progress summary and initial spend forecasts. Financial reports will follow in May 2026, October 2026 and June 2027. Report P36
Spring 2026: MHCLG issues the 2026 to 2027 capacity and capital funding payment. The Programme Fund starts in April 2026. Report P25, P15
17 July 2026: Neighbourhood Boards will confirm final membership and any proposed boundary changes to MHCLG. Report P26
Autumn 2026: MHCLG will review the membership and boundary proposals and confirm whether they are acceptable. Report P27
Winter 2026/27 and Spring 2027: Boards will submit their Regeneration Plans in Winter 2026/27. MHCLG will approve the plans in Spring 2027. Report P28, P29
March 2027: The Impact Fund must be spent by this deadline. Report P16
Plain English for the jargon
MHCLG: Ministry of Housing, Communities and Local Government [P17]
Neighbourhood Board: Local body for the programme area that develops the Regeneration Plan and decides interventions [P20] [P21]
MoU: Memorandum of Understanding with MHCLG for both funds [P17]
PMO: Programme Monitoring Office, proposed to oversee claims, monitoring and assurance locally [P41]
MSOA: Middle Layer Super Output Areas, used to determine the default programme boundary [P20]
Section 151 Officer: Chief financial officer with oversight of the fund and a duty to certify reports [P35] [P36]
MP: Member of Parliament, who must sit on the Neighbourhood Board and be consulted about its Chair [P21]
Regeneration Plan: The neighbourhood's vision and delivery pathway, developed by the Board with the Council [P21]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
The Executive resolved as follows: For the Council to agree to accept both funds and for Council officers to undertake activities to explore options to utilise the funding working with key stakeholders, including local MPs as required. To note the draft list of potential Pride in Place Impact Fund schemes outlined in the report ( Appendix 8a to the Executive report ) and for the approval of the final allocation of funding to be delegated to the Director of Place, in consultation with the Leader of the Council. To approve the proposed approach to develop the arrangements for taking forward and developing the Pride in Place Programme Fund as set out in section 6.3 including specifically the activity to be undertaken to appoint a Pride in Place Neighbourhood Board and appoint a Chair and for a further report to be brought to the Executive when these arrangements are ready for final confirmation To authorise the Head of Legal Services to enter into all required legal documentation in connection with the utilisation of both funds. To authorise, subject to suitable procurement, the potential for providing an element of funding to third party organisations to support any activity as may be required.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
2.1For the Council to agree to accept both funds and for Council officers to undertake activities to explore options to utilise the funding working with key stakeholders, including local MPs as required.
2.2To note and comment upon the draft list of potential Pride in Place Impact Fund schemes outlined in the report (Appendix 8a to the Executive report) and for the approval of the final allocation of funding to be delegated to the Director of Place, in consultation with the Leader of the Council.
2.3To approve the proposed approach to develop the arrangements for taking forward and developing the Pride in Place Programme Fund as set out in section 6.3 including specifically the activity to be undertaken to appoint a Pride in Place Neighbourhood Board and appoint a Chair and for a further report to be brought to the Executive when these arrangements are ready for final confirmation
2.4To authorise the Head of Legal Services to enter into all required legal documentation in connection with the utilisation of both funds.
2.5To authorise, subject to suitable procurement, the potential for providing an element of funding to third party organisations to support any activity as may be required. .
Reasons for recommendations
3.1It is essential to accept the funding programmes, as to not do so would mean funding would be returned to Central Government and benefits to the Blackpool community and wider economy would be lost.
Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
4.1Do nothing – This option would require the Council to not accept the funding awards from MHCLG leading to loss of funding for the Borough.
The Council has been allocated £20m of funding for the Pride in Place Programme and £1.5m for the Pride in Place Impact Fund. The guidance for the use of the funds and the deadline for spend are clearly set and immoveable. The Council has a designated additional funding allocation. For Blackpool to benefit from these funds the key options for consideration, are based around the process for allocating the monies, the schemes chosen, engagement and in the case of the Programme fund, the establishment of a formal Neighbourhood Board with independent Chair.
5.0Council priority:
5.1The relevant Council priorities are both: The Economy: Maximising growth and opportunity across Blackpool. Communities: Creating stronger communities and increasing resilience.
6.0Background information
6.1On 25 September 2025, the UK Government launched its Pride in Place Strategy. It followed on from the English Devolution White Paper which set out plans for a radical shift in the wiring of the state, rolling out streamlined and simplified regional governance. This Strategy is a £5 billion initiative aimed at revitalizing communities across the UK. It places decision-making power in the hands of local residents, allowing them to influence funding and project priorities. The strategy focuses on improving public spaces, high streets, and local economies, with a commitment to support 339 deprived neighbourhoods through community-led projects. The programme aims to foster a sense of pride and belonging among communities, giving communities the resources and tools to drive change themselves and shape their neighbourhoods for the better. 6.2 Blackpool Council was informed that it had been allocated the following funds :-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.