INTERNAL AUDIT FOLLOW UP - CHANNEL SHIFT

Noted Finance 1 paper

AI summaryBlackpool Borough Council's Audit Committee noted progress on channel shift audit actions. [D] Work continues within current budget constraints, but strategy and governance work remain incomplete. [8.1] [P18] [P36] [P44]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress was reported against the channel shift audit recommendations. [1.1] [2.1] [3.1]
MoneyNot stated
What happens nextNot stated
Who it affectsService users and council staff [6.1]The work concerns digital access, service demand and staff capacity. [6.1] [P37] [P42]

What was decided

The Audit Committee noted implementation work addressing the channel shift audit recommendations. Report 2.1

Why

The report was intended to give the Audit Committee an update and progress information on the recommendations. Report 3.1

The review covered work to date, future plans and barriers involving funding and resources. Report P15, P16, P17

The audit affected the council's community priorities. Report 5.1

What happens next

Complete the draft corporate strategy, then obtain Executive approval, stakeholder input and scrutiny before formal sign off. Report P36, P39

Continue the revised action plan to 31st March 2026, including AI demand analysis, software licence options, directorate oversight and resident input. Report P36, P39, P42, P43, P44, P45

Run the Senior Leadership Team session in early 2026. Promote resident surveys and pursue the requested focus group exercise. The 2026 annual training package will reference the AI Policy. Report P44, P46, P48

Options considered

  • Chosen: Note implementation progress. The committee needed an update and progress information on the recommendations. Report 3.1

Implications

  • Risk: The audit found a general lack of corporate direction and no documented Channel Shift strategy. Report P18
  • Financial: The controls are being implemented within current budget constraints, while a bespoke software licence may cost and options remain under consideration. Report 8.1, P43
  • Legal: Risks need effective management to comply with relevant legislation. Report 9.1
  • Risk: The audit gave reasonable assurance that governance, risk management and control were generally sound. Report P18
  • Staffing: Digital channel shift can increase staff productivity and release capacity. The web developer role has 90 to 95 per cent available for Channel Shift. Report P37
  • Equalities: Where appropriate, equality analysis is undertaken for related decisions. Report 11.1
  • Climate: Sustainability, climate change and environmental matters are considered for related decisions. Report 12.1
  • Risk: Resident survey take up is low. Individual service surveys and a focus group were proposed, and paper surveys are distributed. Report P45, P46

Who and where

  • Council service users
  • Council staff and workforce Report P47
  • Residents using online and telephone services Report P45, P46
  • Channel Shift Group Report P35, P36, P37, P38, P39, P40, P41, P42, P44
  • Senior Leadership Team Report P40, P44
  • Directorate Management Teams and managers Report P40, P44
  • Website editors Report P38
  • ICT Helpdesk and Customer First teams Report P41, P42

Timeline

  • 4 November 2024: The internal audit report was issued. Report 1.1
  • 31st March 2025: The Terms of Reference and accessibility actions were marked completed. Report P35, P38
  • 31st July 2025: The original target for AI demand analysis was revised to 31st March 2026. Report P42
  • August 2025: The GDPR refresher training was republished. Report P47
  • 31st March 2026: The revised target for the corporate strategy, partnership working, AI analysis, directorate oversight and resident input actions. Report P36, P39, P42, P44, P45
  • early 2026: A Senior Leadership Team Channel Shift session was scheduled. Report P44
  • 2026: The mandatory annual GDPR and ICT security training package will reference the AI Policy. Report P48

Plain English for the jargon

  • Channel Shift: Moving communication and activity from one medium to another, often from telephone to online self service. [6.1]
  • Terms of Reference: The document defining the Channel Shift Group's purpose, aims, objectives and membership. [P35]
  • AI: Technology used for demand analysis and covered by the council's AI Policy. [P42] [P47]
  • AI Policy: A policy requiring a risk assessment and DPIA for any AI project, whether personal information is used or not. [P47]
  • DPIA: A required review alongside a risk assessment for any AI project. [P47]
  • Customer First: The service area whose pressures were positively affected by Channel Shift and whose communication habits are reviewed. [P18] [P41]
  • Senior Leadership Team: The leadership body whose session and divisional meetings are planned to support oversight and partnership working. [P40] [P44]
  • Reasonable assurance: The audit conclusion that governance, risk management and control were generally sound, despite concerns about corporate direction and strategy. [P18]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

To note the actions being implemented to address the audit recommendations relating to the Channel Shift Audit.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Audit Committee, 11 pages

Purpose of the report

1.1To consider a progress report on the recommendations made in the internal audit report relating to channel shift issued on 4 November 2024.

2.0Recommendation(s):

2.1To consider the actions being implemented to address the audit recommendations relating to the channel shift audit.

3.0Reasons for recommendation(s):

3.1To enable Audit Committee to consider an update and progress report on the audit recommendations.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1N/a

5.0Council priority:

5.1This audit impacts on the Council’s community priorities.

6.0Background information Channel Shift can be defined as the act of moving communications and activity from one medium to 6.1 another. Historically, this has seen communication and interaction between organisations and customers move from in-person to letter, and from letter to telephone. More recently Channel Shift is the process by which organisations seek to encourage customers to access or interact with services via channels other than those which they would normally choose. This is typically from telephone to self service via online mechanisms. Channel Shift brings benefits to customers/service users because it can offer convenience and personalised services. Implementing digital technologies gives organisations the opportunity to redesign service delivery, reduce costs and increase staff productivity. The Local Government Association (LGA) undertook a ‘Digital Channel Shift Programme’, and their publicised evaluation of this makes reference to the major benefits that digital Channel Shift can bring to both Councils and the citizens they serve. In particular, the evaluation states that the programme has demonstrated the potential of such initiatives to generate both improved services and significant savings. Savings have come from finding new and innovative ways to deliver services, reducing the number of inappropriate or unsuccessful service requests, cutting down the volume of avoidable phone or face-to-face contact and integrating and automating back-office process. This has led to the participating Councils generating efficiencies and increasing income. As well as delivering financial benefits the evaluation states that projects have delivered better services for customers, such as more joined-up services, convenient online options, faster delivery and quicker decisions about applications or benefits and better support for vulnerable customers. The evaluation also makes reference to Councils and their workforce benefitting through building in-house skills, better joined- up working and improved data accuracy enabling them to work more effectively and efficiently – all improving staff morale and releasing capacity. 6.2 The scope and assurance statement of the audit was as follows:

Scope

The scope of the audit included:

 Progress and work to date;

 Future plans/direction of travel; and

 Barriers to progress – funding and resources. Assurance Statement

The Channel Shift Group has achieved a good amount of success with the delivery of Channel Shift projects making a positive impact on the pressures on Customer First. We therefore provide reasonable assurance as there is a generally sound system of governance, risk management and control in place. However, there is a general lack of corporate direction, and no documented strategy for Channel Shift is in place.

6.3Does the information submitted include any exempt information? No

7.0List of Appendices:

7.1Appendix 5(a): Internal Audit Recommendations and Agreed Actions.

8.0Financial considerations:

8.1The controls being implemented will be done so within current budget constraints. 9.0 Legal considerations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT FOLLOW UP: CHANNEL SHIFTReport 11 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 15 attended
SB
Councillor Shaun BrookesCommittee Member, present
SC
Councillor Simon CartmellCommittee Member, present
SD
Sharon DavisSecretary, in attendance
MF
Councillor Mel FenlonCommittee Member, present
TG
Tracy GreenhalghOfficer, in attendance
AH
Councillor Alistair HumphreysVice Chair, expected
LH
Lorraine HurstSecretary, expected
NJ
Neil JackOfficer, in attendance
AL
Arthur LoganSecretary, in attendance
BM
Councillor Bradley MitchellChair, present
JS
Jodie StephensonSecretary, expected
DS
David SwiftCo-Optee, in attendance

All 15 on the meeting page

On this subject at Blackpool

Search all
  1. INTERNAL AUDIT FOLLOW UP - CHANNEL SHIFTThis decision
  2. Internal audit follow up - creditor payment financial control assurance testingNoted
  3. Internal audit follow up - illuminations serviceNoted
  4. Global internal audit standards self assessmentNoted
  5. Internal audit follow-up - operational function of securityNoted
  6. Internal audit plan 2026/27Approved

More from Blackpool Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. Approved Open
24 Sep 2026 Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... Noted Open
24 Sep 2026 Internal audit follow up - creditor payment financial control assurance testingTo note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing. Noted Open
24 Sep 2026 Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. Noted Open
24 Sep 2026 Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies