AI summaryBlackpool Council's Executive will take over in-house delivery of Phase 1 of the Revoe Community Sports Village, including 3G pitches, a MUGA and Padel courts, after Blackpool Football Club pulled out. The £6.54m Town Deal funded scheme also covers East Stand refurbishment at Bloomfield Road.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSports pitches delivered directly by the council, not BFC
Money£6.54m Town DealAlready approved, no new council funding
What happens nextAppoint consultant, submit planning applicationNew scheme needed before existing consent expires
Who it affectsRevoe residents, BFC, community groupsSports facilities and Bloomfield Road East Stand
What was decided
The Executive agreed the council will deliver Phase 1 community sports pitches in-house, using £6.54m of Town Deal funding, instead of through Blackpool Football Club. Report 2.1, 3.4
Officers were authorised to appoint an experienced consultant to produce detailed designs, a cost plan, a programme and a new planning application for a revised scheme. Report 2.2
Authority was delegated to the Head of Legal Services to enter into lease and management agreements with Blackpool Football Club and/or its Community Trust for Phase 1 land, and land transfer agreements for the Phase 2 East Stand, with the Director of Place given delegated authority over related spending and contracts. Report 2.3, 2.4, 2.5
Why
Ground condition surveys commissioned by the football club identified risks that made the original scheme unviable, so the council is taking over Phase 1 to retain control of programme, cost and planning responses. Report 3.4, 6.5, 6.6, 6.8, 6.9
The scheme will regenerate a deprived inner area, support healthier lifestyles, and provide all-weather sporting provision, with use planned by BFC Women and Girls, the Community Trust, walking football, junior leagues, wheelchair sports, schools and local groups. Report 3.1, 3.2, 11.2
The decision supports the council priorities of maximising growth and opportunity across Blackpool and creating stronger communities. Report 5.1
What happens next
A consultant will be appointed to draw up designs, a cost plan, a programme and a new planning application, as the existing Phase 1 consent (22/0859) expires in March 2026. Report 2.2, 6.10, 10.3
Remaining properties on the west side of Henry Street will be acquired and demolished over coming months to enable the Phase 2 East Stand and public realm works. Report 3.6, 6.14, 6.15
The Head of Legal Services will finalise land transfer and lease arrangements with Blackpool Football Club, with subsidy control and Section 123 Local Government Act 1972 considerations to be addressed. Report 2.3, 2.4, 8.6, 9.1, 9.2
The money
£6.54m Town Deal Fund grant from DLUHC for the Revoe Community Sports Village Report 6.3, 8.2
Options considered
Rejected: Do nothing, allow land to remain vacant and return or reallocate remaining funding. Would fail to deliver community benefit and risk public perception and loss of Town Deal funding Report 4.1, P16, 4.2, 24.1
Rejected: Minimal intervention, small scale redevelopment, public realm and car parking. Not considered most realistic or suitable option Report 4.1, P17, 24.1
Rejected: Moderate intervention, smaller scale development with community facility and public realm. Not considered most realistic or suitable option Report 4.1, P18, 24.1
Rejected: Full intervention or major change, comprehensive redesign of Phase 1 sports pitches with review of ground conditions, delivered by council Growth and Prosperity Team. Not considered most realistic or suitable option Report 4.1, P19, 24.1
Implications
Financial: No additional council funding is intended beyond the existing £6.54m Town Deal grant, with cost pressures and subsidy control assessment to be considered on land transfers. Report 8.3, 8.6, 10.1
Legal: Land disposals must comply with Section 123 Local Government Act 1972 and the General Disposal Consent (England) 2003, with subsidy control advice being sought. Report 8.6, 9.1, P53, 9.2
Equalities: The final residential dwelling is a tenanted property, and the council is providing ongoing support, advice and practical assistance to residents and tenants. Report 11.1
Climate: A Sustainability Assessment will be undertaken, with measures including EV charging points and reduced travel distances, on a brownfield site. Report 12.1, 12.2, 12.3
Risk: Existing ground conditions and cost increases previously rendered the scheme unviable for the football club; the council has commissioned its own ground surveys to manage this risk. Report 3.4, 6.6, 6.8, 6.9, 10.0
Other: The Padel Courts element of Phase 1 is conditional on Blackpool Football Club providing funding. Report 3.1
Who and where
Residents of the Revoe area of Blackpool, including a remaining tenanted household on Henry Street Report 3.1, 11.1, 13.3
Blackpool Football Club and the Blackpool Football Club Community Trust Report 2.3, 3.2, 6.7
Local community sports users, including BFC Women and Girls, Community Trust Tiny Tangerines, Walking Football, Junior League, wheelchair sports, weight management programmes, schools and community groups Report 3.2
The council's Growth and Prosperity Team, Finance, Legal and Corporate Leadership Team Report 13.1
Timeline
November 2019: Government launched the Town Fund programme Report 6.1
2nd March 2022: DLUHC approved the Business Case and £6.54m of Towns Fund investment Report 6.3
December 2024: Scheme put on hold by Blackpool Football Club for a financial review Report 6.5
August 2025: Ground surveys identified additional challenges, rendering the original scheme unviable Report 6.6
August 2025: Initial Phase 2 East Stand works commenced Report 6.11
September 2025: Council undertook an independent review and commissioned additional ground surveys Report 6.8
Prior to Christmas 2025: Several acquired properties demolished Report 3.6
December 2025: Council confirmed its owned land could be developed and a solution was identified Report 6.9
March 2026: Existing Phase 1 planning consent (22/0859) due to expire; new application to be submitted Report 6.10, 10.3
16 March 2026: Executive decision taken Report 21.1
17 March 2026: Decision published Report 23.1
This summer (proposed): Delivery of further East Stand and public realm works proposed to commence Report 6.12
Plain English for the jargon
Town Deal: UK government Towns Fund programme providing grant funding to town centres to drive regeneration, as administered by the Department for Levelling Up, Housing and Communities.
3G pitch: Artificial grass sports pitch using third generation synthetic turf, suitable for all-weather play.
MUGA: Multi Use Games Area, a surfaced outdoor area marked for several sports.
Padel Court: Enclosed court used for padel, a racquet sport played in pairs.
Compulsory Purchase Order (CPO): Legal mechanism by which a council can acquire land compulsorily, with the paper noting a purchase already agreed for the last property, potentially avoiding the need for one.
Section 123 Local Government Act 1972: Statutory requirement that local authorities dispose of land at best consideration reasonably obtainable, with limited exceptions.
Subsidy Control Act 2022: UK regime governing public subsidies to economic actors, requiring assessment of whether financial assistance is lawful.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
The Executive agreed the recommendation as outlined above namely: To seek agreement for the Council to deliver Phase 1 of the Community Sports Pitches development (as detailed in Appendix 6a, to the Executive report) through in house delivery. To authorise the appointment of an experienced consultant to provide detailed designs, cost plan and programme, and submit a planning application for a revised scheme. To delegate authority to the Head of Legal Services to enter into such legal agreements as may be required with Blackpool Football Club and/or Blackpool Football Club Community Trust in regard to the final lease or management agreements relating to the Phase 1 land and management of the facilities once completed, as shown on the plan in Appendix 6b, to the Executive report. To delegate authority to the Head of Legal Services to enter into any necessary legal agreements with Blackpool Football Club in relation to the transfer of the land required to deliver the Phase 2 East Stand development, as shown on the plan in Appendix 6c, to the Executive report. To delegate authority to the Director of Place to authorise expenditure and contracts pursuant to resolutions 1, 2, 3 and 4 above. To instruct relevant Officers to commence all necessary preparatory works to facilitate both Phase 1 and Phase 2 of the development.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
2.1To seek agreement for the Council to deliver Phase 1 of the Community Sports Pitches development (as detailed in Appendix 6a, to the Executive report) through in-house delivery.
2.2To authorise the appointment of an experienced consultant to provide detailed designs, cost plan and programme, and submit a planning application for a revised scheme.
2.3To delegate authority to the Head of Legal Services to enter into such legal agreements as may be required with Blackpool Football Club and/or Blackpool Football Club Community Trust in regard to the final lease or management agreements relating to the Phase 1 land and management of the facilities once completed, as shown on the plan in Appendix 6b, to the Executive report.
2.4To delegate authority to the Head of Legal Services to enter into any necessary legal agreements with Blackpool Football Club in relation to the transfer of the land required to deliver the Phase 2 East Stand development, as shown on the plan in Appendix 6c, to the Executive report.
2.5To delegate authority to the Director of Place to authorise expenditure and contracts pursuant to clauses 2.1, 2.2 2.3, and 2.4 above. 2.6 To instruct relevant Officers to commence all necessary preparatory works to facilitate both Phase 1 and Phase 2 of the development.
Reasons for recommendations
3.1To enable the development of the Revoe Community Sports Village scheme to progress, which will see the development of Phase 1, including two 7-a-side 3G pitches, one Multi Use Games Area (MUGA), and two Padel Courts (with the padel courts being conditional on Blackpool Football Club funding). This will regenerate a deprived area of the town, assist in supporting healthier lifestyles and provide access to all weather sporting provision in the inner areas. The project will also support and facilitate the growth and development of the Club with the refurbishment of the existing East Stand within Blackpool Football Club’s Bloomfield Road stadium, including the delivery of associated public realm space.
3.2The new sports facilities will be used by a range of clubs including BFC Women and Girls, Community Trust Tiny Tangerines, Walking Football, Junior League, wheelchair sports, weight management programmes, with the ability to run local sports programmes through Blackpool Football Club Community Trust. Access to the pitches will also be made available to local community groups and schools for recreational sport and for the delivery of education programmes.
3.3The original terms of the Town Deal funding were for Blackpool Football Club to lead on the development, appointing consultants and contractors to undertake the construction and delivery of the overall scheme, with the assistance and support from Blackpool Council.
3.4However, a series of site investigations undertaken by the football club’s agents identified issues with the existing ground conditions, which they believe introduce risks and uncertainties to the delivery programme, costs and threatened the overall viability of the Phase 1 sports pitches. As a consequence, an alternative approach was agreed with the Club whereby the Council would undertake the development of the pitches, with the benefit of the Town Deal funding, as delivery of Phase 1 sports pitches by the Council will provide increased control over programme and expenditure, while also enabling more timely and coordinated responses to Planning and Highways enquiries.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.