Blackpool Borough Council
Shareholder Committee, Wednesday 23 September 2026 at 10.00am

WHOLLY OWNED COMPANY STRATEGIC RISK REGISTER 2026/27

Approved Committee 4 papers

AI summaryBlackpool Council's Shareholder Committee approved the 2026/27 Wholly Owned Companies Strategic Risk Register, covering 13 risk categories from cyber attack to financial sustainability, with a maximum gross risk score of 25.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved13 risk categories, each scoring up to 25
MoneyTwo sums noted£1.1m on tram track, £420k housing savings
What happens nextReviews scheduled through 2027Many actions target March 2027 completion dates
Who it affectsCouncil's wholly owned companiesIncludes Blackpool Transport, Tourism and Coastal Housing

What was decided

The Shareholder Committee approved the Wholly Owned Companies' Strategic Risk Register for 2026/27.

The register was approved as a key component of the Council's Risk Management Framework.

A committee member left the meeting after the item was considered.

Why

To ensure that strategic risks relating to the Council's companies are effectively managed.

The Committee noted that the Risk Register was a key component of the Risk Management Framework which required approval by the Committee.

What happens next

A performance dashboard for the Shareholder is in draft and out for wider consultation with Managing Directors before formal launch. Report P5

A new operating agreement for all companies is being developed to set out expectations and how these will be measured. Report P8

A draft Policy Framework will be taken to the Shareholder Committee for approval in July before being rolled out and adopted by each company Board. Report P8

The money

  • £1.1 million spent on tram track maintenance and replacement Report P16
  • £420k saving that the housing companies need to find as part of the shared services agenda Report P19

Options considered

  • Chosen: Approve the Wholly Owned Companies' Strategic Risk Register for 2026/27. To ensure that strategic risks relating to the Council's companies are effectively managed.

Implications

  • Financial: Financial unsustainability carries a gross risk score of 25, the highest level on the register, and is to be monitored through robust budget monitoring and external audit. Report P19
  • Risk: Four risks (Cyber Attack, Financial unsustainability, Unauthorised access, and Failure to reduce carbon emissions) all carry the maximum gross risk score of 25. Report P1, P16, P19, P25, P30, P33
  • Legal: The Legal category includes risks on regulatory compliance, unsafe working practices, and failure to meet statutory landlord obligations. Report P14, P16
  • Climate: A separate risk covers failure to reduce carbon emissions across operations, linked to the Paris Climate Change Agreement and Blackpool's 'fair share' target. Report P33
  • Staffing: The People category covers loss of capacity, stretched council resources, succession planning, and changes in employment law. Report P23
  • Other: The Information category currently has no risks to escalate to the strategic risk register. Report P28

Who and where

  • Blackpool Council's wholly owned companies, including Blackpool Transport Services, Blackpool Tourism Limited and Blackpool Coastal Housing Report P5, P12, P16, P21
  • Council tenants and residents, particularly in relation to landlord statutory obligations Report P16
  • Shareholder Committee members, who will receive new performance dashboard reporting Report P5, P8

Timeline

  • September 2026: Performance dashboard target launch after wider consultation Report P5, P14, P23, P30, P33, P36
  • 23 September 2026: Strategic Risk Register for 2026/27 approved by Shareholder Committee
  • November 2026: Shareholder objectives report to be presented Report P5
  • March 2027: Target review date for most strategic risks, including governance, property and financial risks Report P5, P7, P8, P10, P12, P14, P16, P19, P21, P23, P25, P30, P33, P37
  • March 2028: Target review date for risks relating to tram refurbishment and biodiversity Report P16, P25, P33
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item2

Resolved

To approve the Wholly Owned Companies’ Strategic Risk Register for 2026/27. Reason for To ensure that strategic risks relating to the Council’s companies are effectively managed. The Wholly Owned Companies’ Strategic Risk Register is a key component of the Council’s Risk Management Framework. Alternative Options Considered: The Committee noted that the Risk Register was a key component of the Risk Management Framework which required approval by the Committee. Date of 23 September 2026. [name removed] left the meeting following consideration of this item.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Shareholder Committee

Appendix 3a Wholly Owned Company Strategic Risk Register 2026-27 Nett Risk Score Map Impact 1 2 3 4 5 5 4  Lack of investment in properties used  Financial unsustainability. by the companies.  Failure to reduce carbon emissions  Lack of an affordable tram across operations. refurbishment programme.  Unauthorised access to site. 3  Wholly Owned Company model does  Cyber Attack or Data Breach not deliver Shareholder priorities.  Changes to Central Government policy impacting on operations.  Loss of capacity / capability. Likelihood

2  Shareholder does not set clear priorities  Unsafe Working Practices. and hold the companies to account for  Loss of custom due to the economy and their delivery. changes in spending behaviours.  Failed Company Governance including Shareholder responsibilities.  Failure to deliver against regulatory requirements / statutory duties.  Failure to meet statutory obligations as a significant landlord across the town.  Inability to deliver functions due to an unplanned incident.  Conflicting communication messages. 1 Appendix 3a Wholly Owned Company Strategic Risk Register 2026-27 Strategic Risk Register (by Risk Category)

1. Strategy

Risk Appetite: Open Council Priority: Communities: Creating stronger communities and increasing resilience

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Wholly Owned Company Strategic Risk Register: 2026-2027Report 810 KB DownloadRead as text
PDF
Draft Wholly Owned Company Strategic Risk Register: 2026-2027Report 810 KB Download
PDF
WHOLLY OWNED COMPANY STRATEGIC RISK REGISTER 2026/27Report 489 KB Download
PDF
WHOLLY OWNED COMPANY STRATEGIC RISK REGISTER 2026/27Report 489 KB Download

At this meeting

Whole meeting

Who was there

0 of 11 attended
JB
John BlackledgeOfficer, expected
AC
Alan CavillOfficer, expected
SD
Sharon DavisSecretary, expected
TG
Tracy GreenhalghOfficer, expected
LH
Lorraine HurstSecretary, expected
NJ
Neil JackOfficer, expected
AK
Annette KerrSecretary, expected
MS
Councillor Michele ScottCommittee Member, expected
MS
Councillor Mark SmithChair, expected
KW
Kirsten WhyattOfficer, expected
LW
Councillor Lynn Williams MBECommittee Member, expected

On this subject at Blackpool

Search all
  1. WHOLLY OWNED COMPANY STRATEGIC RISK REGISTER 2026/27This decision
  2. Policy framework - wholly owned companiesRefused
  3. Internal audit follow-up - governance of wholly owned companiesNoted
  4. Funding for the wholly owned housing regeneration companyAgreed

More from Blackpool Shareholder Committee

All decisions
MeetingDecisionOutcome
23 Sep 2026 Central housing regeneration project area: delivery progress and relocation supportTo note the updates outlined in respect of workstream delivery activity, including property acquisitions and forward ... Noted Open
28 Jul 2026 Policy framework - wholly owned companiesThe Council’s wholly owned companies play an important role in delivering the Shareholder’s strategic priorities. It ... Refused Open
28 Jul 2026 Museum and heritage trust updateTo note the update provided on the Museum and Heritage Trust. Noted Open
5 Sep 2023 Exclusion of the publicThat under Section 100 (A) of the Local Government Act 1972 the public be excluded from the meeting during considerat... Decided Open
5 Sep 2022 Exclusion of the publicThat under Section 100 (A) of the Local Government Act 1972 the public be excluded from the meeting during considerat... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies