RESOLVED that the report be accepted, and upon a vote being taken Option 1 was approved, namely:- · To continue as per the existing arrangement where a BCO is not guaranteed to attend an incident. The advantage of this option is that it entails least cost. · However, this is predicated on the Council acknowledging and accepting the risk that in the event that emergency services require professional advice on the safety of a structure e.g. to enter, then there will be no BCO in attendance. · RCSLT are asked to consider the potential risk and reputational damage associated with what may be a major incident and Building Control do not attend. · It may also prove impossible to instigate any cost recovery against property owners.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: Date signed off by the Section 151 Officer:
Committee: Governance and Audit Committee
Date of meeting: 26th April 2023
Report Subject: Building Control - Out of Hours Dangerous Structures Call Outs
Portfolio Holder: Non Cabinet Function - Chair of Planning Committee
Report Submitted by: Service Manager Development & Estates
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Scrutiny Cabinet Council Other – Management Leadership Holder / Audit Services Committee Planning Team Team Chair Committee Committee Committee ✓ ✓ ✓ ✓ Note for Planning Committee – this report was presented to CLT early April 2023 and option 1 was chosen. As a result, BGCBC do not now provide an out of hours rota for dangerous structures. The risk has been captured in the service risk register. The G&A Committee action sheet from the meeting that considered the original internal Audit report indicates this matter will be referred to the relevant Committee once the issue is resolved.
1.0Purpose of the Report To consider the issue of Building Control out of hours dangerous structures (DS) call outs and review whether existing arrangements are fit for purpose.
1.1The report considers calls received outside of normal business hours. Incidents received during 9am to 5pm are responded to as normal, usually within 2 hours.
2.0Scope and Background
2.1The Building Control service is responsible for dealing with incidents where a privately owned property or structure is dangerous and poses a threat to public safety. It should be noted that property in the ownership of the Council is dealt with by the Corporate Landlord (Community Services Division) and therefore sits outside the scope of this report.
2.2At the outset it is worth defining what a DS is. The term 'dangerous structure' covers not only buildings or parts of buildings but also such things as garden walls, fences, scaffolding or hoardings. In fact, any “structure”, which could by its condition endanger persons.
2.3For the purposes of Building Regulations, there are two types of dangerous structures: 2.4 a) Imminent: structures which are at risk of collapse and must be secured for public safety. The owner will normally be recharged for emergency works carried out in these cases. b) Hazardous: structures which from a survey are unstable but not imminently dangerous. In these cases the owner is given a reasonable time to remove the danger. Failure to respond may result in legal action.
2.5The BCO will visit the site to inspect the structure and to arrange for appropriate action to be taken to remove any danger. If the structure is considered potentially dangerous, the owner of the property will be located and requested to arrange for the structure to be removed or repaired. The area surrounding the structure is cordoned off if necessary to ensure safety is maintained whilst the structure is being dealt with.
2.6If the structure is considered immediately dangerous and likely to collapse, the BCO will arrange for a builder to remove or repair the structure as soon as possible, normally on the same day. The builder's costs are recoverable from the owner of the property.
2.7Where responsibilities overlap with other Emergency Services, a close liaison is maintained to ensure safety at all times. If it is necessary to deal with any immediate danger, we can arrange for our own emergency contractor to carry out the work.
2.8Should a major civil emergency occur, the corporate Emergency Plan would be invoked and involve staff in respect of dangerous buildings. This is also a factor needing consideration.
2.9A structure may fall into the legal definition of “dangerous” by a number of means such as a road traffic accident, poor workmanship/maintenance, fire/weather-related incident or other.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.