1.1Every local planning authority in Wales collates performance information regarding the speed and quality of decision making on all types of planning and related applications. This is submitted to Welsh Government on a quarterly basis.
1.2Welsh Government publishes this data on its website. It is a useful source of comparative information where the Council can not only scrutinise its own performance, but benchmark the data against the 25 other Local Planning authorities (22 unitary authorities and 3 National Parks)
1.3Following a delay in Welsh Government publishing data, the June 2023 cycle of this Committee considered a report that covered the data for the entire calendar year of 2022.
1.4This report deals with new performance data for Q4 2022/23 which is January to March of this year.
1.5The data used in this report was published on the WG website on 21st June 2023 at this LINK. Report Date June 2023 Report Author: Steve Smith
2.0Performance Information
2.1The figures reveal…
2.2i. We decided 90% of applications “in time”. This compares to an all-Wales average of 84%.
2.3ii. On average, it took 84 days to decide each application against an all-Wales average of 123 days.
2.4iii. 0% of applications in this quarter decided by Planning Committee were contrary to officer recommendation. The Wales average was 6%.
3.0Evaluation of Performance and Conclusions
3.1The figure of 90% of applications determined in time is broadly in line with historical returns for this indicator.
3.2On average, it takes 84 days to decide each application. Whilst this compares favourably to the all-Wales average, it is higher than I would like and falls short of pre-covid returns.
3.3Members may be aware that we are currently in the process of implementing a new software system and one planning officer has been seconded to manage the process. This will inevitably impact on performance. We have again instructed an external consultancy to take on a limited caseload of applications and this will be closely monitored.
3.4Finally, for the second consecutive quarter we had a nil return for Planning Committee decisions contrary to officer recommendation.
3.5It is pleasing that this puts us above the Welsh average. Overturns are now becoming an exceptional event rather than the norm.
4.1No decision is required.
4.2Planning Committee is invited to scrutinise the performance returns and officers will address any issues or questions at the meeting. Report Date June 2023 Report Author: Steve Smith
Table 1:
January to March 2023 Percentage of Planning Applications Determined “On Time”
Percentage of All Applications Determined Welsh On Time Local Planning Authority % Decided in Time
1 Vale of Glamorgan 98 2 Swansea 96 3 Pembrokeshire 95 Merthyr Tydfil 95 Caerphilly 95 6 Isle of Anglesey 94 7 Neath Port Talbot 93 Powys 93 9 Monmouthshire 92 10 Blaenau Gwent 90 Gwynedd 90 12 Carmarthenshire 87 13 Denbighshire 86 Conwy 86 15 Rhondda Cynon Taff 84 16 Ceredigion 83 17 Wrexham 82 18 Newport 72 19 Torfaen 70 20 Cardiff 69 21 Pembrokeshire Coast NPA 67 22 Bridgend 63 23 Bannau Brycheiniog NPA 57 24 Snowdonia NPA 33 25 Flintshire no return WALES AVERAGE 84% Report Date June 2023 Report Author: Steve Smith
Table 2: January to March 2023
Average Days to Decide Each Application
Welsh Average No. of Days Taken Local Planning Authority to Decide an Application
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Development Management Quarterly Performance Information Quarter 4: January to March 2023Report | 215 KB | DownloadRead as text |
Follow Planning Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Planning Applications ReportRESOLVED that Planning permission be GRANTED subject to the conditions detailed in the report. As a Ward Member for t... | Decided | Open |
| 9 Sep 2026 | Appeals, Consultations and DNS Update September 2026RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
| 9 Sep 2026 | Appeal Update Report – 2 Zion Street, Briery Hill, Ebbw ValeRESOLVED that the report be accepted and the attached appeal decision by PEDW be noted. | Noted | Open |
| 9 Sep 2026 | Planning Appeal Update: Endsleigh, Alma Terrace, Brynmawr.RESOLVED that the report be accepted and the attached appeal decision by PEDW be noted. | Noted | Open |
| 9 Sep 2026 | List of determined applications between 19th June 2026 – 28th August 2026RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.