Blaenau Gwent County Borough Council Action Sheet
Governance & Audit Committee
Meeting Action to be Taken By Whom Action Taken Date 21st June, Item 9 – Annual Report of the 2023 Audit and Risk Manager 2022/2023
➢ An update be provided on Audit & Risk A report had been received by the Committee on one of the the three large investigations Manager investigations and progress against the agreed Action Plan that had commenced during would be received later in the year. the year, at the appropriate juncture. At the request of Committee, a briefing will be provided that identifies the policy framework that was being used to pursue the two investigations to give Members an understanding of the nature of the constraints and the process being followed.
Action: Ongoing 20th June, Item 7 – Forward Work 2024 Programme
A briefing session be arranged for Chief Officer Briefing session to be held on 23rd July 2024. Members to understand the issues Resources regarding the 2022/23 accounts and be extended to Corporate & Performance Scrutiny Members and Audit Wales. Action: Complete Meeting Action to be Taken By Whom Action Taken Date
Timeliness of Reports - Democratic Report Authors Consideration has been given to the forward work Services to review and reassess programme by relevant officers, with amendments being the FWP to ensure reports are made, where possible, following discussion committee more timely. comments.
An email has also been sent to all Governance and Audit Committee members providing rationale for the items and the work programme.
Officers to undertake a quarterly review of the work programme is to take place to ensure items are relevant and timely.
Action: Complete
20th June, Item 8 - Shared Resource 2024 Service (SRS) Annual Internal Audit Report 2023/24
The Chief Officer Resources to Chief Officer Forward Work Programme to be updated. provide more regular reports on the Resources outcome of ongoing audits in the SRS and include this on the Forward Work Programme. Action: Complete Meeting Action to be Taken By Whom Action Taken Date 20th June, Item 9 – Internal Audit Plan 2024 2024-29
A 1 year operational Audit Plan be Professional Report on Agenda. presented to the next meeting. Lead, Internal Quarterly progress updates Audit continue to be provided to the Committee on the 1 year operational plan and on an annual basis the Committee be presented with the revised 5 year Strategic Plan. Action: Complete
20th June, Item 10 - Complaints Information 2024 For Quarter 3 and Quarter 4 – 2023/2024
Assurance be given in terms of the Service Manager - The adopted model complaints & concerns policy is the up- appropriateness of the policy Registration, to-date policy which will be refreshed by the Ombudsman in framework that is currently being Elections & April 2025. used i.e. Ombudsman model – was Corporate it the most up to date framework. Complaints Action: Complete
Consideration be given to include Consideration will be given and an update provided when the use of a grading system to look the quarter 1 & 2 complaints information is reported to at quality issues to better Committee. understand the nature and breadth of complaints. Action: Ongoing Meeting Action to be Taken By Whom Action Taken Date Review of the accessibility Access to complaints will be reviewed and an update mechanism in terms of the public provided when the quarter 1 & 2 complaints information is making complaints/compliments. reported to Committee.
Action: Ongoing
20th June, Exempt 2024 Item 12 Contracts – Estimated Value Below £75,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Action SheetReport | 90 KB | DownloadRead as text |
Follow Governance & Audit Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. | Decided | Open |
| 20 Jul 2026 | Action SheetRESOLVED that the Action sheet be noted. | Noted | Open |
| 20 Jul 2026 | Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. | Decided | Open |
| 20 Jul 2026 | Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... | Decided | Open |
| 20 Jul 2026 | Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.