Resolved
RESOLVED that the Annual Report of the Audit & Risk Manager 2023/24 be accepted.
Governance & Audit Committee decided this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Annual Report of the Audit & Risk Manager 2023/24 be accepted.
1.1This report provides the Governance and Audit Committee with the Audit & Risk Manager’s (A&RM) objective review of the Authority’s system of internal control operating during the financial year 2023/24 and the annual audit opinion of the A&RM.
2. Scope and Background
2.1Background and Context
2.1.1 The report highlights the work undertaken by the Internal Audit Service and complies with the Public Sector Internal Audit Standards (PSIAS) and the Terms of Reference for the Governance and Audit Committee.
2.1.2 In line with the PSIAS, the A&RM is required to produce an annual report for the Governance and Audit Committee. The report must include the following three items: • An annual opinion, including a summary of the audit work that supports that opinion; • A statement on conformance with the International Professional Practices Framework (IPPF), including the PSIAS; and • The results of the Quality Assurance and Improvement Programme.
2.1.3 The A&RM must demonstrate organisational independence, and this is achieved through a series of measures to include: the Committee approving the Internal Audit Charter; the Committee agreeing the Internal Audit Plan; and the Committee receiving periodic reports on the work undertaken by the Internal Audit Service. 2.1.4 This is further illustrated by the A&RM being able to report directly to the Chief Executive Officer and / or the Governance and Audit Committee if the need arises.
2.1.5 The Committee has received quarterly progress reports throughout the year and was provided with the Audit Plan outturn position for 2023/24 at its April 2024 meeting.
2.1.6 The A&RM line manages the Insurance and Risk Management Service in addition to the Internal Audit Service. Appropriate reviewing and reporting processes have been put in place for conducting audit work in this service area. Audit output in respect of the Insurance and Risk Management Service bypasses the A&RM and is subject to sign off by the Chief Officer Resources to ensure independence is maintained.
2.1.7 The appropriateness of this arrangement was raised as part of the last External Quality Assessment (EQA). Both the Corporate Leadership Team (CLT) and this Committee have agreed that the arrangement is satisfactory and that any risk associated with this was minimal and would be tolerated. This stance is confirmed annually when the EQA action plan is reviewed.
2.2Annual Summary of Audit Activity for the Financial Year 2023/24
2.2.1 The annual opinion is formed having consideration to three aspects of the Authority’s arrangements, namely: Governance, Risk Management and Internal Control.
2.2.2 The Governance and Audit Committee have met throughout the year with meetings held both in person and via Teams. The committee carried a lay member vacancy at the start of the 2023/24 municipal year but successfully recruited a third lay member in September 2023.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Report of the Audit and Risk Manager 2023/24Report | 159 KB | DownloadRead as text |
Follow Governance & Audit Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | Governance & Audit CommitteeRESOLVED that the decisions be accepted as a true record of proceedings. | Decided | Open |
| 20 Jul 2026 | Action SheetRESOLVED that the Action sheet be noted. | Noted | Open |
| 20 Jul 2026 | Statement of Accounts 2025/2026 UpdateRESOLVED that the verbal update be accepted. | Decided | Open |
| 20 Jul 2026 | Progress Against Recommendations from External Audit ReportsRESOLVED that the report be accepted and the Committee was assured that the arrangements in place for monitoring and ... | Decided | Open |
| 20 Jul 2026 | Code of Governance 2026/2027RESOLVED that the report be accepted and the revised Code of Governance be approved and adopted. (Option 1) | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.