RESOLVED that the report be accepted and - the urgent decision made to award the contracts for flood defence works be noted and endorsed; and - that Council agreed to fund the works, totalling approximately £800,000. The final level of the Council’s resources required would be subject to the outcome of discussions with Wales Government.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
1.1The report provides Members of the Council with the details and rationale for recent contract awards relating to Flood Defence Works. The decision to award these contracts was taken urgently and outside of the Council’s usual Budget and Policy Framework and therefore requires a retrospective report to the next available council meeting.
2. Scope and Background
2.1Following recent flooding incidents (November 2024), the Council has identified a programme of works that need to be progressed as a matter of urgency to minimize the high risk of flood re-occurrence as well as to secure contractor capacity to undertake the works.
2.2The Council has not yet identified or approved funding for this works but we are in discussions with the Welsh Government and are hopeful of securing grant funding to support the project.
2.3In anticipation of funding being identified, an urgent procurement exercise has been undertaken to identify suitable contractors able to commence the works during March / April 2025 however the successful bidders advised that they would be forced to reallocate their workforces to other projects if contracts were not awarded imminently.
2.4To ensure suitable contractor capacity and avoid further delays to the commencement of the required works, Officers, with the agreement of Cabinet Members, have prior to funding being identified / agreed, taken the urgent decision to award the contracts for Flood Defence Works to enable those works to commence immediately.
3. Options for Recommendation To include Recommendation(s) / Endorsement by other groups, e.g. CLT/Committees/Other groups)
3.1It is recommended the Council note and endorse the urgent decision made to award the contracts for flood defence works.
3.2It is further recommended that Council agree to fund the works, totalling approximately £800,000. The final level of the Council’s resources required will be subject to the outcome of discussions with Wales Government.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
4.1The report topic and the urgent decisions made supports the delivery of flood defence / prevention works that will minimise the risk and impact of future flooding events upon vulnerable communities across Blaenau Gwent.
5. Implications Against Each Option 5.1 Impact on Budget (short and long term impact)
5.1.1 The estimated cost of the works (contracts awarded) is approximately £800,000. The level of the Council’s capital resource needed to fund the works will be subject to any decision of Wales Government on available grant funding.
5.2Risk including Mitigating Actions
5.2.1 Delaying or not undertaking the identified works will leave vulnerable communities across Blaenau Gwent at risk of future flooding events.
5.2.2 If grant funding is not forthcoming, the works will be fully funded using the Council’s own resources. This will reduce the resources available for other capital / priority projects.
5.3Legal N/A
5.4Human Resources N/A
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Scrutiny Report 2025-2026RESOLVED that the report be accepted and - the ‘scrutiny activity’ that had been undertaken by each Scrutiny Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.