Blaenau Gwent County Borough Council
Cabinet, Monday 13 October 2025 at 1.00pm

Capital Report 2024-25 Provisional Outturn

Agreed Executive 3 papers

AI summaryBlaenau Gwent Cabinet accepts the 2024/25 capital provisional outturn, showing £37.5m spent against a £37.6m budget with a £0.05m favourable variance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedMembers agreed to provide financial challenge and continue controls
MoneyFavourable variance of £0.05mAgainst in-year capital budget of £37.6m at 31 March 2025
What happens nextQuarterly budget monitoring continuesScrutiny Committee and Cabinet review each quarter
Who it affectsNot stated

What was decided

Cabinet accepted the Capital Report 2024/25 Provisional Outturn and approved Option 1, which includes continued financial challenge and support for capital control procedures. Report P9, P10

Members noted the budgetary control and monitoring procedures in place within the Capital Team to safeguard Authority funding. Report P10

Why

The report supports the Forward-Looking Corporate Plan 2022/27 by ensuring effective forward financial planning and the council's financial resilience. Report 4.1

The Capital Programme is developed to support the council's strategic priorities and is agreed by full Council, with quarterly scrutiny by the Corporate Governance & Resources Scrutiny Committee. Report 6.3

What happens next

The Capital Services Team will continue to work closely with budget holders and external funding bodies to maximise funding and secure amendments where needed. Report 6.5, P51, P52

The Executive Leadership Team, Scrutiny Committee and Cabinet will continue to consider budget monitoring reports on a quarterly basis. Report 7.1, P56

The money

  • approximately £76.1m Agreed capital programme at 31 March 2025 Report P15
  • £45.7m Welsh Government grant funding Report P16
  • £14.4m Other grant funding Report P16
  • £16m Council Resources funding Report P16
  • approximately £1.4m Funding increase since quarter 3 (£1.28m new external grant and £0.12m from revenue) Report P17
  • £37.5m Capital expenditure incurred during 2024/25 Report P18
  • £37.6m Total in-year capital budget Report P19
  • £0.05m Favourable variance forecast at 31 March 2025 Report P19
  • £9,120 Overspend on The Company Shop, to be financed from Capital contingencies Report P25, P26
  • £53,734 Underspend on 20mph Additional Allocation against grant approval of £211,000 Report P27, P28
  • approximately £150,000 Predicted overspend on Children's Residential Homes to completion Report P30
  • £75,324 Additional Welsh Government funding for Children's Residential Homes Report P30
  • £75,000 Council budget agreed for 2025/26 for Children's Residential Homes Report P30
  • £4.3m Council's own resources utilised to support capital projects during 2024/25 Report P33
  • £11.3m Potential capital slippage identified after review Report P33
  • £11.1m Slippage approved into 2025/26 to support ongoing schemes Report P33
  • £0.2m Released to Capital contingency for future reallocation Report P33

Options considered

  • Chosen: Option 1: Accept the report, provide challenge to financial outcomes, continue support for financial control procedures, and note Capital Team monitoring procedures. Recommended option; supports effective forward financial planning and the Corporate Plan Report P9, P10, 4.1
  • Rejected: Option 2: Do not accept the report Report 3.2

Implications

  • Financial: Capital programme totals approximately £76.1m at 31 March 2025, with £37.5m spent in year and a favourable £0.05m variance against budget. Report P15, P18, P19
  • Financial: £11.1m of slippage approved into 2025/26, with £0.2m released to Capital contingency. Report P33
  • Financial: The Company Shop overspend of £9,120 will be financed through Capital contingencies. Report P25, P26
  • Financial: Children's Residential Homes scheme forecast overspend of approximately £150,000 mitigated by £75,324 Welsh Government funding and £75,000 council budget for 2025/26. Report P30
  • Risk: If funding re-profile cannot be agreed and capital schemes exceed budget, capital reserves may be committed beyond affordable levels and projects may be deferred. Report P36
  • Risk: Expenditure against external funding approvals must be maximised to avoid loss of funding; delays require early liaison with funding bodies. Report P35
  • Climate: Capital Programme includes schemes promoting carbon reduction such as ReFIT, Electric Vehicle Charge Points and Ultra Low Emission Vehicles, in line with the council's 2030 carbon neutral target. Report 6.8

Who and where

  • Communities in Blaenau Gwent receiving capital investment Report 6.2, P44
  • Welsh Government as a major grant funder (£45.7m) Report P16
  • Capital budget holders across all Council Portfolios Report P33, 6.3
  • Corporate Governance & Resources Scrutiny Committee (quarterly oversight) Report 6.3, P47

Timeline

  • 31 March 2025: Capital programme stood at approximately £76.1m with £37.5m spent in year and a £0.05m favourable variance Report P15, P18, P19
  • Q4 2024/25: Funding changes of approximately £1.4m processed, including £1.28m new external grant and £0.12m from revenue Report P17
  • 16.09.25: Report considered by Directorate Management Team Report P3
  • 24/9/25: Report considered by Corporate Governance & Resources Scrutiny Committee Report P3
  • 06/10/2025: Report signed off by Monitoring Officer and Section 151 Officer Report P1
  • 13th October 2025: Cabinet meeting accepts the report Report P2, P3
  • 2025/26: £11.1m slippage applied to support ongoing schemes; £75,000 council budget agreed for Children's Residential Homes Report P30, P33

Plain English for the jargon

  • Provisional outturn: A preliminary year-end position for spending, before the accounts are finalised.
  • Slippage: Funding that is carried forward from one financial year to the next because the related scheme is not yet complete.
  • Capital contingency: A reserve held to meet unexpected costs on capital projects.
  • Re-profile: Changing the timing of when funding is drawn down, agreed with the funding body.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

RESOLVED that the report be accepted and Option 1 was agreed as follows:- a) Cabinet Members accepted the report; b) provided appropriate challenge to the financial outcomes in the report; c) continued to support appropriate financial control procedures agreed by Council; and d) noted the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
Word for word from the decision Blaenau Gwent published for this meeting. Source: democracy.blaenau-gwent.gov.uk

Follow this further

Built from Blaenau Gwent's papers

What the report saysPro

Report to Cabinet

Cabinet and Council only Date signed off by the Monitoring Officer: 06/10/2025 Date signed off by the Section 151 Officer: 06/10/2025

Committee: Cabinet Date of meeting: 13th October 2025 Report Subject: Capital Budget Monitoring, Provisional Outturn 2024/25 Portfolio Holder: Leader & Cabinet Member Corporate Resources Report Submitted by: Corporate Director of Corporate Services

Reporting Pathway Directorate Corporate Portfolio Governan Democrati Scrutiny Cabinet Council Other Management Leadership Holder / ce & Audit c Services Committee (please Team Team/Apollo Chair Committee Committee state) 16.09.25 24/9/25 13/10/25

1. Purpose of the Report 1.1 To provide Members with an overview of each Portfolio’s provisional capital expenditure against funding approvals for the 2024/2025 financial year.

2. Scope and Background

2.1This report provides details on the following:

• Provisional outturn financial position for 2024/2025 across all portfolios. • Details of any significant adverse and/or favourable variances • Funding Changes actioned during the period

2.2This report forms part of the councils financial reporting framework.

3. Options for Recommendation 3.1 Option 1 (Recommended Option)

Members accept the report and • Provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.

3.2Option 2 Do not accept the report.

4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan

4.1This report supports the Forward-Looking Corporate Plan 2022/27 as it ensures effective forward financial planning arrangements are in place to support the Council’s financial resilience. This is a key element to achieving “An ambitious and innovative council delivering quality services at the right time and in the right place”. 5. Implications Against Each Option

5.1Impact on Budget (short and long term impact)

5.1.1 The agreed capital programme at 31 March 2025, is approximately £76.1m and is funded by: -

WG Grant - £45.7m Other grant funding - £14.4m Council Resources - £16m

Funding has increased by approximately £1.4m since quarter 3, £1.28m of which is new external grant funding and £0.12m contribution from the Council’s revenue budget. Further details of funding changes within the period are shown in Appendix 2.

Expenditure of £37.5m was incurred on capital projects during 2024/25, with the remaining funding approvals allocated for use in future years.

The overall financial position as forecast at 31st March 2025 indicates a favourable variance of £0.05m against a total in year capital budget of £37.6m.

The overall position across all Portfolios is shown below: -

Total Future In year Actual Forecast Approvals funding funding Expenditure to Variance Q4 31/03/2025 underspent (Month 12) / (Mar 2025) (overspent)

£000 £000 £000 £000 £000

76,182 38,608 37,574 37,526 48

5.1.2 From this report two significant variances can be highlighted;

5.1.3 The Company Shop - £9,120 (Overspend)

The overspend relates to costs of unexpected survey and material costs, The overspend will be financed through Capital contingencies.

5.1.4 20mph – Additional Allocation - £53,734. (Underspend)

The total grant approval for 2024 / 25 was £211,000, all key stages and milestones were achieved within the funding envelope resulting in an underspend against approval of £53,734. Welsh Government have been made aware of the underspend. Consequently, the remaining funding will not be drawn down from Welsh Government.

5.1.5 Update on Children’s Residential Homes funding position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024-25_Capital_Programme_OutturnAppendix 1 466 KB Download
PDF
2024-25_Q4 _Funding_ChangesAppendix 2 211 KB Download
PDF
Capital Report 2024-25 Provisional OutturnReport 152 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
ST
Councillor Stephen ThomasChair, present
HC
Councillor Helen CunninghamCommittee Member, present
JC
Councillor John C. MorganCommittee Member, present
SE
Councillor Sue EdmundsCommittee Member, present
TS
Councillor Tommy SmithCommittee Member, present
SV
Stephen VickersOfficer, expected
LM
Luisa Munro-MorrisOfficer, present
DL
David LeechOfficer, apologies
RH
Rhian HaydenOfficer, present
AP
Andrea ProsserOfficer, expected
AJ
Andrea JonesOfficer, present
MT
Mark ThomasOfficer, apologies

All 18 on the meeting page

On this subject at Blaenau Gwent

Search all
  1. Capital Report 2024-25 Provisional OutturnThis decision
  2. Capital Budget Monitoring, Provisional Outturn 2023-2024 Financial Year (As At 31 March 2024)Agreed
  3. Capital Budget Monitoring, Provisional Outturn 2022/2023 Financial Year (As at 31 March 2023)Agreed
  4. Capital Budget Monitoring, Provisional Outturn For 2020/2021 Financial Year (As At 31 March 2021)Agreed
  5. Capital Budget Monitoring, Provisional Out-Turn for 2019/2020 Financial YearAgreed

More from Blaenau Gwent Cabinet

All decisions
MeetingDecisionOutcome
7 Sep 2026 CabinetRESOLVED that the decisions be accepted as a true record of proceedings. Decided Open
7 Sep 2026 Conferences, Courses and InvitationsRESOLVED that approval be granted for 1 Member to attend each Conference. Approved Open
7 Sep 2026 Cabinet Forward Work Programme -19th October 2026RESOLVED that the report be accepted and the Forward Work Programme for the October Cabinet meeting be agreed. Agreed Open
7 Sep 2026 Annual Corporate Safeguarding Report 2025/26RESOLVED that the Annual Corporate Safeguarding Report 2025/26 be accepted as presented. Decided Open
7 Sep 2026 Establishment of a Gwent-Wide Social Care Workforce Development ServiceRESOLVED that the report be accepted and Cabinet approves Blaenau Gwent County Borough Council’s participation in the... Approved Open