Capital Budget Monitoring, Forecast for 2025/2026 Financial Year (As at 30 June 2025)
AgreedExecutive3 papers
AI summaryBlaenau Gwent Cabinet accepts capital budget monitoring report, noting a forecast £38.1 million spend in 2025/26 against a total programme of £64.8 million, with a breakeven position at 30 June 2025.
Money£64.8 millionTotal agreed capital programme for 2025/26
What happens nextQuarterly monitoringNext quarterly report to Cabinet
Who it affectsBlaenau Gwent communitiesAreas receiving council capital investment
What was decided
Cabinet accepted the report and committed to providing appropriate challenge to the financial outcomes it contains. Report P20
Cabinet continued to support the appropriate financial control procedures previously agreed by Council. Report P20
Cabinet noted the budgetary control and monitoring procedures in place within the Capital Team to safeguard Authority funding. Report P20
Why
The report forms part of the Council's financial reporting framework to members, providing an overview of capital expenditure and forecasts to 31 March 2026. Report 2.2, P4, P7
It supports the Council's Forward-Looking Corporate Plan 2022 to 2027 by maintaining robust forward financial planning arrangements. Report P22, P23
Active management of overspends and underspends is needed to retain secured funding approvals and avoid loss of external funding. Report P36, P49
What happens next
Budget monitoring reports will be considered quarterly by the Corporate Leadership Team, Scrutiny Committee and Cabinet. Report 7.1, P51
The Capital Services Team will work closely with Budget Holders and the Welsh Government to maximise funding and seek re-profiling where needed. Report 6.6, P54, P39
If funding approvals are likely to be exceeded and no compensatory sources are available, Budget Holders must report implications to the Corporate Leadership Team. Report P39
The money
£32.1m Total approved schemes in the Strategic Indicative Capital Programme 2025/26 to 2029/30 Report P10
£34.7m Total approved funding for the Strategic Indicative Capital Programme Report P10
£16.0 million Total Council Resources Allocated in 2024/25 capital programme Report P14
£4.3 million Resources Utilised During 2024/25 Report P14
£11.3 million Identified Potential Slippage from 2024/25 Report P14
£11.1 million Slippage approved into 2025/26 to continue approved capital schemes Report P17
£0.2 million Released to Capital Contingency for future reallocation Report P17
£64.8 million Total agreed Capital Programme funded by grants and Council resources Report P25
£24.5 million Welsh Government Grant funding within the programme Report P26
£1.9 million Other Grant Funding within the programme Report P26
£38.4 million Council Resources, including slippage from 2024/2025 Report P26
£38.1 million Forecast capital expenditure in 2025/26, equating to breakeven against the in-year budget Report P27, P29
Options considered
Chosen: Option 1: Accept the report, provide challenge, support financial control procedures and note Capital Team monitoring arrangements. Recommended option set out in the report Report P19, P20
Rejected: Option 2: Do not accept the report Report 3.2
Implications
Financial: The overall position as at 30 June 2025 indicates a breakeven outcome against the £38.1 million in-year capital budget. Report P29, P33
Risk: Delays or inflationary pressures could lead to loss of external funding or capital reserves being committed beyond affordable levels, risking deferral or cancellation of schemes. Report P36, P37
Climate: The Capital Programme supports the Council's Decarbonisation Plan, including Re:Fit upgrades, EV charge points, WBRID retrofit work, and the procurement of Ultra Low Emission Vehicles. Report P59, P60, P61
Who and where
Communities of Blaenau Gwent receiving capital investment Report P48
Budget Holders across all Council Portfolios Report P39, P56
External funding bodies, including the Welsh Government Report P36, P54
Timeline
30 June 2025: Date of the financial position reported (Month 3, Q1) Report P4, P28, P33
17 July 2025: Council formally approved the Strategic Indicative Capital Programme 2025/26 to 2029/30 Report P10
13 October 2025: Cabinet meeting at which the report was accepted Report P2
31 March 2026: Forecast end of the 2025/26 financial year for capital expenditure Report P27
Plain English for the jargon
Slippage: Unspent capital funding carried forward from one financial year to the next, to align with project timelines and funding conditions.
Re-profiling: Agreement with a funding body to change the timing of when grant funding is spent.
WBRID: Welsh Building Retrofit and Infrastructure Development, an initiative supporting energy efficiency upgrades.
ULEV: Ultra Low Emission Vehicle.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED that the report be accepted and Option 1 was agreed as follows:- a) Cabinet Members provided appropriate challenge to the financial outcomes in the report; b) continued to support appropriate financial control procedures agreed by Council; and c) noted the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: 01.10.25 Date signed off by the Section 151 Officer: 06.10.2025
Committee: Cabinet Date of meeting: 13 October 2025 Report Subject: Capital Budget Monitoring, Forecast for 2025/2026 Financial Year (As at 30 June 2025) Portfolio Holder: Leader of the Council / Cabinet Member Corporate Resources Report Submitted by: Corporate Director of Corporate Resources
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Scrutiny Cabinet Council Other Management Leadership Holder / Audit Services Committee (please Team Team Chair Committee Committee state) 25.09.25 24/9/2025 13/10/25 (briefing)
1. Purpose of the Report 1.1 To provide Members with an overview of each Portfolio’s actual and forecast capital expenditure against funding approvals for the 2025/2026 financial year, as at 30th June 2025.
2. Scope and Background
2.1This report provides details on the following:
• Forecast financial position to 31st March 2026 across all portfolios. • Details of any significant adverse and/or favourable variances
2.2This report forms part of the Council’s financial reporting framework to members.
2.3Strategic Indicative Capital Programme 2025/26 to 2029/30
2.3.1 The Strategic Indicative Capital Programme for the period 2025/26 to 2029/30 was formally approved by Council on 17 July 2025 with: • Total approved schemes - £32.1m • Total approved funding £34.7m
2.3.2 Full details are provided in Appendix 2.
2.4Capital Programme Slippage – 2024/25 Review
2.4.1 Overview
2.4.2 At the end of each financial year, all ongoing capital schemes are reviewed to assess future funding requirements. Where appropriate, unspent funding is carried forward (‘slipped’) into the following financial year. This process ensures alignment with project timelines and funding terms and conditions. 2.4.3 2024/25 Capital Resource Utilisation • Total Council Resources Allocated: £16.0 million • Resources Utilised During 2024/25: £4.3 million • Identified Potential Slippage: £11.3 million
2.4.4 Corporate Leadership Team Decision
2.4.5 Following scrutiny of ongoing schemes and future funding needs, the Corporate Leadership Team approved the following actions:
• Slippage into 2025/26: £11.1 million To support the continuation of approved capital schemes. • Release to Capital Contingency: £0.2 million To be held for future reallocation based on emerging priorities.
2.4.6 The approved slippage ensures that capital funding remains aligned with project delivery schedules and maintains flexibility for future strategic needs.
3. Options for Recommendation 3.1 Option 1 (Recommended Option)
Members accept the report and • Provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
3.2Option 2 Members do not accept the report.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan 4.1 This report supports the Council’s Forward-Looking Corporate Plan 2022–2027 by ensuring that robust forward financial planning arrangements are in place to maintain and strengthen the Council’s financial resilience. This is a key enabler in achieving the Council’s vision of being:
“An ambitious and innovative council delivering quality services at the right time and in the right place.”.
5. Implications Against Each Option 5.1 Impact on Budget (short and long term impact)
5.1.1 The agreed Capital Programme totals approximately £64.8 million, funded through the following sources:
Welsh Government Grant: £24.5 million Other Grant Funding: £1.9 million Council Resources: £38.4 million (including slippage from 2024/2025). 5.1.2 Forecasted Expenditure – 2025/26
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.