Flood Preparedness – Progress on Improvement Actions and Monitoring
NotedExecutive1 paper
AI summaryCabinet notes progress on flood preparedness after Storm Bert review, with three of 19 improvement actions still outstanding and a scrutiny committee taking on monitoring.
Written from the decision and the officer reportPDF Pro
OutcomeNotedThree of 19 actions remain outstanding
Money£825k plus £300k yearlyDrainage works and four year capital funding
What happens nextScrutiny to monitorEconomic Development Scrutiny Committee oversees remaining actions
Who it affectsFlood risk communitiesCwm, Cwmtillery, Llanhilleth and Tredegar residents
What was decided
Cabinet accepted the report and noted progress on flood preparedness improvements arising from the Storm Bert review. Report P8
Three of the 19 improvement actions remain outstanding, and Cabinet agreed these should be monitored by the Economic Development and Environmental Management Scrutiny Committee. Report P8
Why
Storm Bert in November 2024 caused widespread disruption across Blaenau Gwent, particularly in Cwm, Cwmtillery and Llanhilleth, exposing failings in planning, operations and communications. Report 2.1
A February 2025 review identified 19 improvement recommendations covering the Flood Risk Management Plan, operational readiness, member communications, community resilience and digital reporting. Report 2.1, P29
A November 2025 supplementary review found significant improvement, and Storm Claudia in November 2025 acted as a real world test with minimal local impact. Report 2.2
What happens next
The Economic Development and Environmental Management Scrutiny Committee will monitor the three outstanding actions, with biannual progress reports continuing thereafter. Report P27
The revised Flood Risk Management Plan will be presented to Cabinet and Council for formal adoption, with the Flood Task Group's future role to be considered at that point. Report P27
Phased work on the Cwmtillery tip is scheduled for design and statutory permissions in 2026/27 with completion in 2027/28. Report 6.4
The money
£825k Secured for drainage works completed in target communities Report 5.1
£300k per annum Capital funding approved for the next four years for infrastructure improvements Report 5.1, 6.4
Options considered
Chosen: Accept the report and assign scrutiny monitoring of the three outstanding actions. Recommended by the Economic Development and Environmental Management Scrutiny Committee at its 10 February 2026 meeting Report P8
Implications
Financial: £825k secured for drainage works and £300k per annum capital funding for four years; further scenario testing, community resilience work and digital tools may need modest investment. Report 5.1
Legal: Compliance with statutory flood risk duties and Section 19 flood investigation requirements through external commissioning and regular Cabinet reporting; FRMP adoption will formalise governance. Report 5.3
Risk: Future severe weather could exceed current planning and infrastructure capacity; mitigations include a flood risk management strategy, tested standard operating procedures, training, mutual aid with Torfaen, telemetry and digital data capture. Report 5.2
Staffing: Increased standby pools and surge staffing for operational crews and the contact centre; training delivered to most elected members with outstanding sessions scheduled; extra capacity needed to develop community resilience programmes. Report 5.4
Climate: Infrastructure upgrades and nature based solutions such as wetlands pilots support climate adaptation, and better targeting via telemetry is expected to reduce unnecessary vehicle movements over time. Report 6.8, 6.4
Other: Health and safety improvements include cordon management for press at incidents where the council is lead responder, and safer plant and contractor access. Report 5.5, P29
Who and where
Residents of Cwm, Cwmtillery, Llanhilleth and Tredegar, the communities most affected by Storm Bert Report 2.1, 6.1
Communities across Blaenau Gwent who benefit from reduced flood risk and clearer communications Report 6.2
Operational crews and contact centre staff, who now have surge capacity and standby arrangements in place Report 5.4, P29
Elected members, who have received emergency response training with final sessions still to be scheduled Report 5.4, P29
Partner organisations including the British Red Cross, Torfaen through the mutual aid federation, and contractor partners for rapid plant access Report 5.2, 6.6
Timeline
November 2024: Storm Bert causes widespread disruption across Blaenau Gwent Report 2.1
March 2025: Drainage works completed at Church Street, Tredegar Report 6.1
May 2025: Training delivered to the majority of elected members Report P29
July 2025: Two drainage projects completed in Cwm and draft Flood Risk Management Plan scrutinised Report 6.1, P29
September 2025: Drainage works completed at Railway Terrace, Llanhilleth Report 6.1
October 2025: Live community emergency hub exercise held in Cwm with the British Red Cross Report 6.3, 6.6
November 2025: Storm Claudia provides a real world test of arrangements and the supplementary review is completed Report 2.2
10th February 2026: Economic Development and Environmental Management Scrutiny Committee recommends the monitoring role Report P3
13.02.2026: Report signed off by the Monitoring Officer and Section 151 Officer Report P1
23rd February 2026: Cabinet considers and accepts the report Report P2
2026/27: Cwmtillery tip design and statutory permissions phase Report 6.4
2027/28: Cwmtillery tip works scheduled for completion Report 6.4
Plain English for the jargon
FRMP: Flood Risk Management Plan
ERT: Emergency Response Team
EMP: Emergency Management Plan
IIA: Integrated Impact Assessment
SRO: Senior Responsible Owner
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
RESOLVED that the report be accepted and the progress to date be noted, with the three actions which remain outstanding, it was agreed for the Economic Development & Environmental Management Scrutiny Committee to have a role in monitoring the actions as recommended by the Committee at its meeting on 10 th February, 2026.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer:13.02.2026 Date signed off by the Section 151 Officer: 13.02.2026
Committee: Cabinet Date of meeting: 23rd February 2026 Report Subject: Flood Preparedness – Progress on Improvement Actions and Monitoring Portfolio Holder: Cabinet Member Neighbourhood and Environmental Services Report Submitted by: Joint Director Neighbourhoods and Environment
Reporting Pathway Directorate Corporate Portfolio Governance Democratic Scrutiny Cabinet Council Other Management Leadership Holder / Audit Services Committee (please Team Team Chair Committee Committee state) 10.02.26 23.02.26
1. Purpose of the Report 1.1 To provide Cabinet with a comprehensive update on progress against the 19 improvement recommendations arising from the February 2025 review into the Council’s response to Storm Bert.
2. Scope and Background
2.1Storm Bert (November 2024) caused widespread disruption across Blaenau Gwent, particularly in Cwm, Cwmtillery, and Llanhilleth. The February 2025 review, based on documentation and interviews with residents, elected members and officers, identified initial failings including: failure to apply lessons from previous incidents (e.g. Storm Dennis 2020); an out-of-date Flood Risk Management Plan (FRMP); insufficient operational readiness (slow mobilisation, limited sandbag availability, inadequate out-of-hours capacity); ineffective communications (residents unable to contact the Council; elected members lacked priority channels); and a disconnect between Council and communities.
2.2In November 2025, a supplementary review assessed progress and found significant improvements across strategic planning, operational response, infrastructure works, communications, and community resilience. Storm Claudia (November 2025, amber warning) provided a real-world test, with minimal local impact and an exemplar response, while highlighting minor areas for refinement (multi-agency overnight communications).
3. Recommendation 3.1 To consider progress to date, note that three actions remain outstanding and to agree for the Economic Development & Environmental Management Scrutiny Committee have a role in monitoring the actions as recommended by the Committee at its meeting on 10th February 2026.
3.2Endorsement by other groups: The Corporate Leadership Team and Portfolio Holder have been engaged through the supplementary review process and operational debriefs; Scrutiny’s recommendations has informed Cabinet reporting.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
The improvement programme supports statutory duties under flood risk management and civil contingencies act 2004; delivers Corporate Plan priorities on resilient, safe communities and infrastructure; and aligns with the Blaenau Gwent Well-being Plan by strengthening community resilience, prevention, and partnership working.
5. Implications Against Each Option
5.1Impact on Budget (short and long term impact) Secured: £825k for drainage works completed in target communities; £300k per annum capital funding approved for the next four years for infrastructure improvements. Additional operational costs for proactive inspections, surge staffing and telemetry are being managed within existing resources; further scenario testing, community resilience programme and digital tools may require modest investment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.